99-3900. Notice of Application Accepted for Filing and Soliciting Motions to Intervene and Protests  

  • [Federal Register Volume 64, Number 32 (Thursday, February 18, 1999)]
    [Notices]
    [Page 8084]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-3900]
    
    
    
    [[Page 8084]]
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    
    
    Notice of Application Accepted for Filing and Soliciting Motions 
    to Intervene and Protests
    
    February 11, 1999.
        Take notice that the following hydroelectric application has been 
    filed with the Commission and is available for public inspection.
        a. Type of Application: Preliminary Permit.
        b. Project No.: P-11641-000.
        c. Date filed: November 27, 1998.
        d. Applicant: Universal Electric Power Corp.
        e. Name of Project: Tionesta Dam Project.
        f. Location: At the Corps of Engineer's Tionesta Dam, on the 
    Tionesta Creek, near the town of Tionesta, Forest County, Pennsylvania.
        g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)--825(r).
        h. Applicant Contact: Mr. Ronald Feltenberger, Universal Electric 
    Power Corp., Akron, Ohio 44301, (330) 535-7115.
        i. FERC Contact: Any questions on this notice should be addressed 
    to Michael Spencer, E-mail address at [email protected]FERC.fed.us, or 
    telephone (202) 219-2846.
        j. Comment Date: 60 days from the issuance date of this notice.
        k. Description of Project: The proposed project would utilize the 
    Corps of Engineer's Tionesta Dam and consist of the following: (1) a 
    66-inch-diameter, 50-foot-long penstock, constructed in the existing 
    discharge conduit; (2) a powerhouse, containing two generating units 
    with a combined capacity of 1.2 MW and an estimated average annual 
    generation of 9.0 Gwh; and (3) a 1,500-foot-long transmission line.
        l. Locations of the application: A copy of the application is 
    available for inspection and reproduction at the Commission's Public 
    Reference and Files Maintenance Branch, located at 888 North Capitol 
    Street, N.E., Room 2A, Washington, D.C. 20426, or by calling (202) 219-
    1371. The application may be viewed on the web at www.ferc.fed.us. Call 
    (202) 208-2222 for assistance. A copy is also available for inspection 
    and reproduction at the address in item h above.
        m. This notice also consists of the following standard paragraphs: 
    A5, A7, A9, A10, B, C, and D2.
        A5. Preliminary Permit--Anyone desiring to file a competing 
    application for preliminary permit for a proposed project must submit 
    the competing application itself, or a notice of intent to file such an 
    application, to the Commission on or before the specified comment date 
    for the particular application (see 18 CFR 4.36). Submission of a 
    timely notice of intent allows an interested person to file the 
    competing preliminary permit application no later than 30 days after 
    the specified comment date for the particular application. A competing 
    preliminary permit application must conform with 18 CFR 4.30(b) and 
    4.36.
        A7. Preliminary Permit--Any qualified development applicant 
    desiring to file a competing development application must submit to the 
    Commission, on or before a specified comment date for the particular 
    application, either a competing development application or a notice or 
    intent to file such an application. Submission of a timely notice of 
    intent to file a development application allows an interested person to 
    file the competing application no later than 120 days after the 
    specified comment date for the particular application. A competing 
    license application must conform with 18 CFR 4.30(b) and 4.36.
        A9. Notice of intent--A notice of intent must specify the exact 
    name, business address, and telephone number of the prospective 
    applicant, and must include an unequivocal statement of intent to 
    submit, if such an application may be filed, either a preliminary 
    permit application or a development application (specify which type of 
    application). A notice of intent must be served on the applicant(s) 
    named in this public notice.
        A10. Proposed Scope of Studies under Permit--A preliminary permit, 
    if issued, does not authorize construction. The term of the proposed 
    preliminary permit would be 36 months. The work proposed under the 
    preliminary permit would include economic analysis, preparation of 
    preliminary engineering plans, and a study of environmental impacts. 
    Based on the results of these studies, the Applicant would decide 
    whether to proceed with the preparation of a development application to 
    construct and operate the project.
        B. Comments, Protests, or Motions to Intervene--Anyone may submit 
    comments, a protest, or a motion to intervene in accordance with the 
    requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
    .214. In determining the appropriate action to take, the Commission 
    will consider all protests or other comments filed, but only those who 
    file a motion to intervene in accordance with the Commission's Rules 
    may become a party to the proceeding. Any comments, protests, or 
    motions to intervene must be received on or before the specified 
    comment date for the particular application.
        C. Filing and Service of Responsive Documents--Any filings must 
    bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
    TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
    ``PROTEST'', ``MOTION TO INTERVENE'', as applicable, and the Project 
    Number of the particular application to which the filing refers. Any of 
    the above-named documents must be filed by providing the original and 
    the number of copies provided by the Commission's regulations to: The 
    Secretary, Federal Energy Regulatory Commission, 888 First Street, 
    N.E., Washington, D.C. 20426. An additional copy must be sent to 
    Director, Division of Project Review, Federal Energy Regulatory 
    Commission, at the above-mentioned address. A copy of any notice of 
    intent, competing application or motion to intervene must also be 
    served upon each representative of the Applicant specified in the 
    particular application.
        D2. Agency Comments--Federal, state, and local agencies are invited 
    to file comments on the described application. A copy of the 
    application may be obtained by agencies directly from the Applicant. If 
    an agency does not file comments within the time specified for filing 
    comments, it will be presumed to have no comments. One copy of an 
    agency's comments must also be sent to the Applicant's representatives.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 99-3900 Filed 2-17-99; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
02/18/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-3900
Dates:
60 days from the issuance date of this notice.
Pages:
8084-8084 (1 pages)