98-3319. Approval and Promulgation of State Implementation Plan, Texas: 15% Rate-of-Progress Plan, 1990 Emission Inventory, Motor Vehicle Emission Budget, and Contingency Plan for the Beaumont/Port Arthur Ozone Nonattainment Area  

  • [Federal Register Volume 63, Number 27 (Tuesday, February 10, 1998)]
    [Rules and Regulations]
    [Pages 6659-6664]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-3319]
    
    
    -----------------------------------------------------------------------
    
    ENVIRONMENTAL PROTECTION AGENCY
    
    40 CFR Part 52
    
    [TX82-1-7336b; FRL-5962-5]
    
    
    Approval and Promulgation of State Implementation Plan, Texas: 
    15% Rate-of-Progress Plan, 1990 Emission Inventory, Motor Vehicle 
    Emission Budget, and Contingency Plan for the Beaumont/Port Arthur 
    Ozone Nonattainment Area
    
    AGENCY: Environmental Protection Agency (EPA).
    
    ACTION: Direct final rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: In this action, EPA is approving a revision to the Texas State 
    Implementation Plan (SIP) for the Beaumont/Port Arthur ozone 
    nonattainment area for the purpose of satisfying the 15% rate-of-
    progress requirements of the Clean Air Act (Act) as amended in 1990, 
    which will aid in ensuring the attainment of the National Ambient Air 
    Quality Standard (NAAQS) for ozone. The EPA is also approving the 
    area's associated Motor Vehicle Emission Budget (MVEB).
        In addition, EPA is approving revisions to the 1990 base year 
    emissions inventory and the contingency plan for this area.
        This action also replaces the proposed limited approval/limited 
    disapproval of the Beaumont/Port Arthur 15% Plan and Contingency Plan 
    published on January 29, 1996. The May 22, 1997 (62 FR 27964), limited 
    approval of the Volotile Organic Compound (VOC) control measures 
    continues in effect.
    
    DATES: This direct final rule document is effective April 13, 1998, 
    unless adverse comments are received by March 12, 1998. If the 
    effective date is delayed, timely notice will be published in the 
    Federal Register.
    
    ADDRESSES: Written comments should be addressed to Mr. Thomas H. Diggs, 
    Chief, Air Planning Section (6PD-L), at the EPA Regional Office listed 
    below. Copies of the documents relevant to this final action are 
    available for public inspection during normal business hours at the 
    following locations. Interested persons wanting to examine these 
    documents should make an appointment with the appropriate office at 
    least 24 hours before the visiting day.
        Environmental Protection Agency, Region 6, Multimedia Planning and 
    Permitting Division, 1445 Ross Avenue, suite 700, Dallas, Texas 75202-
    2733.
        Texas Natural Resource Conservation Commission (TNRCC), 12100 Park 
    35 Circle, Building F, Austin, Texas 78753.
        Documents which are incorporated by reference are available for 
    public inspection at the Air and Radiation Docket and Information 
    Center, Environmental Protection Agency, 401 M Street, SW., Washington, 
    DC 20460.
    
    FOR FURTHER INFORMATION CONTACT: Mr. Eaton R. Weiler, of the EPA Region 
    6 Air Planning Section at the above address, telephone (214) 665-7242.
    
    SUPPLEMENTARY INFORMATION:
    
    I. Background
    
    A. Clean Air Act Requirements
    
        Section 182(b)(1) of the Act as amended in 1990 requires all ozone 
    nonattainment areas classified as moderate and above to submit a SIP 
    revision by November 15, 1993, which describes, in part, how these 
    areas will achieve an actual reduction in VOC emissions of at least 15 
    percent, from a 1990 baseline, during the first six years after 
    enactment of the Act (November 15, 1996). The Act also sets limitations 
    on the creditability of certain types of reductions. Specifically, 
    states cannot take credit for reductions achieved by Federal Motor 
    Vehicle Control Program (FMVCP) measures (new car emissions standards) 
    promulgated prior to 1990, or for reductions resulting from 
    requirements to lower the Reid Vapor Pressure (RVP) of gasoline 
    promulgated prior to 1990. Furthermore, the Act does not allow credit 
    for corrections to Vehicle Inspection and Maintenance Programs (I/M), 
    or corrections to Reasonably Available Control Technology (RACT) rules 
    as these programs were required prior to 1990. Emissions and emissions 
    reductions shall be calculated on a typical weekday basis for the 
    ``peak'' 3-month ozone period (generally June through August).
        In addition, section 172(c)(9) of the Act requires that contingency 
    measures be included in the plan revision to be implemented if 
    reasonable further progress is not achieved, or if the standard is not 
    attained.
        In Texas, the Beaumont/Port Arthur ozone nonattainment area is 
    classified as ``moderate'' and is subject to the
    
    [[Page 6660]]
    
    section 182(b)(1) 15% rate-of-progress requirements. The Beaumont/Port 
    Arthur ozone nonattainment area is comprised of the following counties: 
    Orange, Jefferson, and Hardin. The 15 percent VOC emissions reduction 
    required by November 15, 1996, is defined within this document as 
    ``rate-of-progress'' (ROP). The SIP revision which delineates the plan 
    for achieving the emissions reductions is defined in this document as 
    the ``15% ROP Plan.''
    
    B. Previous 15 Percent Rate of Progress SIP revisions
    
        Texas first adopted measures for the 15% ROP Plans and the required 
    contingency measures for the four nonattainment areas of Dallas/Fort 
    Worth, Houston/Galveston, El Paso, and Beaumont/Port Arthur in two 
    phases. Phase I was submitted to EPA on November 13, 1993, and 
    contained measures achieving the bulk of the required reductions in 
    each of the nonattainment areas. Phase II was submitted May 9, 1994. 
    The Phase II submittal was to make up the shortfall in reductions not 
    achieved by the Phase I measures. The combination of the Phase I and 
    Phase II measures was ruled administratively complete by EPA on May 12, 
    1994.
        The EPA analyzed the November 13, 1993, and May 9, 1994, submittals 
    and determined that the measures included in the plan did not achieve 
    the required amount of reductions. Among other reasons, there was a 
    shortfall because the I/M program relied on reductions in the plans 
    which had subsequently been repealed by the State. On January 29, 1996 
    (61 FR 2751), EPA published a proposed limited approval/limited 
    disapproval of the 15% Plans included in the November 13, 1993, and May 
    9, 1994, submittal.
        The EPA also proposed a limited approval of the measures that were 
    included with the plans because they resulted in a strengthening of the 
    SIP. For a complete discussion of the deficiencies in the State's 
    plans, please see the January 29, 1996, Federal Register document.
    
    C. Current 15 Percent SIP Revision
    
        The Governor of Texas submitted revisions to the 15% ROP Plans for 
    Beaumont/Port Arthur, Dallas/Fort Worth, El Paso and Houston/Galveston 
    areas in a letter dated August 9, 1996. The SIP submittal also included 
    revisions to the 1990 Base Year Inventory, El Paso section 818 
    analysis, the Post 96 ROP Plan for Houston, and the Employee Commute 
    Options. In this Federal Register, EPA is taking action on only the 
    Emission Inventory, 15% ROP Plan, Contingency measures, and MVEB for 
    the Beaumont/Port Arthur area. The EPA is taking no action on the other 
    portions of the August 23, 1996, submittal in this Federal Register, 
    nor on any plans for the Dallas/Fort Worth, El Paso and Houston areas. 
    The other portions of the Governor's SIP submittal will be finalized in 
    separate Federal Register actions.
    
    II. Analysis of the Submittal
    
    A. General
    
        Texas has made the following changes to address the shortfalls that 
    were identified in the January 29, 1996, limited approval/limited 
    disapproval proposed action. First, Texas made several revisions to its 
    emissions estimates. These revisions were based on more recent 
    information or source surveys. From these studies, Texas concluded 
    that, in some instances, better estimates of emissions were available 
    based on locally derived emission factors rather than defaults based on 
    national data. Second, these same studies resulted, in some instances, 
    in lower projections of emissions in 1996 resulting in less growth to 
    be offset. Finally, by better segregating the emission points that were 
    subject to specific rules, Texas identified additional emission 
    reductions from measures in the original 15% Plan. The EPA believes 
    that the revisions to the Emission Inventory and Growth Projections 
    eliminate the shortfall identified in the January 29, 1996, limited 
    disapproval/limited approval proposed action.
    
    B. Emission Inventory Revisions
    
        The EPA approved the Texas 1990 base year inventory on November 8, 
    1994 (59 FR 55586). In the August 23, 1996 SIP submittal, Texas 
    included revisions to the approved VOC inventory. The revisions have 
    been made based on more recently available information from source 
    surveys and other methods. Much of the information was developed as 
    part of bottom-up surveys of area source categories performed as part 
    of the 1993 intensive ozone study in the Houston and Beaumont. This 
    study, called the Coastal Oxidant Assessment for Southeast Texas 
    (COAST), included a study of area source emissions. Traditional area 
    source emission inventory techniques use national or state level 
    statistics for the level of activity of a source category. For example, 
    gallons of gasoline sold statewide might be used to determine emissions 
    from gasoline stations. These emissions would be apportioned 
    geographically using a surrogate such as population. In the bottom-up 
    approach, surveys of actual facilities were used to determine emission 
    levels. In addition to the data collected from bottom-up surveys, other 
    improvements were made to the 1990 inventory. A brief discussion of the 
    changes made to the inventory follows.
    1. Other Product Coatings, High Performance Maintenance and Other 
    Special Purpose Coatings
        These categories are all surface coating categories that were 
    estimated for the 1990 inventory using per capita emission factors 
    provided by EPA. The per capita factors were developed from national 
    level estimates of usage of a product divided by the 1989 population. 
    The documentation of the coatings and emissions covered by these 
    categories was not initially available. The TNRCC, with EPA approval, 
    removed these categories from the 1993 periodic emissions inventory. 
    After further study, documentation of the specific categories and 
    coatings was identified and the 1990 inventory has been adjusted 
    appropriately. Once the categories had been accurately identified, 
    overlap with the point source inventory could be accounted for and an 
    improved area source estimate was obtained.
    2. Marine Vessel Loading Losses
        Area source emissions in this category were based on estimates of 
    the total amount of VOCs loaded at Texas ports. Texas determined that 
    individual point sources had under reported emissions from this 
    category. When the revised point source emissions are considered, it 
    was determined that the bulk of the emissions in the Beaumont area were 
    covered in the point source emission inventory. Therefore, the area 
    source estimate could be reduced.
    3. Surface Cleaning
        A contractor performed a bottom-up survey of this category. This 
    survey was later expanded by TNRCC staff. The results of the survey 
    indicated that the national default estimate of emissions for this 
    category should be revised for the nonattainment areas in Texas.
    4. Architectural Coatings
        Texas revised emissions estimate by using more recent information 
    from the National Paint and Coatings Association combined with data 
    from surveys on thinner usage.
    5. Automobile Refinishing
        Texas used more recent information from the National Paint and 
    Coatings
    
    [[Page 6661]]
    
    Association and source surveys to revise the emission estimates for 
    this category. In addition, using data from the Department of Commerce 
    on paint shipments, Texas projected a substantial decrease in emissions 
    between 1990 and 1994.
    6. Sheet, Strip and Coil
        This category was estimated for the 1990 emission factor of 1.5 
    tons/employee. The number of employees related to this industry was 
    obtained from the County Business Patterns for Standard Industrial 
    Classification (SIC) code 3479. This SIC code includes many businesses 
    not engaged in coil coating operations. A list of companies involved in 
    coil coating operations was obtained from the national coil coaters 
    association. It was determined that all of the companies involved in 
    these operations were outside the nonattainment area or were reporting 
    their emissions in the point source inventory. Therefore, including 
    their emissions in the area source emissions would be double counting. 
    Therefore, the area source emissions were removed from the inventory.
    7. Vessels With Outboards
        A telephone survey of pleasure craft owners in the Beaumont/Port 
    Arthur area was conducted. The survey showed that 62 percent of boat 
    usage occurs on weekends rather than on weekdays. Previous emission 
    estimates had allocated pleasure craft emissions equally to each day of 
    the week. It is important to know when emissions occur in developing 
    control strategies. In this case, according to the EPA guidance, 
    emissions are to be reduced from their 1990 summer time weekday levels. 
    Therefore, Texas reduced the expected weekday emissions based on the 
    results of the survey. A similar adjustment had previously been made to 
    the Dallas/Fort Worth and Houston/Galveston inventories.
    8. Generators <50 horsepower="" as="" part="" of="" the="" coast="" project,="" local="" area-specific="" construction="" and="" recreational="" area="" information="" and="" more="" current="" information="" about="" horsepower="" distributions="" and="" equipment/populations="" were="" utilized="" to="" obtain="" a="" more="" refined="" estimate="" of="" emissions="" in="" this="" category.="" 9.="" residential="" lawnmowers="" similar="" to="" the="" survey="" performed="" of="" recreational="" boat="" users,="" a="" survey="" of="" homeowners="" was="" performed="" to="" determine="" when="" they="" actually="" cut="" their="" lawns.="" fifty-nine="" percent="" of="" the="" surveyed="" respondents="" reported="" that="" they="" cut="" their="" lawns="" on="" the="" weekends.="" texas="" reallocated="" the="" emissions="" based="" on="" the="" results="" of="" the="" survey.="" 10.="" 1994="" quality="" assurance="" efforts="" during="" 1994,="" the="" tnrcc="" completed="" a="" thorough="" evaluation="" of="" the="" 1990="" point="" source="" inventory="" and="" discovered="" that="" emissions="" from="" facilities="" in="" several="" sic="" codes="" were="" misplaced="" under="" the="" wrong="" emissions="" category.="" this="" effort="" resulted="" in="" significant="" changes="" to="" some="" emissions="" categories.="" the="" realignment="" of="" emissions="" did="" not="" affect="" the="" total="" emissions.="" the="" realignment="" of="" emissions="" did="" have="" the="" effect="" of="" increasing="" the="" amount="" of="" reductions="" that="" were="" expected="" for="" certain="" control="" measures="" and="" decreasing="" the="" amount="" of="" emission="" reductions="" expected="" from="" other="" control="" measures.="" the="" epa="" is="" proposing="" to="" approve="" these="" revisions="" to="" the="" 1990="" base="" year="" voc="" inventory="" for="" the="" beaumont/port="" arthur="" area.="" the="" original="" biogenic="" emissions="" are="" unchanged.="" a="" summary="" of="" the="" revised="" 1990="" emissions="" inventory="" for="" the="" beaumont/port="" arthur="" area="" is="" included="" in="" table="" 1.="" table="" 1.--1990="" base="" year="" emissions="" inventory="" ------------------------------------------------------------------------="" beaumont="" port="" arthur="" -------------------------------------------------------------------------="" point="" area="" on-road="" non-road="" total="" ------------------------------------------------------------------------="" 245.35.......="" 30.63="" 19.11="" 18.44="" 313.53="" ------------------------------------------------------------------------="" c.="" calculation="" of="" the="" 1996="" target="" level="" of="" emissions="" texas="" subtracted="" the="" noncreditable="" reductions="" from="" the="" fmvcp="" and="" rvp="" program="" from="" the="" 1990="" emissions="" inventory.="" this="" subtraction="" results="" in="" the="" 1990="" adjusted="" inventory.="" the="" total="" required="" emission="" reduction="" required="" to="" meet="" the="" 15%="" rop="" plan="" requirement="" equals="" the="" sum="" of="" 15="" percent="" of="" the="" adjusted="" inventory,="" plus="" reductions="" to="" offset="" any="" growth="" that="" takes="" place="" between="" 1990="" and="" 1996,="" plus="" any="" reductions="" that="" result="" from="" corrections="" to="" the="" i/m="" or="" voc="" ract="" rules.="" table="" 2="" summarizes="" the="" calculations="" for="" the="" beaumont/port="" arthur="" area.="" table="" 2:="" calculation="" of="" required="" reductions="" (tons/day)="" ------------------------------------------------------------------------="" beaumont="" port="" arthur="" ------------------------------------------------------------------------="" 1990="" emission="" inventory.......................................="" 323.77="" 1990="" adjusted="" emission="" inventory..............................="" 313.53="" 15%="" of="" adjusted...............................................="" 47.03="" ract="" and="" i/m="" correction.......................................="" 4.28="" 1996="" target...................................................="" 262.22="" 1996="" projection="" \1\...........................................="" 320.01="" required="" reduction............................................="" 57.79="" ------------------------------------------------------------------------="" \1\="" 1996="" forecasted="" emissions="" with="" growth="" and="" pre-1990="" controls.="" d.="" projections="" of="" growth="" as="" can="" be="" seen="" from="" the="" calculations="" in="" table="" 2,="" an="" important="" component="" of="" calculating="" the="" required="" emission="" reductions="" is="" to="" project="" the="" amount="" of="" growth="" in="" emissions="" that="" is="" expected="" between="" 1990="" and="" 1996.="" since="" the="" 1996="" emissions="" are="" related="" to="" the="" 1990="" emissions,="" the="" changes="" in="" the="" 1990="" emission="" inventory="" resulted="" in="" changes="" to="" the="" 1996="" projections.="" in="" addition,="" as="" discussed="" previously,="" texas="" has="" projected="" reductions="" in="" the="" emissions="" from="" surface="" cleaning="" and="" auto="" refinishing="" emissions="" from="" 1990="" levels.="" e.="" deficiencies="" identified="" in="" the="" january="" 29,="" 1996="" federal="" register="" in="" the="" january="" 29,="" 1996="" federal="" register,="" epa="" identified="" several="" areas="" where="" it="" was="" believed="" that="" texas="" had="" projected="" too="" much="" emissions="" reduction="" for="" particular="" control="" measures.="" the="" epa="" has="" reviewed="" the="" august="" 9,="" 1996,="" sip="" revision="" and="" believes="" that="" it="" addresses="" the="" previously="" identified="" concerns.="" a="" brief="" discussion="" of="" the="" previously="" identified="" concerns="" follows="" below.="" 1.="" architectural="" coatings="" texas="" projected="" emission="" reductions="" for="" this="" category="" based="" on="" past="" epa="" guidance.="" the="" guidance,="" however,="" was="" changed="" in="" a="" memorandum="" dated="" march="" 22,="" 1995="" (credit="" for="" the="" 15="" percent="" rate-of-progress="" plans="" for="" reductions="" from="" the="" architectural="" and="" industrial="" maintenance="" (aim)="" coating="" rule).="" the="" [[page="" 6662]]="" august,="" 1996="" sip="" revision="" revises="" the="" projected="" emissions="" reduction="" estimate="" based="" on="" the="" more="" recent="" guidance.="" projected="" emissions="" reductions="" from="" the="" aim="" rule="" are="" based="" on="" the="" aim="" rule="" proposed="" by="" epa="" on="" june="" 25,="" 1995="" which="" expected="" compliance="" by="" april,="" 1997.="" subsequently,="" epa="" was="" sued="" over="" this="" proposed="" national="" rule="" and="" has="" negotiated="" a="" compliance="" date="" of="" no="" earlier="" than="" january="" 1,="" 1998.="" the="" previous="" guidance="" allowed="" states="" to="" take="" emission="" reduction="" credit="" for="" the="" aim="" rule="" even="" though="" the="" reductions="" were="" not="" expected="" to="" occur="" until="" april="" 1997.="" the="" epa="" believes="" that="" even="" though="" the="" compliance="" date="" has="" been="" pushed="" back,="" the="" projected="" emissions="" reduction="" from="" the="" national="" aim="" rule="" are="" creditable="" in="" state="" 15%="" plans.="" 2.="" acetone="" substitution="" texas="" had="" projected="" emissions="" reductions="" for="" the="" rules="" to="" regulate="" the="" cultured="" (synthetic)="" marble="" and="" fiber="" reinforced="" plastic="" operations.="" the="" epa,="" however,="" has="" added="" acetone="" to="" the="" list="" of="" non-="" reactive="" substances.="" texas,="" in="" the="" august,="" 1996="" submittal,="" removed="" emissions="" reduction="" credit="" for="" these="" rules.="" 3.="" vehicle="" inspection="" and="" maintenance="" (i/m)="" under="" the="" federal="" i/m="" flexibility="" amendments="" promulgated="" september="" 18,="" 1995,="" urbanized="" areas="" with="" a="" population="" of="" less="" than="" 200,000="" for="" 1990="" are="" not="" mandated="" to="" participate="" in="" the="" vehicle="" i/m="" program.="" the="" state="" of="" texas="" has="" elected="" not="" to="" implement="" a="" vehicle="" i/m="" program="" in="" the="" beaumont/port="" arthur="" nonattainment="" area.="" for="" a="" complete="" discussion="" of="" the="" control="" measures="" considered="" please="" see="" the="" technical="" support="" document="" for="" this="" action.="" table="" 3="" summarizes="" the="" control="" measures="" and="" their="" projected="" emissions="" reductions="" used="" to="" achieve="" the="" 15="" percent="" target.="" table="" 3.--summary="" emission="" reductions="" for="" beaumont/port="" arthur="" ------------------------------------------------------------------------="" ------------------------------------------------------------------------="" required="" reduction="" (tons/day).................................="" 57.79="" ract="" catchup................................................="" 9.88="" tsdf........................................................="" 0.01="" vehicle="" refueling="" (stage="" ii)................................="" 1.96="" general="" vent="" gas............................................="" 11.75="" benzene="" neshaps.............................................="" 0.28="" fmvcp="" tier="" i................................................="" 0.21="" vessel="" cleaning.............................................="" 0.02="" fugitives...................................................="" 17.46="" re="" floating="" roof="" tank.......................................="" 25.62="" re="" improvements="" (excluding="" floating="" roof="" tank)..............="" 5.04="" gas="" utility="" engines.........................................="" 0.95="" stage="" i.....................................................="" 1.49="" architectural="" coatings......................................="" 0.45="" consumer/commercial="" products................................="" 0.38="" traffic="" markings............................................="" 0.05="" high="" performance="" maintenance................................="" 0.05="" other="" special="" purpose.......................................="" 0.12="" total="" estimated="" reductions..............................="" 75.71="" ------------------------------------------------------------------------="" f.="" motor="" vehicle="" emissions="" budgets="" the="" clean="" air="" act,="" section="" 176(c),="" and="" the="" transportation="" conformity="" rule="" require="" the="" states="" to="" establish="" mvebs="" in="" any="" control="" strategy="" sip="" that="" is="" submitted="" for="" attainment="" and="" maintenance="" of="" the="" naaqs.="" the="" state="" of="" texas="" has="" established="" a="" mveb="" for="" voc="" for="" the="" beaumont/port="" arthur="" area.="" the="" epa="" is="" proposing="" to="" approve="" the="" following="" mveb="" in="" table="" 4:="" table="" 4.--1996="" voc="" motor="" vehicle="" emissions="" budget="" ------------------------------------------------------------------------="" voc="" area="" (tons/="" day)="" ------------------------------------------------------------------------="" beaumont/port="" arthur..........................................="" 21.66="" ------------------------------------------------------------------------="" g.="" contingency="" measures="" ozone="" areas="" classified="" as="" moderate="" or="" above="" must="" include="" in="" their="" submittals,="" under="" section="" 172(c)(9)="" of="" the="" act,="" contingency="" measures="" to="" be="" implemented="" if="" reasonable="" further="" progress="" (rfp)="" is="" not="" achieved="" or="" if="" the="" standard="" is="" not="" attained="" by="" the="" applicable="" date.="" the="" general="" preamble="" to="" title="" i="" (57="" fr="" 13498)="" states="" that="" the="" contingency="" measures="" should,="" at="" a="" minimum,="" ensure="" that="" an="" appropriate="" level="" of="" emissions="" reduction="" progress="" continues="" to="" be="" made="" if="" attainment="" or="" rfp="" is="" not="" achieved="" and="" additional="" planning="" by="" the="" state="" is="" needed.="" therefore,="" the="" epa="" interprets="" the="" act="" to="" require="" states="" with="" moderate="" and="" above="" ozone="" nonattainment="" areas="" to="" include="" sufficient="" contingency="" measures="" in="" the="" november="" 1993="" submittal,="" so="" that="" upon="" implementation="" of="" such="" measures,="" additional="" emissions="" reductions="" of="" up="" to="" three="" percent="" of="" the="" adjusted="" base="" year="" inventory="" (or="" a="" lesser="" percentage="" that="" will="" make="" up="" the="" identified="" shortfall)="" would="" be="" achieved="" in="" the="" year="" after="" the="" failure="" has="" been="" identified.="" states="" must="" show="" that="" their="" contingency="" measures="" can="" be="" implemented="" with="" minimal="" further="" action="" on="" their="" part="" and="" with="" no="" additional="" rulemaking="" actions="" such="" as="" public="" hearings="" or="" legislative="" review="" .="" iii.="" analysis="" of="" specific="" contingency="" measures="" the="" following="" is="" a="" discussion="" of="" each="" of="" the="" contingency="" measures="" that="" have="" been="" included="" in="" the="" sip="" submittals="" and="" an="" analysis="" of="" their="" acceptableness.="" a.="" gas="" utility="" engines="" texas="" has="" projected="" emission="" reductions="" that="" will="" occur="" from="" the="" small="" engine="" rule="" in="" the="" year="" following="" the="" required="" milestone="" demonstration="" or="" 1997.="" the="" epa="" believes="" that="" these="" reductions="" have="" been="" quantified="" appropriately.="" b.="" tier="" i="" additional="" reductions="" are="" projected="" for="" tier="" i.="" the="" epa="" agrees="" with="" these="" reduction="" estimates.="" c.="" excess="" reductions="" excess="" reductions="" from="" measures="" in="" place="" are="" sufficient="" to="" ensure="" that="" the="" contingency="" measure="" target="" of="" three="" percent="" is="" met.="" these="" emission="" reductions="" are="" in="" excess="" of="" what="" is="" required="" for="" the="" area="" to="" achieve="" by="" november="" 15,="" 1996.="" if="" texas="" has="" to="" rely="" on="" these="" measures="" for="" contingency="" measures="" or="" for="" future="" plans="" then="" the="" state="" will="" have="" one="" year="" to="" backfill="" the="" contingency="" plan.="" table="" 7.--summary="" of="" contingency="" measures:="" beaumont/port="" arthur="" (tons/="" day)="" ------------------------------------------------------------------------="" ------------------------------------------------------------------------="" required="" contingency..........................................="" 9.41="" creditable="" contingency="" reductions:="" gas="" utility="" engines.........................................="" 0.08="" tier="" i......................................................="" 0.69="" excess="" from="" existing="" measures...............................="" 17.92="" total...................................................="" 18.69="" ------------------------------------------------------------------------="" iv.="" final="" action="" the="" epa="" has="" evaluated="" the="" emissions="" inventory,="" 15%="" plans="" and="" contingency="" measures="" submitted="" as="" part="" of="" the="" august="" 9,="" 1996,="" sip="" revision="" for="" texas.="" the="" epa="" is="" approving="" the="" revisions="" to="" the="" 1990="" base="" year="" inventory,="" the="" 15%="" plan,="" and="" contingency="" plan="" for="" the="" beaumont/="" port="" arthur="" area="" without="" prior="" proposal="" because="" the="" agency="" views="" this="" as="" a="" noncontroversial="" amendment="" and="" anticipates="" no="" adverse="" comments.="" however,="" in="" a="" separate="" document="" in="" this="" federal="" register="" publication,="" epa="" is="" proposing="" to="" approve="" this="" action="" should="" adverse="" or="" critical="" comments="" be="" filed.="" this="" action="" will="" be="" effective="" april="" 13,="" 1998,="" unless="" by="" march="" 12,="" 1998,="" adverse="" comments="" are="" received.="" if="" epa="" receives="" such="" comments,="" this="" action="" will="" be="" withdrawn="" before="" the="" effective="" date="" by="" publishing="" a="" [[page="" 6663]]="" subsequent="" document="" that="" will="" withdraw="" the="" final="" action.="" all="" public="" comments="" received="" will="" then="" be="" addressed="" in="" a="" subsequent="" final="" rule="" based="" on="" proposed="" action.="" the="" epa="" will="" not="" institute="" a="" second="" comment="" period.="" any="" parties="" interested="" in="" commenting="" on="" this="" action="" should="" do="" so="" at="" this="" time.="" if="" no="" such="" comments="" are="" received,="" the="" public="" is="" advised="" that="" this="" action="" will="" be="" effective="" april="" 13,="" 1998.="" nothing="" in="" this="" action="" should="" be="" construed="" as="" permitting="" or="" allowing="" or="" establishing="" a="" precedent="" for="" any="" future="" request="" for="" revision="" to="" any="" sip.="" each="" request="" for="" revision="" to="" the="" sip="" shall="" be="" considered="" separately="" in="" light="" of="" specific="" technical,="" economic,="" and="" environmental="" factors="" and="" in="" relation="" to="" relevant="" statutory="" and="" regulatory="" requirements.="" v.="" administrative="" requirements="" a.="" executive="" order="" (e.o.)="" 12866="" the="" office="" of="" management="" and="" budget="" has="" exempted="" this="" regulatory="" action="" from="" e.o.="" 12866="" review.="" b.="" regulatory="" flexibility="" act="" under="" the="" regulatory="" flexibility="" act,="" 5="" u.s.c.="" 600="" et="" seq.,="" epa="" must="" prepare="" a="" regulatory="" flexibility="" analysis="" assessing="" the="" impact="" of="" any="" proposed="" or="" final="" rule="" on="" small="" entities.="" see="" 5="" u.s.c.="" 603="" and="" 604.="" alternatively,="" epa="" may="" certify="" that="" the="" rule="" will="" not="" have="" a="" significant="" impact="" on="" a="" substantial="" number="" of="" small="" entities.="" small="" entities="" include="" small="" businesses,="" small="" not-for-profit="" enterprises,="" and="" government="" entities="" with="" jurisdiction="" over="" populations="" of="" less="" than="" 50,000.="" the="" sip="" approvals="" under="" section="" 110="" and="" subchapter="" i,="" part="" d="" of="" the="" act="" do="" not="" create="" any="" new="" requirements="" but="" simply="" approve="" requirements="" that="" the="" state="" is="" already="" imposing.="" therefore,="" because="" the="" federal="" sip="" approval="" does="" not="" impose="" any="" new="" requirements,="" i="" certify="" that="" it="" does="" not="" have="" a="" significant="" impact="" on="" any="" small="" entities="" affected.="" moreover,="" due="" to="" the="" nature="" of="" the="" federal-state="" relationship="" under="" the="" act,="" preparation="" of="" a="" flexibility="" analysis="" would="" constitute="" federal="" inquiry="" into="" the="" economic="" reasonableness="" of="" state="" action.="" the="" act="" forbids="" epa="" to="" base="" its="" actions="" concerning="" sips="" on="" such="" grounds.="" see="" union="" electric="" co.="" v.="" u.s.="" epa,="" 427="" u.s.="" 246,="" 255-66="" (1976);="" 42="" u.s.c.="" 7410(a)(2).="" c.="" unfunded="" mandates="" under="" section="" 202="" of="" the="" unfunded="" mandates="" reform="" act="" of="" 1995,="" signed="" into="" law="" on="" march="" 22,="" 1995,="" epa="" must="" prepare="" a="" budgetary="" impact="" statement="" to="" accompany="" any="" proposed="" or="" final="" rule="" that="" includes="" a="" federal="" mandate="" that="" may="" result="" in="" estimated="" costs="" to="" state,="" local,="" or="" tribal="" governments="" in="" the="" aggregate;="" or="" to="" private="" sector,="" of="" $100="" million="" or="" more.="" under="" section="" 205,="" epa="" must="" select="" the="" most="" cost-="" effective="" and="" least="" burdensome="" alternative="" that="" achieves="" the="" objectives="" of="" the="" rule="" and="" is="" consistent="" with="" statutory="" requirements.="" section="" 203="" requires="" epa="" to="" establish="" a="" plan="" for="" informing="" and="" advising="" any="" small="" governments="" that="" may="" be="" significantly="" or="" uniquely="" impacted="" by="" the="" rule.="" the="" epa="" has="" determined="" that="" this="" approval="" action="" proposed="" does="" not="" include="" a="" federal="" mandate="" that="" may="" result="" in="" estimated="" costs="" of="" $100="" million="" or="" more="" to="" either="" state,="" local,="" or="" tribal="" governments="" in="" the="" aggregate,="" or="" to="" the="" private="" sector.="" this="" federal="" action="" approves="" preexisting="" requirements="" under="" state="" or="" local="" law,="" and="" imposes="" no="" new="" federal="" requirements.="" accordingly,="" no="" additional="" costs="" to="" state,="" local,="" or="" tribal="" governments,="" or="" to="" the="" private="" sector,="" result="" from="" this="" action.="" d.="" submission="" to="" congress="" and="" the="" general="" accounting="" office="" under="" 5="" u.s.c.="" 801(a)(1)(a)="" as="" added="" by="" the="" small="" business="" regulatory="" enforcement="" fairness="" act="" of="" 1996,="" epa="" submitted="" a="" report="" containing="" this="" rule="" and="" other="" required="" information="" to="" the="" u.s.="" senate,="" the="" u.s.="" house="" of="" representatives="" and="" the="" comptroller="" general="" of="" the="" general="" accounting="" office="" prior="" to="" publication="" of="" this="" rule="" in="" today's="" federal="" register.="" this="" rule="" is="" not="" a="" ``major="" rule''="" as="" defined="" by="" 5="" u.s.c.="" 804(2).="" e.="" petitions="" for="" judicial="" review="" under="" section="" 307(b)(1)="" of="" the="" act,="" petitions="" for="" judicial="" review="" of="" this="" action="" must="" be="" filed="" in="" the="" united="" states="" court="" of="" appeals="" for="" the="" appropriate="" circuit="" by="" april="" 13,="" 1998.="" filing="" a="" petition="" for="" reconsideration="" by="" the="" administrator="" of="" this="" final="" rule="" does="" not="" affect="" the="" finality="" of="" this="" rule="" for="" the="" purposes="" of="" judicial="" review="" nor="" does="" it="" extend="" the="" time="" within="" which="" a="" petition="" for="" judicial="" review="" may="" be="" filed,="" and="" shall="" not="" postpone="" the="" effectiveness="" of="" such="" rule="" or="" action.="" this="" action="" may="" not="" be="" challenged="" later="" in="" proceedings="" to="" enforce="" its="" requirements.="" see="" section="" 307(b)(2)="" of="" the="" act.="" list="" of="" subjects="" in="" 40="" cfr="" part="" 52="" environmental="" protection,="" air="" pollution="" control,="" carbon="" monoxide,="" hydrocarbons,="" incorporation="" by="" reference,="" intergovernmental="" relations,="" lead,="" nitrogen="" dioxide,="" ozone,="" particulate="" matter,="" reporting="" and="" recordkeeping="" requirements,="" sulfur="" oxides,="" volatile="" organic="" compounds.="" note:="" incorporation="" by="" reference="" of="" the="" sip="" for="" the="" state="" of="" texas="" was="" approved="" by="" the="" director="" of="" the="" federal="" register="" on="" july="" 1,="" 1982.="" dated:="" january="" 22,="" 1998.="" lynda="" f.="" carroll,="" acting="" regional="" administrator,="" region="" 6.="" part="" 52,="" chapter="" i,="" title="" 40="" of="" the="" code="" of="" federal="" regulations="" is="" amended="" as="" follows:="" part="" 52--[amended]="" 1.="" the="" authority="" citation="" for="" part="" 52="" continues="" to="" read="" as="" follows:="" authority:="" 42="" u.s.c.="" 7401="" et="" seq.="" subpart="" ss--texas="" 2.="" section="" 52.2270="" is="" amended="" by="" adding="" paragraph="" (c)(107)="" to="" read="" as="" follows:="" sec.="" 52.2270="" identification="" of="" plan.="" *="" *="" *="" *="" *="" (c)="" *="" *="" *="" (107)="" a="" revision="" to="" the="" texas="" state="" implementation="" plan="" addressing="" the="" 15%="" rate-of-progress="" plan="" requirements="" for="" the="" beaumont/port="" arthur="" ozone="" nonattainment="" area="" was="" submitted="" by="" a="" cover="" letter="" from="" governor="" george="" bush="" dated="" august="" 9,="" 1996.="" this="" revision="" will="" aid="" in="" ensuring="" that="" reasonable="" further="" progress="" is="" made="" towards="" attaining="" the="" national="" ambient="" air="" quality="" standard="" (naaqs)="" for="" ozone="" in="" the="" beaumont/port="" arthur="" area.="" this="" submittal="" also="" contained="" revisions="" to="" the="" 1990="" base="" year="" emissions="" inventory,="" motor="" vehicle="" emission="" budget,="" and="" contingency="" plan="" for="" the="" beaumont/port="" arthur="" area.="" (i)="" incorporation="" by="" reference.="" texas="" natural="" resource="" conservation="" commission="" (tnrcc)="" order="" adopting="" amendments="" to="" the="" state="" implementation="" plan;="" docket="" number="" 96-0465-sip,="" issued="" july="" 31,="" 1996.="" (ii)="" additional="" material.="" (a)="" tnrcc="" certification="" letter="" dated="" july="" 24,="" 1996,="" and="" signed="" by="" gloria="" vasquez,="" chief="" clerk,="" tnrcc.="" (b)="" the="" sip="" narrative="" plan="" and="" tables="" entitled,="" ``revisions="" to="" the="" state="" implementation="" plan="" for="" the="" control="" of="" ozone="" air="" pollution,''="" as="" it="" applies="" to="" the="" beaumont/port="" arthur="" area="" dated="" july="" 24,="" 1996.="" 3.="" section="" 52.2309="" is="" amended="" by="" adding="" paragraph="" (d)="" to="" read="" as="" follows:="" sec.="" 52.2309="" emissions="" inventories.="" *="" *="" *="" *="" *="" (d)="" the="" texas="" natural="" resource="" conservation="" commission="" submitted="" state="" implementation="" plan="" revisions="" to="" the="" 1990="" base="" year="" emission="" inventory="" [[page="" 6664]]="" for="" the="" beaumont/port="" arthur="" area="" with="" a="" cover="" letter="" from="" the="" governor="" of="" texas="" dated="" august="" 9,="" 1996.="" [fr="" doc.="" 98-3319="" filed="" 2-9-98;="" 8:45="" am]="" billing="" code="" 6560-50-p="">

Document Information

Effective Date:
4/13/1998
Published:
02/10/1998
Department:
Environmental Protection Agency
Entry Type:
Rule
Action:
Direct final rule.
Document Number:
98-3319
Dates:
This direct final rule document is effective April 13, 1998, unless adverse comments are received by March 12, 1998. If the effective date is delayed, timely notice will be published in the Federal Register.
Pages:
6659-6664 (6 pages)
Docket Numbers:
TX82-1-7336b, FRL-5962-5
PDF File:
98-3319.pdf
CFR: (2)
40 CFR 52.2270
40 CFR 52.2309