2012-3939. Nationwide Categorical Waivers Under Section 1605 (Buy American) of the American Recovery and Reinvestment Act of 2009 (Recovery Act)
-
Start Preamble
AGENCY:
Office of Energy Efficiency and Renewable Energy, U.S. Department of Energy (DOE).
ACTION:
Notice of limited waivers.
SUMMARY:
The U.S. Department of Energy (DOE) is hereby granting a nationwide limited waiver of the Buy American requirements of section 1605 of the Recovery Act under the authority of Section 1605(b)(2), (iron, steel, and the relevant manufactured goods are not produced in the United States in sufficient and reasonably available quantities and of a satisfactory quality), with respect to Recovery Act projects funded by EERE for ((1) 400 amp Dual Element Time-Delay Fuses for electric vehicle supply equipment (EVSE) charging station; (2) Video imaging card rack mounted boards for vehicle presence and data detection; (3) 20-ton split system heat pump that meets a minimum static pressure requirement of 3.0 inches of water column (only where the 3.0 water column is a requirement of the system); and (4) network manager for conversion of proprietary protocol—Staefa brand system—to a non-proprietary open source protocol.
DATES:
Effective Date: 01/24/2012.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Christine Platt-Patrick, Office of Energy Efficiency and Renewable Energy (EERE), (202) 287-1553, Department of Energy, 1000 Independence Avenue SW., Mailstop EE-2K, Washington, DC 20585.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
Under the authority of American Recovery and Reinvestment Act of 2009 (Recovery Act), Public Law 111-5, section 1605(b)(2), the head of a Federal department or agency may issue a “determination of inapplicability” (a waiver of the Buy American provision) if the iron, steel, or relevant manufactured good is not produced or manufactured in the United States in sufficient and reasonably available quantities and of a satisfactory quality (“nonavailability”). The authority of the Secretary of Energy to make all inapplicability determinations was re-delegated to the Assistant Secretary for Energy Efficiency and Renewable Energy (EERE), for EERE projects under the Recovery Act, in Redelegation Order No. 00-002.01E, dated April 25, 2011. Pursuant to this delegation the Acting Assistant Secretary, EERE, has concluded that: (1) 400amp Dual Element Time-Delay Fuses for electric vehicle supply equipment (EVSE) charging station; (2) Video imaging card rack mounted boards for vehicle presence and data detection; (3) 20-ton split system heat pump that meets a minimum static pressure requirement of 3.0 inches of water column (only where the 3.0 water column is a requirement of the system); and (4) network manager for conversion of proprietary protocol—Staefa brand system—to a non-proprietary open source protocol, are not produced or manufactured in the United States in sufficient and reasonably available quantities and of a satisfactory quality. The above items, when used on eligible EERE Recovery Act-funded projects, qualify for the “nonavailability” waiver determination.
EERE has developed a robust process to ascertain in a systematic and expedient manner whether or not there is domestic manufacturing capacity for the items submitted for a waiver of the Recovery Act Buy American provision. This process involves a close collaboration with the United States Department of Commerce National Institute of Standards and Technology (NIST) Manufacturing Extension Partnership (MEP), in order to scour the domestic manufacturing landscape in search of producers before making any nonavailability determinations.
The MEP has 59 regional centers with substantial knowledge of, and connections to, the domestic manufacturing sector. MEP uses their regional centers to `scout' for current or potential manufacturers of the product(s) submitted in a waiver request. In the course of this interagency collaboration, MEP has been able to find exact or partial matches for Start Printed Page 9907manufactured goods that EERE grantees had been unable to locate. As a result, in those cases, EERE was able to work with the grantees to procure American-made products rather than granting a waiver.
Upon receipt of completed waiver requests for the four products in the current waiver, EERE reviewed the information provided and submitted the relevant technical information to the MEP. The MEP then used their network of nationwide centers to scout for domestic manufacturers. The MEP reported that their scouting process did not locate any domestic manufacturers for these exact or equivalent items.
In addition to the MEP collaboration outlined above, the EERE Buy American Coordinator worked with other manufacturing stakeholders to scout for domestic manufacturing capacity or an equivalent product for each item contained in this waiver.
EERE also conducted significant amounts of independent research to supplement MEP's scouting efforts, including utilizing the solar experts employed by the Department of Energy's National Renewable Energy Laboratory. EERE's research efforts confirmed the MEP findings that the goods included in this waiver are not produced in the United States in sufficient and reasonably available quantities and of a satisfactory quality.
The nonavailability determination is also informed by the inquiries and petitions to EERE from recipients of EERE Recovery Act funds, and from suppliers, distributors, retailers and trade associations—all stating that their individual efforts to locate domestic manufacturers for these items have been unsuccessful.
Specific technical information for the manufactured goods included in this non-availability determination is detailed below:
(1) 400amp Dual Element Time-Delay Fuses for electric vehicle supply equipment (EVSE) charging station
These are used in the installation of EV charging stations. Two national trade organizations representing American manufacturers of this equipment verified that these are not manufactured in the US. Further, MEP did not identify a potential manufacturer.
(2) Video imaging card rack mounted boards for vehicle presence and data detection
These card racks are installed into existing traffic systems and are not manufactured domestically. Neither transportation manufacturing trade associations nor MEP identified any US manufacturer of this product.
(3) 20-ton split system heat pump that meets a minimum static pressure requirement of 3.0 inches of water column (only where the 3.0 water column is a requirement of the system)
This waiver is limited to systems that require compatibility with this extremely high water column. No US manufacturers (four manufacturers of this type of equipment were identified by EERE and MEP and contacted) were able to meet this need.
(4) Network manager for conversion of proprietary protocol- Staefa brand system to a non-proprietary open source protocol
For use where a Staefa system was installed previously, and where utilizing a domestic control module would mean that the existing energy management controls would have to be removed and a new energy management controls system would have to replace the existing Staefa system. This product allows the grantee to convert from the proprietary protocol to an open-source protocol- providing a wider variety of controls in the future.
In these cases, the grantee is unable to use a domestic control module because the existing system runs off of a proprietary communication protocol (rather than LON or BACnet), and the entire system would have to be replaced to install additional controllers. Trade organizations, DOE and MEP all agreed that this was the only controller capable of properly interfacing with this protocol.
In light of the foregoing, and under the authority of section 1605(b)(2) of Public Law 111-5 and Redelegation Order 00-002-01E, with respect to Recovery Act projects funded by EERE, I hereby issue a “determination of inapplicability” (a waiver under the Recovery Act Buy American provision) for: ((1) 400amp Dual Element Time-Delay Fuses for electric vehicle supply equipment (EVSE) charging station; (2) Video imaging card rack mounted boards for vehicle presence and data detection; (3) 20-ton split system heat pump that meets a minimum static pressure requirement of 3.0 inches of water column (only where the 3.0 water column is a requirement of the system); and (4) network manager for conversion of proprietary protocol- Staefa brand system- to a non-proprietary open source protocol.
Having established a proper justification based on domestic nonavailability, EERE hereby provides notice that on January 24, 2012, four (4) nationwide categorical waivers of section 1605 of the Recovery Act were issued as detailed supra. This notice constitutes the detailed written justification required by Section 1605(c) for waivers based on a finding under subsection (b).
This waiver determination is pursuant to the delegation of authority by the Secretary of Energy to the Assistant Secretary for Energy Efficiency and Renewable Energy with respect to expenditures within the purview of his responsibility. Consequently, this waiver applies to all EERE projects carried out under the Recovery Act.
Start SignatureDated: Issued in Washington, DC, on January 24, 2012.
Henry Kelly,
Acting Assistant Secretary, Energy Efficiency and Renewable Energy, U.S. Department of Energy.
[FR Doc. 2012-3939 Filed 2-17-12; 8:45 am]
BILLING CODE 6450-01-P
Document Information
- Published:
- 02/21/2012
- Department:
- Energy Efficiency and Renewable Energy Office
- Entry Type:
- Notice
- Action:
- Notice of limited waivers.
- Document Number:
- 2012-3939
- Pages:
- 9906-9907 (2 pages)
- PDF File:
- 2012-3939.pdf
- Supporting Documents:
- » Agency Information Collection Activities; Proposals, Submissions, and Approvals
- » Requests for Nominations: Biomass Research and Development Technical Advisory Committee
- » Request forInformation: Challenges and Opportunities for the American Solar Industry
- » Meetings: Water Security
- » Requests for Information: Understanding Catalyst Production and Development Needs at National Laboratories
- » Public Hearings: Navajo Nation Tribal Government Weatherization Assistance Program
- » Meetings: State Energy Advisory Board, Teleconference
- » The SunShot Prize-Solar in Your Community Challenge
- » Agency Information Collection Activities; Proposals, Submissions, and Approvals
- » Requests for Information: Challenges and Opportunities for Sustainable Development of Hydropower in Undeveloped Stream Reaches of the United States