-
Start Preamble
February 12, 2009.
Take notice that on January 30, 2009, Transcontinental Gas Pipe Line Company, LLC (Transco), Post Office Box 1396, Houston, Texas 77251, filed with the Commission an application under section 7 of the Natural Gas Act (NGA) for a certificate of public convenience and necessity authorizing Transco's 85 North Expansion Project (Project). Specifically, Transco proposes to expand its existing pipeline system in its Southern Market area to provide an additional 308,500 dekatherms per day (dt/day) of incremental firm transportation service to four shippers. Transco proposes to complete the project in two phases, with 90,000 dt/day to be placed in-service July 1, 2010, and an additional 218,500 dt/day to be placed in-service May 1, 2011. Transco also requests authorization to abandon four obsolete compressor units at Transco's existing Compressor Station No. 100 and two centrifugal compressors at Transco's existing Compressor Station No. 125, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY, (202) 502-8659.
Any questions regarding this application should be directed to Scott Turkington, Rates and Regulatory, Transcontinental Gas Pipe Line Company, Post Office Box 1396, Houston, Texas 77251-1396, phone (713) 215-3391, e-mail scott.c.turkington@williams.com.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.Start Printed Page 8079
There are two ways to become involved in the Commission's review of this application. First, any person wishing to obtain legal status by becoming a party to this proceeding should file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10) by the comment date, below. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.
However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to the project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest.
Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission's environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission's environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission's final order.
The Commission strongly encourages electronic filings of comments, protests, and interventions via the Internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site (http://www.ferc.gov) under the “e-Filing” link. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.
Comment Date: March 5, 2009.
Start SignatureKimberly D. Bose,
Secretary.
[FR Doc. E9-3678 Filed 2-20-09; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Effective Date:
- 3/5/2009
- Published:
- 02/23/2009
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- E9-3678
- Dates:
- March 5, 2009.
- Pages:
- 8078-8079 (2 pages)
- Docket Numbers:
- Docket No. CP09-57-000
- EOCitation:
- of 2009-02-12
- PDF File:
- e9-3678.pdf