98-4673. Intent To Prepare a Draft Environmental Impact Statement (DEIS) for the East Waterway Channel Deepening Project, Seattle Harbor, Seattle, Washington  

  • [Federal Register Volume 63, Number 36 (Tuesday, February 24, 1998)]
    [Notices]
    [Pages 9213-9215]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-4673]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF DEFENSE
    
    Department of the Army, Corps of Engineers
    
    
    Intent To Prepare a Draft Environmental Impact Statement (DEIS) 
    for the East Waterway Channel Deepening Project, Seattle Harbor, 
    Seattle, Washington
    
    AGENCY: U.S. Army Corps of Engineers, Seattle District, DoD.
    
    ACTION: Notice of intent.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Corps of Engineers has been directed by Section 356 of the 
    Water Resources Development Act (WRDA) of 1996 to (1) study the 
    feasibility of deepening of a 750-foot-wide segment of existing federal 
    channel in the East Waterway (Duwamish River) from Elliott Bay to 
    Terminal 25 to a depth of up to 51 feet, and (2) if feasible, to 
    implement deepening as routine maintenance. Section 356 of WRDA 96 
    further directs the Corps to coordinate with the Port of Seattle 
    regarding use of Slip 27 as a nearshore confined dredged material 
    disposal site. Plans call for the dredging and disposal of 
    approximately 850,000 cubic yards of sediment from an approximately 112 
    acre area in East Waterway. Of this total, approximately 253,000 cubic 
    yards are known to be contaminated to the extent that they would not 
    qualify for disposal at the Elliott Bay Puget Sound Dredge Disposal 
    Analysis (PSDDA) open water site. Based on sediment sampling conducted 
    by the Port of Seattle, an additional 200,000 cubic yards may be 
    similarly contaminated. Dredged material suitable for openwater 
    disposal will either be placed at the PSDDA site in Elliott Bay, or at 
    a beneficial use site, should such a need be identified.
        A range of alternatives will be examined for placement of the 
    contaminated dredged material, including: (1) a nearshore confined 
    facility, (2) an offshore contained aquatic disposal (CAD) facility, 
    (3) an upland confined disposal facility, and (4) disposal in a solid 
    waste landfill. Key environmental issues in the DEIS will include: (1) 
    impacts on an important juvenile salmon migration and feeding route; 
    (2) potential loss of 12 acres of productive benthic habitat at Slip 27 
    or Terminal 90/91; (3) impacts on kelp beds and shorebird/waterfowl 
    habitat; (4) dredging and disposal of up to 450,000 cubic yards of 
    contaminated sediments with short-term adverse impacts in the water 
    column at the dredging and disposal site; (4) beneficial impacts in 
    that the dredging would
    
    [[Page 9214]]
    
    remove contaminated sediments from the waterway, and (5) Native 
    American concerns, related to impacts on Tribal fishing access and 
    operations in a usual and accustomed fishing area, and on salmon 
    habitat. In addition, it is anticipated that Chinook salmon will be 
    proposed for listing as threatened in Puget Sound in early 1998.
    
    FOR FURTHER INFORMATION CONTACT:
    Questions regarding the scoping process or preparation of the DEIS may 
    be directed to Dr. Stephen Martin, Technical Services Branch, U.S. Army 
    Corps of Engineers, P.O. Box 3755, 4735 East Marginal Way S., Seattle, 
    Washington, 98134-3755, (206) 764-3631.
    
    SUPPLEMENTARY INFORMATION:
    
    1. Proposed Action
    
        The East Waterway, located in Puget Sound's Elliott Bay at Seattle, 
    Washington, is part of the federally authorized East, West and Duwamish 
    Waterways navigation channel. The East Waterway is approximately 5,800 
    feet long and has an authorized width of 750 feet and depth of 39 feet 
    Mean Lower Low Water. The waterway is deeper than the federally 
    authorized depth throughout most of its reach and is not currently 
    maintained by the federal government. The East Waterway provides access 
    to the Port of Seattle's container terminals 18, 25, and 30. The 
    container fleet is rapidly changing with ships becoming larger and 
    having greater capacity. The most recent additions to the post-Panamax 
    fleet are ships which are in excess of 900 feet long, 130 feet wide, 
    have a design operating draft of 46 feet, and a capacity in excess of 
    5,000 twenty foot equivalent units. As a result, the Port of Seattle is 
    concerned that current and potential tenants may elect not to use the 
    Port's facilities due to depth limitations in East Waterway. The Port 
    has stated that a deeper channel, specifically the area that allows 
    access to berths 1 through 5 of Terminal 18, needs to be constructed by 
    calendar year 2001. The deep water access to berths 1 through 5 in the 
    East Waterway requires dredging in the federal channel.
        As directed by Section 356 of the Water Resources Development Act 
    of 1996, the Corps of Engineers is conducting an Evaluation Study with 
    the following project features: dredging in the East Waterway (Seattle 
    Harbor) to a depth of up to 51 feet of the 750-foot wide segment of the 
    federal channel, construction of a disposal site for dredged material 
    that is unsuitable for open water disposal at the Elliott Bay PSDDA 
    disposal site, and construction of all mitigation features. If this is 
    determined to be feasible, the channel would be deepened as part of the 
    Federal project maintenance. The Port of Seattle would provide the 
    dredged material disposal site(s). Major project features are as 
    follows: (1) channel improvement dredging by the Corps to a depth of up 
    to 51 feet plus 1 foot allowable overdepth of a 750-foot-wide segment 
    of existing federal channel of the Duwamish River East Waterway; (2) 
    construction of a disposal site(s) for dredge materials not acceptable 
    for disposal at Elliott Bay PSDDA disposal site; (3) construction of 
    mitigation features required for the project, and any required 
    monitoring of mitigation improvements; (4) dredging and disposal of 
    about 850,000 cubic yards of sediment from East Waterway. Of this 
    total, approximately 253,000 cubic yards are known to be contaminated 
    to the extent that they would not qualify for disposal at the Elliott 
    Bay PSDDA open water site; and (5) total dredging acreage for the 
    project is approximately 112 acres.
    
    2. Alternatives
    
        In addition to the ``No Action'' alternative, the draft EIS will 
    evaluate a suite of commonly used disposal alternatives for the 
    placement of dredged material that will not qualify for disposal at the 
    PSDDA open water site. Included in the evaluation will be a 
    comprehensive discussion of the environmental impacts of each 
    alternative. The final EIS will identify the environmentally preferred 
    disposal alternative. Disposal alternatives to be evaluated will 
    include: (1) construction and operation of a Nearshore Confined 
    Disposal Facility including Slip 27 in the East Waterway, and Terminal 
    91 in Elliott Bay; (2) construction and operation of an Upland Confined 
    Disposal Facility; (3) construction and operation of a deep water 
    Contained Aquatic Disposal Facility; (4) disposal in a Solid Waste 
    Landfill; (5) a combination of the above alternatives; and (6) 
    alternative fill designs at the proposed fill location. Dredging 
    alternatives to be evaluated include established mechanical and 
    hydraulic methods.
    
    3. Scoping and Public Involvement
    
        Public involvement will be sought during the scoping and conduct of 
    the study in accordance with NEPA and SEPA procedures. A public meeting 
    will be held during public review of the draft EIS. Further meetings 
    will be scheduled as needed. A public scoping process will be initiated 
    to clarify issues of major concern, identify studies that might be 
    needed in order to analyze and evaluate impacts, and obtain public 
    input on the range and acceptability of alternatives. This Notice of 
    Intent formally commences the joint scoping process under NEPA. As part 
    of the scoping process, all affected Federal, state, and local 
    agencies, Indian Tribes, and other interested private organizations, 
    including environmental interest groups, are invited to comment on the 
    scope of the EIS. Comments are requested concerning project 
    alternatives, mitigation measures, probable significant environmental 
    impacts, and permits or other approvals that may be required. To date, 
    the following areas have been identified to be analyzed in depth in the 
    draft EIS: (1) extent and degree of sediment contamination in East 
    Waterway; (2) dredging and disposal impacts on water quality; (3) 
    impacts on juvenile salmon, as East Waterway is a major migration and 
    feeding route for juvenile salmon, and is an area that they use for 
    saltwater physiological adaptation; the project would result in the 
    loss of several acres of intertidal and shallow subtidal fisheries 
    habitat; (4) impacts on benthic organisms and their habitat at both 
    nearshore confined disposal and contained aquatic disposal sites; e.g. 
    with the construction of a nearshore confined fill area, there would be 
    a loss of about 12 acres of productive benthic habitat that contributes 
    to the aquatic food web of Elliott Bay; (5) other estuarine resources, 
    as with construction of a nearshore confined fill area, there would be 
    losses of other estuarine resources, including shorebirds and waterfowl 
    habitat and kelp beds; (6) Native American concerns including dredging 
    and disposal of contaminated sediments, increased shipping, and 
    nearshore fills and their impacts on Tribal fishing access and 
    operations, and on salmon habitat; also, concerns over cumulative 
    impacts of recent shoreline developments in Elliott Bay on adjudicated 
    treaty fishing rights; (7) beneficial impacts, in that dredging would 
    remove up to 450,000 cubic yards of contaminated sediments over an 
    extent of about 112 acres of East Waterway, thereby removing a 
    substantive source of contaminants that affect the Elliott Bay food 
    web; and (8) threatened and endangered Species, as the DEIS will 
    evaluate the impact of the dredging/disposal project on bald eagles 
    that are known to nest within two miles of the project site; it is 
    likely that Chinook salmon will be proposed for listing as threatened 
    in Elliott Bay in early 1998 and may be listed as threatened sometime 
    during 1998. The
    
    [[Page 9215]]
    
    environmental review process will be comprehensive and will integrate 
    and satisfy the requirements of NEPA (federal) and SEPA (Washington 
    State), and other relevant Federal, state, and local environmental 
    laws.
    
    4. Scoping Meeting
    
        A notice of the scoping meeting will be mailed to all involved 
    agencies and individuals known to have an interest in this project. A 
    scoping workshop will be held on March 5, 1998, at the Port of 
    Seattle's Commission Chambers, 2711 Alaskan Way (Pier 69) from 4:00 to 
    6:00 PM. Verbal or written comments will be accepted at the scoping 
    meeting, or written comments may be sent to Dr. Stephen Martin at the 
    above address on or before March 20, 1998.
    
    5. Other Environmental Review, Coordination, and Permit Requirements
    
        Other environmental review, coordination, and permit requirements 
    include preparation of a Section 404 (b)(1) evaluation by the Corps of 
    Engineers; and consultation among the Corps, the U.S. Fish and Wildlife 
    Service, and the State of Washington per Section 7 of the Endangered 
    Species Act. Coordination will also be initiated with the U.S. Fish and 
    Wildlife Service to meet the requirements of the Fish and Wildlife 
    Coordination Act.
    
    6. Availability of Draft EIS
    
        The draft EIS is scheduled for release in March 1999.
    
        Dated: February 12, 1998.
    James M. Rigsby,
    Colonel, Corps of Engineers, District Engineer.
    [FR Doc. 98-4673 Filed 2-23-98; 8:45 am]
    BILLING CODE 3710-ER-M
    
    
    

Document Information

Published:
02/24/1998
Department:
Engineers Corps
Entry Type:
Notice
Action:
Notice of intent.
Document Number:
98-4673
Pages:
9213-9215 (3 pages)
PDF File:
98-4673.pdf