99-3605. Magnetic Levitation Transportation Technology Development Program  

  • [Federal Register Volume 64, Number 29 (Friday, February 12, 1999)]
    [Rules and Regulations]
    [Pages 7133-7134]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-3605]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF TRANSPORTATION
    
    Federal Railroad Administration
    
    49 CFR Part 268
    
    [FRA Docket No. FRA-95-4545; Notice No. 2]
    RIN 2130-AB29
    
    
    Magnetic Levitation Transportation Technology Development Program
    
    AGENCY: Federal Railroad Administration (FRA), Department of 
    Transportation (DOT).
    
    ACTION: Amendment to the interim final rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: FRA published an Interim Final Rule with request for comments 
    on October 13, 1998 (63 FR 54600), implementing the Magnetic Levitation 
    Technology Deployment Program. The Interim Final Rule established a 
    deadline of December 31, 1998, for the submission of application 
    packages for preconstruction planning assistance, and set out a 
    schedule for other actions flowing from the submission of application 
    packages. This Amendment to the Interim Final Rule extends the deadline 
    for the submission of application packages to February 15, 1999, and 
    makes other adjustments to various dates which flow from that extension 
    of time.
    
    EFFECTIVE DATE: This Amendment to the Interim Final Rule is effective 
    February 12, 1999.
    
    FOR FURTHER INFORMATION CONTACT: Neil E. Moyer, Chief--Program 
    Development Division, FRA, 1120 Vermont Ave., NW, Washington, DC 20590 
    (telephone 202-493-6365; E-mail address: Neil.Moyer@fra.dot.gov), or 
    Gareth Rosenau, Attorney, Office of Chief Counsel, FRA, 1120 Vermont 
    Ave., NW, Mailstop 10, Washington, DC 20590 (telephone 202-493-6054; E-
    mail address: Gareth.Rosenau@fra.dot.gov).
    
    SUPPLEMENTARY INFORMATION: Citing the extensive and comprehensive 
    information required to be submitted, several potential applicants 
    expressed an interest in an extension of the deadline for receipt of 
    applications for maglev preconstruction planning grants. In response, 
    on December 22, 1998, FRA extended the deadline from December 31, 1998, 
    to February 15, 1999. All known potential applicants were contacted by 
    telephone and were notified of the change. A memorandum advising all 
    known interested parties of the change was also mailed at the same 
    time.
        Formal comments to the docket concerning the Interim Final Rule 
    will be discussed upon publication of the Final Rule. None of the 
    formal comments to the docket concerned the extension of the deadline 
    for maglev preconstruction planning grants, or other dates, being 
    modified by this Amendment No. 1.
    
    Regulatory Analyses and Notices
    
        This Amendment to the Interim Final Rule merely extends the 
    deadline for application packages for preconstruction planning 
    assistance from December 31, 1998, to February 15, 1999, and adds one 
    month to all subsequent milestones listed in Sec. 268.3. There are no 
    other changes to the Interim Final Rule. Declarations with respect to 
    various regulatory requirements were contained in the Interim Final 
    Rule. By this Amendment, those declarations with respect to various 
    regulatory requirements are incorporated herein by reference, and it is 
    stated that there are no other modifications required to those 
    declarations by virtue of the action taken in this Amendment.
    
    List of subjects in 49 CFR Part 268
    
        Grant programs-transportation, High speed ground transportation, 
    Maglev, Magnetic levitation.
    
    The Rule
    
        In consideration of the foregoing, FRA amends part 268 title 49 of 
    the Code of Federal Regulations as set forth below:
    
    PART 268--[AMENDED]
    
        1. The authority citation for part 268 continues to read as 
    follows:
    
    
    [[Page 7134]]
    
    
        Authority: 49 U.S.C. 322, 23 U.S.C. 322; 49 CFR 1.49.
    
        2. Section 268.3 is amended by revising paragraphs (b), (c), (d), 
    (e), and (f) to read as follows:
    
    
    Sec. 268.3  Different phases of the Maglev Deployment Program.
    
    * * * * *
        (b) Phase I--Competition for Planning Grants (Early October 1998-
    April 30, 1999).
        (1) Description. In Phase I, States will apply for funds for 
    preconstruction planning activities. As required by Sec. 268.13, 
    applications must be filed with FRA by February 15, 1999. FRA will 
    select one or more projects to receive preconstruction planning 
    financial assistance awarded under this part to perform Phase II of the 
    Maglev Deployment Program.
        (2) Timing of Major Milestones.
        (i) February 15, 1999--Planning grant applications due.
        (ii) March 31, 1999--FRA selects grantees for planning grants.
        (iii) April 30, 1999--FRA awards planning grants for the conduct of 
    activities listed in Phase II.
        (c) Phase II--Project Description Development (May 1, 1999-April 
    30, 2000).
        (1) Description. In Phase II, each grant recipients will prepare 
    and submit to FRA a project description and supporting preconstruction 
    planning reports and an EA. Supporting reports may include demand and 
    revenue analyses, project specification, cost estimates, scheduling, 
    financial studies, and other information in support of the project 
    description. FRA will use this information in reaching a decision on 
    which project to select for final engineering and construction 
    financing. In addition, after completion of the EA, each grant 
    recipient will initiate activities aimed at preparing a site-specific 
    draft EIS. FRA will initiate documentation of environmental factors 
    considered in the project selection process.
        (2) Timing of Major Milestones.
        (i) December 31, 1999--Deadline for submission of appropriate EA 
    needed by FRA for the selection of one project under Phase III.
        (ii) April 30, 2000--Deadline for submission of project 
    descriptions and any related supporting reports needed by FRA for 
    project selection.
        (d) Phase III--Project Selection Process (May 1, 2000-August 31, 
    2000).
        (1) Description. FRA will evaluate the information provided by the 
    grant recipients under Phase II and will select one project for final 
    design, engineering, and construction funding. Recipients of assistance 
    will progress work on site-specific EISs.
        (2) Timing of Major Milestones. August 31, 2000--FRA selects the 
    project.
        (e) Phase IV--Project Development and Completion of Site-specific 
    EIS (September 1, 2000-August 31, 2001).
        (1) Description. The financial assistance recipient selected in 
    Phase III will undertake final design and engineering work for the 
    selected project together with completing the site-specific final EIS. 
    Detailed agreements for the construction and operation of the project 
    would be negotiated. The other grant recipients may also elect to 
    complete the site-specific draft EISs initiated during Phase II.
        (2) Timing of Major Milestones. August 31, 2001--Final Record of 
    Decision on site-specific EIS, confirming the project design.
        (f) Phase V--Completion of Detailed Engineering & Construction 
    (September 1, 2001 and beyond).
        (1) Description. In Phase V, the sponsoring State or State 
    designated authority would oversee the efforts of the public/private 
    partnership formed to progress the selected project, to complete the 
    detailed engineering designs, finance, construct, equip, and operate 
    the project in revenue service. Construction would likely be contingent 
    on the appropriation of federal funds.
        (2) [Revised]
        3. Section 268.13 is revised to read as follows:
    
    
    Sec. 268.13  Deadline for submission of applications for 
    preconstruction planning assistance.
    
        Completed application packages shall be returned to FRA by February 
    15, 1999. Applications shall be submitted to: Honorable Jolene M. 
    Molitoris, Administrator, Federal Railroad Administration, ATTN: Maglev 
    Project, RDV-11, 1120 Vermont Ave., NW, Stop 20, Washington, DC 20590.
    
        Issued in Washington, DC, on February 9, 1999.
    Donald M. Itzkoff,
    Deputy Federal Railroad Administrator.
    [FR Doc. 99-3605 Filed 2-11-99; 8:45 am]
    BILLING CODE 4910-06-P
    
    
    

Document Information

Effective Date:
2/12/1999
Published:
02/12/1999
Department:
Federal Railroad Administration
Entry Type:
Rule
Action:
Amendment to the interim final rule.
Document Number:
99-3605
Dates:
This Amendment to the Interim Final Rule is effective February 12, 1999.
Pages:
7133-7134 (2 pages)
Docket Numbers:
FRA Docket No. FRA-95-4545, Notice No. 2
RINs:
2130-AB29: Planning Activities Under the Magnetic Levitation Transportation Technology Deployment Program
RIN Links:
https://www.federalregister.gov/regulations/2130-AB29/planning-activities-under-the-magnetic-levitation-transportation-technology-deployment-program
PDF File:
99-3605.pdf
CFR: (2)
49 CFR 268.3
49 CFR 268.13