97-3153. Project Cost and Annual Limits  

  • [Federal Register Volume 62, Number 27 (Monday, February 10, 1997)]
    [Rules and Regulations]
    [Pages 5913-5914]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-3153]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    
    18 CFR Part 157
    
    [Docket No. RM81-19-000]
    
    
    Project Cost and Annual Limits
    
    Issued February 4, 1997.
    AGENCY: Federal Energy Regulatory Commission.
    
    ACTION: Final rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Pursuant to the authority delegated by 18 CFR 375.307(e)(1), 
    the Director of the Office of Pipeline Regulation computes and 
    publishes the project cost and annual limits specified in Table I of 
    Sec. 157.208(d) and Table II of Sec. 157.215(a) for each calendar year.
    
    EFFECTIVE DATE: January 1, 1997.
    
    FOR FURTHER INFORMATION CONTACT: Michael J. McGehee, Division of 
    Pipeline Certificates, OPR (202) 208-2257.
    
    SUPPLEMENTARY INFORMATION:
    
    Publication of Project Cost Limits Under Blanket Certificates; Order of 
    the Director, OPR
    
        Section 157.208(d) of the Commission's Regulations provides for 
    project cost limits applicable to construction, acquisition, operation 
    and miscellaneous rearrangement of facilities (Table I) authorized 
    under the blanket certificate procedure (Order No. 234, 19 FERC para. 
    61,216). Section 157.215(a) specifies the calendar year dollar limit 
    which may be expended on underground storage testing and development 
    (Table II) authorized under the blanket certificate. Section 157.208(d) 
    requires that the ``limits specified in Tables I and II shall be 
    adjusted each calendar year to reflect the `GNP implicit price 
    deflator' published by the Department of Commerce for the previous 
    calendar year.''
        Pursuant to Sec. 375.307(e)(1) of the Commission's Regulations, the 
    authority for the publication of such cost limits, as adjusted as 
    inflation, is delegated to the Director of the Office of Pipeline 
    Regulation. The cost limits for calendar years 1982 through 1997, as 
    published in Table I of Sec. 157.208(d) and Table II of 
    Sec. 157.215(a), are hereby issued.
    
    [[Page 5914]]
    
        Note that these inflation adjustments are based on the Gross 
    Domestic Product (GDP) Implicit Price Deflator, rather than the Gross 
    National Product (GNP) Implicit Price Deflator, which is not yet 
    available for 1996. The Commerce Department advises that in recent 
    years the annual change has been virtually the same for both indices. 
    Further adjustments will be made, if necessary.
    
    List of Subjects in 18 CFR Part 157
    
        Natural gas.
    Kevin P. Madden,
    Director, Office of Pipeline Regulation.
        Accordingly, 18 CFR Part 157 is amended as follows:
    
    PART 157--[AMENDED]
    
        1. The authority citation for part 157 continues to read as 
    follows:
    
        Authority: 15 U.S.C. 717-717w, 3301-3432; 42 U.S.C. 7101-7352.
    
    
    Sec. 157.208  [Amended]
    
        2. Table I in Sec. 157.208(d) is revised to read as follows:
    
    
    Sec. 157.208  Construction, acquisition, operation, and miscellaneous 
    rearrangement of facilities.
    
    * * * * *
        (d) * * *
    
                                     Table I                                
    ------------------------------------------------------------------------
                                                           Limit            
                                             -------------------------------
                      Year                      Auto. proj.    Prior notice 
                                                cost limit      proj. cost  
                                                 (col. 1)     limit (col. 2)
    ------------------------------------------------------------------------
    1982....................................      $4,200,000     $12,000,000
    1983....................................       4,500,000      12,800,000
    1984....................................       4,700,000      13,300,000
    1985....................................       4,900,000      13,800,000
    1986....................................       5,100,000      14,300,000
    1987....................................       5,200,000      14,700,000
    1988....................................       5,400,000      15,100,000
    1989....................................       5,600,000      15,600,000
    1990....................................       5,800,000      16,000,000
    1991....................................       6,000,000      16,700,000
    1992....................................       6,200,000      17,300,000
    1993....................................       6,400,000      17,700,000
    1994....................................       6,600,000      18,100,000
    1995....................................       6,700,000      18,400,000
    1996....................................       6,900,000      18,800,000
    1997....................................       7,000,000      19,200,000
    ------------------------------------------------------------------------
    
    * * * * *
    
    
    Sec. 157.215  [Amended]
    
        3. Table II in Sec. 157.215(a) is revised to read as follows:
    
    
    Sec. 157.215  Underground storage testing and development.
    
        (a) * * *
    
                                    Table II                                
    ------------------------------------------------------------------------
                              Year                                 Limit    
    ------------------------------------------------------------------------
    1982....................................................      $2,700,000
    1983....................................................       2,900,000
    1984....................................................       3,000,000
    1985....................................................       3,100,000
    1986....................................................       3,200,000
    1987....................................................       3,300,000
    1988....................................................       3,400,000
    1989....................................................       3,500,000
    1990....................................................       3,600,000
    1991....................................................       3,800,000
    1992....................................................       3,900,000
    1993....................................................       4,000,000
    1994....................................................       4,100,000
    1995....................................................       4,200,000
    1996....................................................       4,300,000
    1997....................................................       4,400,000
    ------------------------------------------------------------------------
    
    * * * * *
    [FR Doc. 97-3153 Filed 2-7-97; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Effective Date:
1/1/1997
Published:
02/10/1997
Department:
Federal Energy Regulatory Commission
Entry Type:
Rule
Action:
Final rule.
Document Number:
97-3153
Dates:
January 1, 1997.
Pages:
5913-5914 (2 pages)
Docket Numbers:
Docket No. RM81-19-000
PDF File:
97-3153.pdf
CFR: (4)
18 CFR 157.215(a)
18 CFR 157.208(d)
18 CFR 157.208
18 CFR 157.215