Start Preamble
AGENCY:
Defense Acquisition Regulation System, Department of Defense (DoD).
ACTION:
Final rule.
SUMMARY:
DoD has issued a final rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to update text addressing uniform line item numbering in DoD contracts. This rule is a result of a transformation initiative undertaken by DoD to dramatically change the purpose and content of the DFARS.
DATES:
Effective Date: February 23, 2006.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Ms. Deborah Tronic, Defense Acquisition Regulations System, OUSD (AT&L) DPAP (DARS), IMD 3C132, 3062 Defense Pentagon, Washington, DC 20301-3062. Telephone (703) 602-0289; facsimile (703) 602-0350. Please cite DFARS Case 2003-D082.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
A. Background
DFARS Transformation is a major DoD initiative to dramatically change the purpose and content of the DFARS. The objective is to improve the efficiency and effectiveness of the acquisition process, while allowing the acquisition workforce the flexibility to innovate. The transformed DFARS will contain only requirements of law, DoD-wide policies, delegations of FAR authorities, deviations from FAR requirements, and policies/procedures that have a significant effect beyond the internal operating procedures of DoD or a significant cost or administrative impact on contractors or offerors. Additional information on the DFARS Transformation initiative is available at http://www.acq.osd.mil/dpap/dars/dfars/transformation/index.htm.
This final rule is a result of the DFARS Transformation initiative. The rule:
- Eliminates certain exceptions to requirements for uniform contract line item numbering at DFARS 204.7102, to promote standardization in contract writing; and
- Deletes procedures for use and numbering of contract exhibits and attachments at DFARS 204.7105. This text has been relocated to the new DFARS companion resource, Procedures, Guidance, and Information, available at http://www.acq.osd.mil/dpap/dars/pgi.
DoD published a proposed rule at 70 FR 19036 on April 12, 2005. Two respondents submitted comments on the proposed rule. A discussion of the comments follows:
1. Comment: DoD should not eliminate the option of using exhibits and attachments, as these are useful tools for the contracting officer.
DoD Response: The rule does not eliminate the use of exhibits and attachments. They are still permitted and are addressed in Subpart 204.71 of the DFARS companion resource, Procedures, Guidance, and Information.
2. Comment: DoD should add guidance on the structuring of contract line items and subline items under performance-based contracts. Start Printed Page 9269
DoD Response: The recommendation is considered to be outside the scope of this DFARS case. Therefore, DoD has made no change to the rule as a result of this comment.
DoD has adopted the proposed rule as a final rule without change.
This rule was not subject to Office of Management and Budget review under Executive Order 12866, dated September 30, 1993.
B. Regulatory Flexibility Act
DoD certifies that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because the rule pertains only to DoD administrative procedures for numbering of contract line items, exhibits, and attachments.
C. Paperwork Reduction Act
The Paperwork Reduction Act does not apply, because the rule does not impose any information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501, et seq.
Start List of SubjectsList of Subjects in 48 CFR Part 204
- Government procurement
Michele P. Peterson,
Editor, Defense Acquisition Regulations System.
Therefore, 48 CFR Part 204 is amended as follows:
End Amendment Part Start Amendment Part1. The authority citation for 48 CFR Part 204 continues to read as follows:
End Amendment Part Start PartPART 204—ADMINISTRATIVE MATTERS
End Part Start Amendment Part2. Section 204.7102 is revised to read as follows:
End Amendment PartPolicy.(a) The numbering procedures of this subpart shall apply to all—
(1) Solicitations;
(2) Solicitation line and subline item numbers;
(3) Contracts as defined in FAR Subpart 2.1;
(4) Contract line and subline item numbers;
(5) Exhibits;
(6) Exhibit line and subline items; and
(7) Any other document expected to become part of the contract.
(b) The numbering procedures are mandatory for all contracts where separate contract line item numbers are assigned, unless—
(1) The contract is an indefinite-delivery type for petroleum products against which posts, camps, and stations issue delivery orders for products to be consumed by them; or
(2) The contract is a communications service authorization issued by the Defense Information Systems Agency's Defense Information Technology Contracting Organization.
3. Section 204.7105 is revised to read as follows:
End Amendment PartContract exhibits and attachments.Follow the procedures at PGI 204.7105 for use and numbering of contract exhibits and attachments.
[FR Doc. 06-1630 Filed 2-22-06; 8:45 am]
BILLING CODE 5001-08-P
Document Information
- Published:
- 02/23/2006
- Department:
- Defense Acquisition Regulations System
- Entry Type:
- Rule
- Action:
- Final rule.
- Document Number:
- 06-1630
- Pages:
- 9268-9269 (2 pages)
- Docket Numbers:
- DFARS Case 2003-D082
- Topics:
- Government procurement
- PDF File:
- 06-1630.pdf
- CFR: (2)
- 48 CFR 204.7102
- 48 CFR 204.7105