06-1632. Defense Federal Acquisition Regulation Supplement; Contractor Insurance/Pension Reviews  

  • Start Preamble

    AGENCY:

    Defense Acquisition Regulations System, Department of Defense (DoD).

    ACTION:

    Final rule.

    SUMMARY:

    DoD has issued a final rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to update text pertaining to Government review of contractor insurance programs, pension plans, and other deferred compensation plans. This rule is a result of a transformation initiative undertaken by DoD to dramatically change the purpose and content of the DFARS.

    DATES:

    Effective Date: February 23, 2006.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Ms. Debra Overstreet, Defense Acquisition Regulations System, OUSD (AT&L) DPAP (DARS), IMD 3C132, 3062 Defense Pentagon, Washington, DC 20301-3062. Telephone (703) 602-0310; facsimile (703) 602-0350. Please cite DFARS Case 2003-D050.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    A. Background

    DFARS Transformation is a major DoD initiative to dramatically change the purpose and content of the DFARS. The objective is to improve the efficiency and effectiveness of the acquisition process, while allowing the acquisition workforce the flexibility to innovate. The transformed DFARS will contain only requirements of law, DoD-wide policies, delegations of FAR authorities, deviations from FAR requirements, and policies/procedures that have a significant effect beyond the internal operating procedures of DoD or a significant cost or administrative impact on contractors or offerors. Additional information on the DFARS Transformation initiative is available at http://www.acq.osd.mil/​dpap/​dars/​dfars/​transformation/​index.htm.

    This final rule is a result of the DFARS Transformation initiative. The DFARS changes—

    • Update and clarify requirements and responsibilities for Government review of a contractor's insurance programs, pension plans, and other deferred compensation plans; and
    • Delete text addressing procedural matters relating to these reviews. This text has been relocated to the new DFARS companion resource, Procedures, Guidance, and Information (PGI), available at http://www.acq.osd.mil/​dpap/​dars/​pgi.

    DoD published a proposed rule at 70 FR 35606 on June 21, 2005. DoD received no comments on the proposed rule. Therefore, DoD has adopted the proposed rule as a final rule without change.

    This rule was not subject to Office of Management and Budget review under Executive Order 12866, dated September 30, 1993.

    B. Regulatory Flexibility Act

    DoD certifies that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because contractor insurance/pension review requirements apply primarily to large business concerns.

    C. Paperwork Reduction Act

    The Paperwork Reduction Act does not apply, because the rule does not impose any information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501, et seq.

    Start List of Subjects

    List of Subjects in 48 CFR Part 242

    • Government procurement
    End List of Subjects Start Signature

    Michele P. Peterson,

    Editor, Defense Acquisition Regulations System.

    End Signature Start Amendment Part

    Therefore, 48 CFR part 242 is amended as follows:

    End Amendment Part Start Amendment Part

    1. The authority citation for 48 CFR part 242 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 41 U.S.C. 421 and 48 CFR Chapter 1.

    End Authority Start Part

    PART 242—CONTRACT ADMINISTRATION AND AUDIT SERVICES

    [Removed]
    End Part Start Amendment Part

    2. Section 242.7300 is removed.

    End Amendment Part Start Amendment Part

    3. Sections 242.7301 through 242.7303 are revised to read as follows:

    End Amendment Part
    General.

    (a) The administrative contracting officer (ACO) is responsible for determining the allowability of insurance/pension costs in Government contracts and for determining the need for a Contractor/Insurance Pension Review (CIPR). Defense Contract Management Agency (DCMA) insurance/pension specialists and Defense Contract Audit Agency (DCAA) auditors assist ACOs in making these determinations, conduct CIPRs when needed, and perform other routine audits as authorized under FAR 42.705 and 52.215-2. A CIPR is a DCMA/DCAA joint review that—

    (1) Provides an in-depth evaluation of a contractor's—

    (i) Insurance programs;

    (ii) Pension plans;

    (iii) Other deferred compensation plans; and

    (iv) Related policies, procedures, practices, and costs; or

    (2) Concentrates on specific areas of the contractor's insurance programs, pension plans, or other deferred compensation plans.

    (b) DCMA is the DoD Executive Agency for the performance of all CIPRs.

    (c) DCAA is the DoD agency designated for the performance of contract audit responsibilities related to Cost Accounting Standards administration as described in FAR Subparts 30.2 and 30.6 as they relate to a contractor's insurance programs, Start Printed Page 9274pension plans, and other deferred compensation plans.

    Requirements.

    Follow the procedures at PGI 242.7302 to determine if a CIPR is needed.

    Responsibilities.

    Follow the procedures at PGI 242.7303 when conducting a CIPR.

    End Supplemental Information

    [FR Doc. 06-1632 Filed 2-22-06; 8:45 am]

    BILLING CODE 5001-08-P

Document Information

Published:
02/23/2006
Department:
Defense Acquisition Regulations System
Entry Type:
Rule
Action:
Final rule.
Document Number:
06-1632
Pages:
9273-9274 (2 pages)
Docket Numbers:
DFARS Case 2003-D050
Topics:
Government procurement
PDF File:
06-1632.pdf
CFR: (4)
48 CFR 242.7300
48 CFR 242.7301
48 CFR 242.7302
48 CFR 242.7303