97-3737. Proposed Generic Communication; Loss of Reactor Coolant Inventory and Associated Potential for Loss of Emergency Mitigation Functions While in a Shutdown Condition (M92635)  

  • [Federal Register Volume 62, Number 31 (Friday, February 14, 1997)]
    [Notices]
    [Pages 7075-7077]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-3737]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    
    Proposed Generic Communication; Loss of Reactor Coolant Inventory 
    and Associated Potential for Loss of Emergency Mitigation Functions 
    While in a Shutdown Condition (M92635)
    
    AGENCY: Nuclear Regulatory Commission.
    
    ACTION: Notice of opportunity for public comment.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Nuclear Regulatory Commission (NRC) is proposing to issue 
    a generic letter that will request addressees to (1) assess the 
    susceptibility of their emergency core cooling system (ECCS) to common-
    cause failure as a result of reactor coolant system (RCS) draindown 
    while in a shutdown condition, and (2) submit certain information, 
    pursuant to Sec. 50.54(f) of Title 10 of the Code of Federal 
    Regulations (10 CFR 50.54(f)), concerning their findings regarding 
    potential pathways for inadvertent RCS drain-down and the suitability 
    of configuration control and operating practices during reactor 
    shutdown cooling. This information will enable NRC staff to verify 
    whether addressees comply and conform with NRC regulatory and license 
    requirements; i.e., are adequately maintaining the residual heat 
    removal safety function to transfer fission product decay heat and 
    other residual heat from the reactor core (General Design Criterion 
    (GDC) 34 of Appendix A to 10 CFR 50), and the ECCS to provide abundant 
    emergency core cooling when required (GDC 35 of Appendix A to 10 CFR 
    part 50). The NRC is seeking comment from interested parties regarding 
    both the technical and regulatory aspects of the proposed generic 
    letter presented under the Supplementary Information heading.
        The proposed generic letter has been endorsed by the Committee to 
    Review Generic Requirements (CRGR). The relevant information that was 
    sent to the CRGR will be placed in the NRC Public Document Room. The 
    NRC will consider comments received from interested parties in the 
    final evaluation of the proposed generic letter. The NRC's final 
    evaluation will include a review of the technical position and, as 
    appropriate, an analysis of the value/impact on licensees. Should this 
    generic letter be issued by the NRC, it will become available for 
    public inspection in the NRC Public Document Room.
    
    DATES: Comment period expires March 17, 1997. Comments submitted after 
    this date will be considered if it is practical to do so, but assurance 
    of consideration cannot be given except for comments received on or 
    before this date.
    
    ADDRESSES: Submit written comments to Chief, Rules Review and 
    Directives Branch, U.S. Nuclear Regulatory Commission, Mail Stop T-6D-
    69, Washington, DC 20555-0001. Written comments may also be delivered 
    to 11545 Rockville Pike, Rockville, Maryland, from 7:30 am to 4:15 pm, 
    Federal workdays. Copies of written comments received may be examined 
    at the NRC Public Document Room, 2120 L Street, N.W. (Lower Level), 
    Washington, D.C.
    
    FOR FURTHER INFORMATION CONTACT: Muhammad M. Razzaque (301) 415-2882.
    
    SUPPLEMENTARY INFORMATION:
    
    NRC Generic Letter 97-xx: Loss of Reactor Cooland Inventory and 
    Associated Potential for Loss of Emergency Mitigation Functions While 
    in a Shutdown Condition
    
    Addressees
    
        All holders of operating licenses for pressurized-water reactors 
    (PWRs), except those that have certified to the permanent cessation of 
    operations.
    
    Purpose
    
        The U.S. Nuclear Regulatory Commission (NRC) is issuing this 
    generic letter to request that addressees (1) assess the susceptibility 
    of their emergency core cooling systems (ECCSs) to common-cause failure 
    as a result of reactor coolant system (RCS) draindown while in a 
    shutdown condition, and (2) submit certain information, pursuant to 
    Sec. 50.54(f) of Title 10 of the Code of Federal Regulations (10 CFR 
    50.54(f)), concerning their findings regarding potential pathways for 
    inadvertent RCS drain-down and the suitability of configuration control 
    and operating practices during reactor shutdown cooling. This 
    information will enable NRC staff to verify whether addressees comply 
    and conform with NRC regulatory and license requirements; i.e., are 
    adequately maintaining the RHR safety function to transfer fission 
    product decay heat and other residual heat from the reactor core 
    (General Design Criterion (GDC) 34 of Appendix A to 10 CFR part 50), 
    and the ECCS to provide abundant emergency core cooling when required 
    (GDC 35 of Appendix A to 10 CFR part 50).
    
    Background
    
        The NRC issued Information Notice (IN) 95-03, ``Loss of Reactor 
    Coolant Inventory and Potential Loss of Emergency Mitigation Functions 
    While in a Shutdown Condition,'' on January 12, 1995, to alert 
    addressees to an incident at the Wolf Creek Plant involving the loss of 
    reactor coolant inventory while the reactor was in a shutdown 
    condition. In that event, operators were attempting to reborate 
    residual heat removal (RHR) train B, while at the same time maintenance 
    personnel were repacking an RHR train A-to-train B crossover isolation 
    valve. Train B is reborated by recirculating water through a loop that 
    contains the RHR system piping, the refueling water storage tank 
    (RWST), a containment spray pump, a manual RWST isolation
    
    [[Page 7076]]
    
    valve, and an RHR system crossover line. When the RWST isolation valve 
    was opened for the reboration process and the train A-to-train B 
    crossover isolation valve was opened for stroke testing, a drain-down 
    path was inadvertently created from the reactor coolant system (RCS) to 
    the RWST. This drain-down path included a suction header common to all 
    ECCS pumps.
        Events of this nature are considered particularly significant 
    because they can result in loss of emergency core cooling capability 
    and involve the potential for containment bypass. On March 25, 1996, 
    the staff issued a supplement to IN 95-03 that further analyzed the 
    event. The NRC has also issued a number of other communications 
    describing events at reactor facilities involving inadvertent loss of 
    reactor coolant inventory while the reactor was in a shutdown 
    condition. The Office for Analysis and Evaluation of Operational Data 
    (AEOD) published AEOD/E704, ``Discharge of Primary Coolant Outside of 
    Containment at PWRs While on RHR Cooling,'' in March 1987, which 
    documented six events involving RCS backflow into the RWST. In Generic 
    Letter 88-17, ``Loss of Decay Heat Removal (DHR) 10 CFR 50.54(f),'' 
    dated October 17, 1988, the NRC requested several actions to address 
    loss-of-DHR events that occurred while reactors were in a shutdown 
    condition. In IN 91-42, ``Plant Outage Events Involving Poor 
    Coordination Between Operations and Maintenance Personnel During Valve 
    Testing and Manipulations,'' dated June 27, 1991, the NRC discussed 
    inadvertent loss-of-inventory events.
    
    Discussion
    
        At Wolf Creek, all ECCS pump suction lines are tied into a common 
    suction header. When the draindown event occurred at Wolf Creek, hot 
    RCS water was introduced into this common suction header between the 
    RWST and the ECCS pumps. This hot water flashed to steam, resulting in 
    a steam/water mixture in the header. In the event of an ECCS actuation, 
    this mixture would have been introduced into the suction of the ECCS 
    pumps. If operators had not been able to terminate the event, the hot 
    water in the RWST suction piping might have led to steam binding, which 
    could have affected all pumps in both ECCS trains. In addition, water 
    flashing to steam in the header and the RWST could have caused serious 
    mechanical damage to the RHR piping and the RWST as a result of water 
    hammer. Finally, steaming through the RWST establishes a containment 
    bypass path.
        The licensee estimated (using actual plant conditions) that for an 
    unmitigated event, the reactor vessel water level could have drained to 
    the bottom of the hot leg within 5 minutes and, as a consequence, RHR 
    pump A would have lost suction, cavitated, and failed. Shortly 
    thereafter, the common ECCS suction header could have reached a 90-
    percent steam/water ratio. The licensee also estimated that continued 
    boil-off could have caused the pressure vessel water level to drop to 
    the point of core uncovery in less than 1 hour.
        The AEOD report ``Reactor Coolant System Blowdown at Wolf Creek on 
    September 17, 1994,'' (AEOD/S95-01), dated March 1995, noted 19 events 
    in which RCS water was transferred to the RWST. On the basis of this 
    history and the potential for containment bypass, the staff has 
    concluded that additional information is required to confirm the 
    adequacy of existing ECCS configuration control and operating practices 
    regarding residual heat removal.
    
    Requested Actions
    
        Addressees are requested to determine whether their ECCSs are 
    susceptible to common-cause failure, e.g., as a result of events 
    similar to the Wolf Creek RCS drain-down event of September 17, 1994.
        If ECCSs are found to be susceptible to common-cause failure, 
    addressees are expected to take corrective action, as appropriate, in 
    accordance with the requirements stated in Section XVI of Appendix B to 
    10 CFR Part 50, to ensure compliance with NRC regulatory and license 
    requirements.
    
    Requested Information
    
        Within 120 days of the date of this generic letter, addressees are 
    requested to submit a written summary report that includes a 
    description of the evaluation conducted and the conclusions reached 
    concerning the susceptibility of the RCS to drain-down events with a 
    potential for consequential common-cause ECCS failure, and the 
    corrective actions that were taken, or that are planned to be taken, if 
    any, in response to the above requested actions. If the RCS is found to 
    be susceptible to drain-down events, describe each potential drain-down 
    flow path (include piping sizes, identify flow path valves and their 
    normal positions, and identify valve interlocks and provisions for 
    valve position indication in the control room), describe potential 
    valve testing manipulations or uses, and describe any administrative 
    controls that are intended to be used to control valve manipulations to 
    preclude RCS drain-down events.
    
    Required Response
    
        Within 30 days of the date of this generic letter, addressees are 
    required to submit a written response indicating (1) whether or not the 
    requested actions will be taken, (2) whether or not the requested 
    information will be submitted, and (3) whether or not the requested 
    information will be submitted within the requested time period. 
    Addressees who choose not to complete the requested actions, or choose 
    not to submit the requested information, or are unable to satisfy the 
    requested completion date must describe in their response any 
    alternative course of action that is proposed to be taken, including 
    the basis for establishing the acceptability of the proposed 
    alternative course of action and the basis for continued operability of 
    affected systems and components, as applicable.
        Address the required written responses to the U.S. Nuclear 
    Regulatory Commission, ATTN: Document Control Desk, Washington, D.C. 
    20555-0001, under oath or affirmation under the provisions of Section 
    182a of the Atomic Energy Act of 1954, as amended, and 10 CFR 50.54(f). 
    In addition, submit a copy to the appropriate regional administrator.
    
    Backfit Discussion
    
        The actions requested in this generic letter, if required, would be 
    backfits in accordance with NRC procedures and are necessary to ensure 
    that addressees are in compliance with existing NRC rules and 
    regulations. Specifically, 10 CFR 50.46 requires that the ECCS be 
    designed to provide adequate flow capability to maintain the core 
    temperature at an acceptably low value and to remove decay heat for the 
    extended period of time required by the long-lived radioactivity 
    remaining in the core. The Wolf Creek event has demonstrated that the 
    adequacy of ECCS configuration control and operating practices 
    regarding residual heat removal can adversely impact ECCS performance 
    and could prevent the ECCS from performing its safety function 
    following events at reactor facilities involving inadvertent loss of 
    reactor coolant inventory while the reactor is shut down. Therefore, 
    this generic letter is being issued as if the requested actions were 
    compliance backfits under the terms of 10 CFR 50.109(a)(4)(i). A full 
    backfit analysis was not performed. However, in accordance with NRC 
    procedures, an evaluation was prepared stating the objectives of and 
    the reasons for the requested actions and the basis for invoking the 
    compliance exception if
    
    [[Page 7077]]
    
    the requested actions were to be required. A copy of this evaluation 
    will be made available in the NRC Public Document Room.
    
        Dated at Rockville, Maryland, this 10th day of February 1997.
    
        For the Nuclear Regulatory Commission.
    Thomas T. Martin,
    Director, Division of Reactor Program Management, Office of Nuclear 
    Reactor Regulation.
    [FR Doc. 97-3737 Filed 2-13-97; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
02/14/1997
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Action:
Notice of opportunity for public comment.
Document Number:
97-3737
Dates:
Comment period expires March 17, 1997. Comments submitted after this date will be considered if it is practical to do so, but assurance of consideration cannot be given except for comments received on or before this date.
Pages:
7075-7077 (3 pages)
PDF File:
97-3737.pdf