E8-2722. Salvatore and Michelle Shifrin; Notice of Application Tendered for Filing with the Commission, Soliciting Additional Study Requests, and Establishing Procedual Schedule for Licensing and Deadline for Submission of Final Amendments  

  • Start Preamble February 7, 2008.

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

    a. Type of Application: Exemption From Licensing.

    b. Project No.: P-12551-001.

    c. Date Filed: January 25, 2008.

    d. Applicant: Salvatore and Michelle Shifrin.

    e. Name of Project: Mansfield Hollow Hydro Power Project.

    f. Location: On the Natchaug River in Tolland County, Connecticut. The project would occupy lands of the United States.

    g. Filed Pursuant to: Public Utilities Regulatory Policies Act of 1978, 16 U.S.C. 2705, 2708.

    h. Applicant Contact: Salvatore or Michelle Shifrin, 78 Bricktop Road, Windham, CT 06280, (860) 423-7709.

    i. FERC Contact: Tom Dean, (202) 502-6041.

    j. Cooperating Agencies: We are asking Federal, State, and local agencies and Indian tribes with jurisdiction and/or special expertise with respect to environmental issues to cooperate with us in the preparation of the environmental document. Agencies who would like to request cooperating status should follow the instructions for filing comments described in item l below.

    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant.

    l. Deadline for filing additional study requests and requests for cooperating agency status: March 25, 2008.

    All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

    Additional study requests and requests for cooperating agency status may be filed electronically via the internet in lieu of paper. The Commission strongly encourages electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site at (http://www.ferc.gov) under the “eFiling” link.

    m. This application is not ready for environmental analysis at this time.

    n. Description of Project: The Mansfield Hollow Hydro Power Project would consist of: (1) The existing 80-foot-long, 10-foot-high Kirby Mill Dam; (2) the existing 1.6-acre reservoir; (3) the existing headgate structure; (4) the existing 12-foot-wide, 8-foot-foot-high, 330-foot-long head race channel; (5) a new powerhouse containing five generating units with a total installed capacity of 500 kilowatts; (6) the existing 5-foot-wide, 7-foot-high, 100-foot-long conduit and 75-foot-long open tailrace; and (7) appurtenant facilities. The project would have an average annual generation of about 2,500 megawatt-hours.

    In addition to a new powerhouse, project restoration would consist of: (1) A new 12-foot-wide, 8-foot-high, 330-foot-long head race channel; (2) a new 20-foot-wide, 8-foot-high, 20-foot-long box culvert connected to a new 25-foot-wide, 4-foot-high, 153-foot-long open channel tail race; and (3) a new 275-foot-long transmission line.

    o. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, contact (202) 502-8659. A copy is also available for inspection and reproduction at the address in item h above.

    You may also register online at http://www.ferc.gov/​docs-filing/​esubscription.asp to be notified via e-mail of new filings and issuances Start Printed Page 8658related to this or other pending projects. For assistance, contact FERC Online Support.

    p. With this notice, we are initiating consultation with the Connecticut State Historic Preservation Officer (SHPO), as required by section 106, National Historic Preservation Act, and the regulations of the Advisory Council on Historic Preservation, 36 CFR 800.4.

    q. Procedural schedule and final amendments: The application will be processed according to the following Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate. The Commission staff proposes to issue one environmental assessment rather than issue a draft and final EA. Comments, terms and conditions, recommendations, prescriptions, and reply comments, if any, will be addressed in an EA. Staff intends to give at least 30 days for entities to comment on the EA, and will take into consideration all comments received on the EA before final action is taken on the license application.

    Issue Acceptance Letter or Deficiency LetterApril 2008.
    Issue Scoping DocumentMay 2008.
    Notice of application is ready for environmental analysisAugust 2008.
    Notice of the availability of the EAApril 2009.

    Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis.

    Start Signature

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. E8-2722 Filed 2-13-08; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
02/14/2008
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
E8-2722
Pages:
8657-8658 (2 pages)
Docket Numbers:
Project No. 12551-001
EOCitation:
of 2008-02-07