2019-26459. Kaukauna Utilities; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions  

  • Start Preamble Start Printed Page 67263

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

    a. Type of Application: New Major License.

    b. Project No.: 10674-017.

    c. Date filed: February 14, 2019.

    d. Applicant: Kaukauna Utilities.

    e. Name of Project: Kimberly Hydroelectric Project (Kimberly Project).

    f. Location: The Kimberly Project is located at the U.S. Army Corps of Engineers' (Corps) Cedars Dam on the Lower Fox River in the Village of Kimberly in Outagamie County, Wisconsin. The proposed project boundary would include 0.0225 acres of federal land.

    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).

    h. Applicant Contact: Mike Pedersen, Manager of Generation and Operations, Kaukauna Utilities, 777 Island Street, P.O. Box 1777, Kaukauna, WI 54130-7077, (902) 766-05721.

    i. FERC Contact: Colleen Corballis, (202) 502-8598, colleen.corballis@ferc.gov.

    j. Deadline for filing motions to intervene and protests, comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice.

    The Commission strongly encourages electronic filing. Please file motions to intervene and protests, comments, recommendations, terms and conditions, and prescriptions using the Commission's eFiling system at http://www.ferc.gov/​docs-filing/​efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at http://www.ferc.gov/​docs-filing/​ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P-10674-017.

    The Commission's Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    k. This application has been accepted and is ready for environmental analysis at this time.

    l. The Kimberly Project consists of: (1) A 161-foot-long, 43-foot-wide, 61-foot-high reinforced concrete and brick masonry powerhouse located at the south abutment of the Corps' Cedars Dam and containing three turbine-generator units each rated at 723 kilowatts for a total installed capacity of 2.170 megawatts; (2) a 2.4-kilovolts (kV) to 34.5-kV step-up transformer; (3) a 320-foot-long, 2.4-kV transmission line; and (4) appurtenant facilities. The project is directly connected to a 34.5-kV local distribution line, which is not part of the project. The average annual generation was 12,324,827 kilowatt-hours for the period 2011 to 2017.

    m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's website at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above.

    n. Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.

    All filings must (1) bear in all capital letters the title “PROTEST”, “MOTION TO INTERVENE”, “COMMENTS”, “REPLY COMMENTS”, “RECOMMENDATIONS,” “TERMS AND CONDITIONS,” or “PRESCRIPTIONS;” (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.

    You may also register online at http://www.ferc.gov/​docs-filing/​esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

    o. A license applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification.

    p. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate.

    Commission issues Environmental Assessment—June 2020

    Comments on Environmental Assessment—July 2020

    Start Signature

    Dated: December 3, 2019.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. 2019-26459 Filed 12-6-19; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
12/09/2019
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2019-26459
Pages:
67263-67263 (1 pages)
Docket Numbers:
Project No. 10674-017
PDF File:
2019-26459.pdf