2019-02528. Defense Federal Acquisition Regulation Supplement: Modification of DFARS Clause “Transportation of Supplies by Sea” (DFARS Case 2018-D028)
-
Start Preamble
AGENCY:
Defense Acquisition Regulations System, Department of Defense (DoD).
ACTION:
Final rule.
SUMMARY:
DoD is issuing a final rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to modify the text of an existing DFARS clause to include the text of another DFARS clause, in order to streamline the instructions to contractors subject to both of these clauses.
DATES:
Effective February 15, 2019.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Ms. Carrie Moore, telephone 571-372-6093.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
I. Background
DoD published a proposed rule in the Federal Register at 83 FR 42846 on August 24, 2018, to modify DFARS clause 252.247-7023, Transportation of Supplies by Sea, to include the instructions currently specified in DFARS clause 252.247-7024, Notification of Supplies by Sea, and then remove DFARS clause 252.247-7024 from the DFARS. No public comments were received in response to the proposed rule.
II. Applicability to Contracts at or Below the Simplified Acquisition Threshold and for Commercial Items, including Commercially Available Off-The-Shelf Items
This rule does not create any new provisions or clauses or impose any new requirements. The rule merely consolidates existing instructions regarding notifications of transportation of supplies by sea into a single DFARS clause, 252.247-7023, which will continue to apply to contracts for commercial and commercially available Off-the-shelf items, as well as contracts at or below the simplified acquisition threshold.
III. Executive Orders 12866 and 13563
Executive Order (E.O.) 12866, Regulatory Planning and Review; and E.O. 13563, Improving Regulation and Regulatory Review, direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. The Office of Management and Budget, Office of Information and Regulatory Affairs, has determined that this is not a significant regulatory action as defined under section 3(f) of E.O. 12866 and, therefore, was not subject to review under section 6(b). This rule is not a major rule as defined at 5 U.S.C. 804(2).
IV. Executive Order 13771
This final rule is not an E.O. 13771 regulatory action, because this rule is not significant under E.O. 12866.
V. Regulatory Flexibility Act
A final regulatory flexibility analysis (FRFA) has been prepared consistent with the Regulatory Flexibility Act, 5 U.S.C. 601, et seq. The FRFA is summarized as follows:
DoD is amending DFARS clause 252.247-7023, Transportation of Supplies by Sea, to include the instructions currently specified in DFARS clause 252.247-7024, Notification of Supplies by Sea, and then removing DFARS clause 252.247-7024 from the DFARS. The objective of this rule is to streamline the instructions to contractors pertaining to the transportation of supplies by sea. The combination of these DFARS clauses supports a recommendation from the DoD Regulatory Reform Task Force.
No public comments were received in response to the initial regulatory flexibility analysis.
Based on fiscal year 2016 data from the Federal Procurement Data System, the Government issued approximately 83,000 contract actions that included DFARS clause 252.247-7023. Of the 83,000 contract actions, approximately 39,000 awards were made to 15,000 unique small businesses entities.
This rule does not include any new reporting, recordkeeping, or other compliance requirements for small businesses.
There are no known significant alternative approaches to the rule that would meet the proposed objectives.Start Printed Page 4371
VI. Paperwork Reduction Act
The Paperwork Reduction Act (44 U.S.C. chapter 35) does apply; however, these changes to the DFARS do not impose additional information collection requirements to the paperwork burden previously approved under OMB Control Number 0704-0245, titled: Defense Federal Acquisition Regulation Supplement (DFARS) Part 247, Transportation and Related Clauses.
Start List of SubjectsList of Subjects in 48 CFR Parts 212, 247, and 252
- Government procurement
Jennifer Lee Hawes,
Regulatory Control Officer, Defense Acquisition Regulations System.
Therefore, 48 CFR parts 212, 247, and 252 are amended as follows:
Start Amendment Part1. The authority citation for 48 CFR parts 212, 247, and 252 continues to read as follows:
End Amendment Part Start PartPART 212—ACQUISITION OF COMMERCIAL ITEMS
[Amended]2. Amend section 212.301 by:
End Amendment Part Start Amendment Parta. Removing paragraph (f)(xix)(D);
End Amendment Part Start Amendment Partb. Redesignating paragraphs (f)(xix)(E) through (H) as paragraphs (f)(xix)(D) through (G), respectively;
End Amendment Part Start Amendment Partc. In the newly redesignated paragraph (f)(xix)(D), removing “247.574(d)” and adding “247.574(c)” in its place;
End Amendment Part Start Amendment Partd. In the newly redesignated paragraph (f)(xix)(E), removing “247.574(e)” and adding “247.574(d)” in its place;
End Amendment Part Start Amendment Parte. In the newly redesignated paragraph (f)(xix)(F), removing “247.574(f)” and adding “247.574(e)” in its place; and
End Amendment Part Start Amendment Partf. In the newly redesignated paragraph (f)(xix)(G), removing “U.S” and adding “U.S.” in its place.
End Amendment Part Start PartPART 247—TRANSPORTATION
[Amended]3. Amend section 247.574 by:
End Amendment Part Start Amendment Parta. Removing paragraph (c); and
End Amendment Part Start Amendment Partb. Redesignating paragraphs (d) through (f) as paragraphs (c) through (e), respectively.
End Amendment Part Start PartPART 252—SOLICITATION PROVISIONS AND CONTRACT CLAUSES
End Part Start Amendment Part4. Amend section 252.247-7023 by:
End Amendment Part Start Amendment Parta. In the clause heading, removing the date “(APR 2014)” and adding “(FEB 2019)” in its place;
End Amendment Part Start Amendment Partb. Redesignating paragraph (h) as paragraph (i);
End Amendment Part Start Amendment Partc. Adding a new paragraph (h); and
End Amendment Part Start Amendment Partd. In the newly redesignated paragraphs (i)(1) and (2), removing “paragraph (h)” and adding “paragraph (i)” in both places;
End Amendment Part Start Amendment Parte. In Alternate I:
End Amendment Part Start Amendment Parti. In the clause heading, removing the date of “(APR 2014)” and adding “(FEB 2019)” in its place;
End Amendment Part Start Amendment Partii. Redesignating paragraph (h) as paragraph (i);
End Amendment Part Start Amendment Partiii. In the newly redesignated paragraphs (i)(1) and (2), removing “paragraph (h)” and adding “paragraph (i)” in both places; and
End Amendment Part Start Amendment Partiv. Adding a new paragraph (h).
End Amendment Part Start Amendment Partf. In Alternate II—
End Amendment Part Start Amendment Parti. In the clause heading, removing the date of “(APR 2014)” and adding “(FEB 2019)” in its place;
End Amendment Part Start Amendment Partii. Redesignating paragraph (h) as paragraph (i);
End Amendment Part Start Amendment Partiii. In the newly redesignated paragraphs (i)(1) and (2), removing “paragraph (h)” and adding “paragraph (i)” in both places; and
End Amendment Part Start Amendment Partiv. Adding a new paragraph (h).
End Amendment PartThe additions read as follows:
Transportation of Supplies by Sea.* * * * *(h) If the Contractor has indicated by the response to the solicitation provision, Representation of Extent of Transportation by Sea, that it did not anticipate transporting by sea any supplies; however, after the award of this contract, the Contractor learns that supplies will be transported by sea, the Contractor—
(1) Shall notify the Contracting Officer of that fact; and
(2) Hereby agrees to comply with all the terms and conditions of this clause.
* * * * *Alternate I. * * *
* * * * *(h) If the Contractor has indicated by the response to the solicitation provision, Representation of Extent of Transportation by Sea, that it did not anticipate transporting by sea any supplies; however, after the award of this contract, the Contractor learns that supplies will be transported by sea, the Contractor—
(1) Shall notify the Contracting Officer of that fact; and
(2) Hereby agrees to comply with all the terms and conditions of this clause.
* * * * *Alternate II. * * *
* * * * *(h) If the Contractor has indicated by the response to the solicitation provision, Representation of Extent of Transportation by Sea, that it did not anticipate transporting by sea any supplies, but the contractor learns after the award of the contract that supplies will be transported by sea, the Contractor shall notify the Contracting Officer of that fact.
* * * * *[Removed and Reserved]4. Remove and reserve section 252.247-7024.
End Amendment Part[Amended]5. Amend section 252.247-7025, in the introductory text, by removing “247.574(d)” and adding “247.574(c)” in its place.
End Amendment Part[Amended]6. Amend section 252.247-7026, in the introductory text, by removing “247.574(e)” and adding “247.574(d)” in its place.
End Amendment Part[Amended]7. Amend section 252.247-7027, in the introductory text, by removing “247.574(f)” and adding “247.574(e)” in its place.
End Amendment Part End Supplemental Information[FR Doc. 2019-02528 Filed 2-14-19; 8:45 am]
BILLING CODE 5001-01-P
Document Information
- Effective Date:
- 2/15/2019
- Published:
- 02/15/2019
- Department:
- Defense Acquisition Regulations System
- Entry Type:
- Rule
- Action:
- Final rule.
- Document Number:
- 2019-02528
- Dates:
- Effective February 15, 2019.
- Pages:
- 4370-4371 (2 pages)
- Docket Numbers:
- Docket DARS-2018-0040
- RINs:
- 0750-AJ94: Modification of DFARS Clause "Transportation of Supplies By Sea" (DFARS Case 2018-D028)
- RIN Links:
- https://www.federalregister.gov/regulations/0750-AJ94/modification-of-dfars-clause-transportation-of-supplies-by-sea-dfars-case-2018-d028-
- Topics:
- Government procurement
- PDF File:
- 2019-02528.pdf
- CFR: (7)
- 48 CFR 212.301
- 48 CFR 247.574
- 48 CFR 252.247-7023
- 48 CFR 252.247-7024
- 48 CFR 252.247-7025
- More ...