98-3947. Notice of Application Acceptance and Notice Requesting Interventions and Protests  

  • [Federal Register Volume 63, Number 32 (Wednesday, February 18, 1998)]
    [Notices]
    [Pages 8194-8195]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-3947]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    
    
    Notice of Application Acceptance and Notice Requesting 
    Interventions and Protests
    
    February 11, 1998.
        Take notice that the following hydroelectric application has been 
    filed with the Commission and is available for public inspection:
        a. Type of Application: Original License for a Major Water Power 
    Project--5 Megawatts or Less.
        b. Project No.: 11480.
        c. Date filed: November 25, 1997.
        d. Applicant: Haida Corporation.
        e. Name of Project: Reynolds Creek Hydroelectric Project.
        f. Location: On Reynolds Creek, Prince of Wales Island, Alaska.
        g. Filed Pursuant to: Federal Power Act and Public Utility 
    Regulatory Policies Act.
        h. Applicant Contact: Michael V. Stimac, HDR Engineering, Inc., 
    500-108th Avenue NE, Suite 1200, Bellevue, Washington 98004-5538, (425) 
    453-1523.
        i. FERC Contact: Carl J. Keller, (202) 219-2831.
        j. Deadline for filing interventions and protests: April 15, 1998.
        k. Status of Environmental Analysis: This application is not ready 
    for environmental analysis at this time; therefore, the Commission is 
    not now requesting comments, recommendations, terms and conditions, or 
    prescriptions--see attached paragraph D7.
        l. Brief Description of Project: The proposed modified run-of-river 
    hydroelectric project would consist of: (1) A 20-foot-long, concrete 
    weir, diversion dam and intake at the outlet of Rich's Pond; (2) a 
    3,200-foot-long, 42-inch diameter, steel penstock, (3) a metal 
    powerhouse initially containing a 1,500 kilowatt (kW) horizontal 
    impulse turbine/generator for Phase 1; Phase II would add a second 
    3,500 kW turbine/generator, (4) about 500 feet of new access road, and 
    (5) a 10.9-mile-long, 34.5 kilovolt overhead transmission line.
        m. This notice also consists of the following standard paragraphs: 
    A2, A-9, B1, and D7.
        n. Available Locations of Application: A copy of the application is 
    available for inspection and reproduction at the Commission's Public 
    Reference Room, Room 2A, 888 First Street, N.E., Washington, D.C. 20426 
    or by calling (202) 208-1659. A copy is also available
    
    [[Page 8195]]
    
    for inspection and reproduction by contacting Mr. Michael Stimac at HDR 
    Engineering, Inc. at (425) 453-1523 in Bellevue, Washington or Mr. 
    Charles Skultka, Sr., Haida Corporation, at (907) 966-2574 in Hydaburg, 
    Alaska.
        A2. Development Application--Any qualified applicant desiring to 
    file a competing application must submit to the Commission, on or 
    before the specified deadline date for the particular application, a 
    competing development application, or a notice of intent to file such 
    an application. Submission of a timely notice of intent allows an 
    interested person to file the competing development application no 
    later than 120 days after the specified deadline date for the 
    particular application. Applications for preliminary permits will not 
    be accepted in response to this notice.
        A9. Notice of intent--A notice of intent must specify the exact 
    name, business address, and telephone number of the prospective 
    applicant, and must include an unequivocal statement of intent to 
    submit, if such an application may be filed, either a preliminary 
    permit application or a development application (specify which type of 
    application). A notice of intent must be served on the applicant(s) 
    named in this public notice.
        B1. Protests or Motions to Intervene--Anyone may submit a protest 
    or a motion to intervene in accordance with the requirements of Rules 
    of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In 
    determining the appropriate action to take, the Commission will 
    consider all protests filed, but only those who file a motion to 
    intervene in accordance with the Commission's Rules may become a party 
    to the proceeding. Any protests or motions to intervene must be 
    received on or before the specified deadline date for the particular 
    application.
        D7. Filing and Service of Responsive Documents--The application is 
    not ready for environmental analysis at this time; therefore, the 
    Commission is not now requesting comments, recommendations, terms and 
    conditions, or prescriptions.
        When the application is ready for environmental analysis, the 
    Commission will issue a public notice requesting comments, 
    recommendations, terms and conditions, or prescriptions.
        All filings must (1) bear in all capital letters the title 
    ``PROTEST'' or ``MOTION TO INTERVENE,'' ``NOTICE OF INTENT TO FILE 
    COMPETING APPLICATION,'' or ``COMPETING APPLICATION;'' (2) set forth in 
    the heading the name of the applicant and the project number of the 
    application to which the filing responds; (3) furnish the name, 
    address, and telephone number of the person protesting or intervening; 
    and (4) otherwise comply with the requirements of 18 CFR 385.2001 
    through 385.2005. Any of these documents must be filed by providing the 
    original and the number of copies required by the Commission's 
    regulations to: The Secretary, Federal Energy Regulatory Commission, 
    888 First Street, N.E., Washington, D.C. 20426. An additional copy must 
    be sent to Director, Division of Project Review, Office of Hydropower 
    Licensing, Federal Energy Regulatory Commission, at the above address. 
    A copy of any protest or motion to intervene must be served upon each 
    representative of the applicant specified in the particular 
    application.
    Lindwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 98-3947 Filed 2-19-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
02/18/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-3947
Pages:
8194-8195 (2 pages)
PDF File:
98-3947.pdf