95-4381. Use of the 220-222 MHz Band by the Private Land Mobile Radio Services  

  • [Federal Register Volume 60, Number 35 (Wednesday, February 22, 1995)]
    [Rules and Regulations]
    [Pages 9787-9788]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-4381]
    
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    FEDERAL COMMUNICATIONS COMMISSION
    
    47 CFR Part 90
    
    [PR Docket No. 89-552; DA 95-251]
    
    
    Use of the 220-222 MHz Band by the Private Land Mobile Radio 
    Services
    
    AGENCY: Federal Communications Commission.
    
    ACTION: Interpretation; Extension of compliance date.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Non-nationwide 220-222 MHz licensees are currently required to 
    construct their stations and place them in operation by April 4, 1995. 
    Recently, however, the Commission has received requests from 
    manufacturers of 220-222 MHz radio equipment to extend this deadline. 
    The manufacturers indicate that an extension is necessary because they 
    will not be able to deliver radio equipment to many licensees in time 
    to enable them to construct their stations by April 4, 1995. The 
    Wireless Telecommunications Bureau agrees that some measure of relief 
    should be afforded to non-nationwide 220-222 MHz licensees and has 
    therefore adopted this Order extending the deadline to December 31, 
    1995 for all non-nationwide 220-222 MHz licensees to construct their 
    stations and place them in operation.
    
    DATES: Compliance date extended to December 31, 1995.
    
    FOR FURTHER INFORMATION CONTACT:
    Martin D. Liebman, Policy Division, Wireless Telecommunications Bureau, 
    (202) 418-0620.
    
    SUPPLEMENTARY INFORMATION:
    
    Order
    
    Adopted: February 16, 1995
    Released: February 17, 1995
    
        By the Chief, Wireless Telecommunications Bureau:
        1. On August 19, 1994. the Private Radio Bureau released a Public 
    Notice (DA 94-902)\1\ extending the deadline for construction of non-
    nationwide 220 MHz stations from December 2, 1994 to April 4, 1995.\2\ 
    The Commission, in the Third Report and Order, GN Docket No. 93-252, 
    Implementation of Sections 3(n) and 332 of the Communications Act, 
    released September 23, 1994, 9 FCC Rcd 7988 (1994) 59 FR 59945, 
    November 21, 1994, again identified April 4, 1995 as the construction 
    deadline for non-nationwide 220 MHz stations. In that decision, the 
    Commission noted that the extension ``gives these licensees 
    approximately 12 months from the date of * * * [the March 30, 1994 
    Order] * * * to complete construction and commence operations. * * 
    *''\3\
    
        \1\The responsibility for licensing the 220 MHz radio service 
    now resides in the Wireless Telecommunications Bureau.
        \2\(59 FR 15857, April 5, 1994). The December 2, 1994 deadline 
    was announced in a Private Radio Bureau Order released on March 30, 
    1994 (see 9 FCC Rcd 1739 (1994)). In that Order, the Bureau, citing 
    the court appeal challenging the Commission's 220 MHz licensing 
    procedures (see Evans v. Federal Communications Commission, Order, 
    per curiam, Case No. 92-1317 (D.C. Cir. March 18, 1994)) decided 
    that, upon termination of the appeal, all non-nationwide 220 MHz 
    licensees would be afforded the full 8 months provided under our 
    rules (see 47 C.F.R. Sec. 90.725(f)) to construct and operate their 
    stations. The December 2, 1994 deadline reflected the approximate 8-
    month period following the March 30, 1994 release of the Order.
        \3\See 9 FCC Rcd 8077 (1994).
    ---------------------------------------------------------------------------
    
        2. Recently, the Wireless Telecommunications Bureau received 
    [[Page 9788]] requests from three 220 MHz radio equipment manufacturers 
    to extend the current construction deadline beyond April 4, 1995. The 
    first of these was submitted by SEA, Inc. (SEA) in a letter sent to 
    Regina M. Keeney, Chief, Wireless Telecommunications Bureau, on January 
    17, 1995. SEA asks that the deadline be extended to December 31, 1995 
    for those licensees who have, by placing equipment orders with 
    manufacturers, demonstrated their intent to construct their 220 MHz 
    stations. SEA argues that this extension is needed because the 
    manufacturing capacity of the companies producing 220 MHz equipment 
    ``is not sufficient to fill existing orders by the April 4 deadline'' 
    and that those licensees who have placed orders ``should not be 
    required to forfeit their licenses'' due to manufacturers' inability to 
    deliver equipment by that date. As further support for its request, SEA 
    contends that the Evans v. FCC\4\ court appeal caused licensees to 
    delay placing orders, and that, upon dismissal of the appeal, 
    manufacturers were required suddenly to deliver equipment by a 
    ``single, across-the-board'' deadline applicable to all licensees. SEA 
    observes that, had the court case not occurred, manufacturers would 
    have had to satisfy the less difficult requirement of filling orders to 
    meet the progressive 8-month construction deadlines of the 
    approximately 3,600 individual stations that were authorized over an 
    extended period.
    
        \4\See footnote 2, supra.
    ---------------------------------------------------------------------------
    
        3. E.F. Johnson Company (EFJ), another 220 MHz equipment 
    manufacturer, in a letter sent to Regina M. Keeney on January 25, 1995, 
    supports SEA's request for an extension until December 31, 1995 for 
    those 220 MHz licensees who have timely placed an equipment order with 
    a manufacturer offering type-accepted equipment. EFJ argues that the 
    current ``compressed manufacturing and delivery schedule can simply not 
    be met, even with the considerable resources [the company] will commit 
    to the process'' and contends that if an extension is not granted, the 
    Commission will ``irreparably harm the nascent 220 MHz industry and 
    seriously set back efforts to employ spectrum efficient narrowband 
    technology on a widespread basis.''
        4. Finally, the third manufacturer, Linear Modulation Technology 
    Limited (LMT), a wholly-owned subsidiary of the Securicor Group plc, in 
    a letter sent to Regina M. Keeney on February 1, 1995, also expresses 
    support for the granting of an extension to December 31, 1995. LMT 
    claims that, while it will be able to construct a significant number of 
    220 MHz systems by the April 4, 1995 deadline, it will not be able to 
    deliver and construct by that date many of the orders for the 
    ``approximately one thousand full systems that licensees or managers of 
    220 MHz systems have attempted to place with LMT.'' LMT contends that, 
    if those licensees who have tried to construct their systems by the 
    deadline lose their licenses due to the unavailability of equipment, 
    the prospects for the successful deployment of the 220 MHz service 
    ``will significantly diminish'' and the U.S. 220 MHz industry will be 
    placed ``in serious jeopardy.''\5\
    
        \5\In addition to the letters received from these equipment 
    manufacturers, certain other interested parties, including 220 MHz 
    licensees, have submitted requests to the Wireless 
    Telecommunications Bureau asking for construction deadline 
    extensions of up to three years.
    ---------------------------------------------------------------------------
    
        5. The manufacturers of 220 MHz equipment have indicated that, 
    despite their best efforts, equipment ordered by many non-nationwide 
    220 MHz licensees will not be delivered in time to enable such 
    licensees to construct their stations by April 4, 1995. The Bureau 
    believes that these licensees should be afforded some measure of relief 
    from the current construction deadline. The Bureau is also concerned 
    that a number of licensees, aware of manufacturers' production 
    difficulties, have delayed the placement of orders or have chosen not 
    to place orders at all under the assumption that the orders could not 
    be filled by April 4, 1995. Therefore, to provide relief to all 
    licensees--those that have placed orders as well as those that must 
    still do so--the Bureau extends to December 31, 1995 the deadline for 
    nonnationwide 220 MHz licensees to construct their stations and place 
    them in operation.
        6. Accordingly, for good cause shown, It is Ordered That the 
    requests by SEA Inc., E.F. Johnson Company, Linear Modulation 
    Technology Limited and other parties for extension of the deadline for 
    construction of non-nationwide 220 MHz stations are Granted to the 
    extent indicated herein and otherwise denied.
    
    Federal Communications Commission.
    Regina M. Keeney,
    Chief, Wireless Telecommunications Bureau.
    [FR Doc. 95-4381 Filed 2-21-95; 8:45 am]
    BILLING CODE 6712-01-M
    
    

Document Information

Published:
02/22/1995
Department:
Federal Communications Commission
Entry Type:
Rule
Action:
Interpretation; Extension of compliance date.
Document Number:
95-4381
Dates:
Compliance date extended to December 31, 1995.
Pages:
9787-9788 (2 pages)
Docket Numbers:
PR Docket No. 89-552, DA 95-251
PDF File:
95-4381.pdf
CFR: (1)
47 CFR 90