DEPARTMENT OF AGRICULTURE
Oglethorpe Power Corp.; Finding of No Significant Impact
AGENCY: Rural Electrification Administration, USDA.
ACTION: Notice of finding of no significant impact.
-----------------------------------------------------------------------
SUMMARY: Notice is hereby given that the Rural Electrification
Administration (REA) has made a Finding of No Significant Impact with
respect to the potential environmental impacts resulting from a
proposal by Oglethorpe Power Corporation to construct a 500 kV
transmission line between its Rocky Mountain Switching Station at its
Rocky Mountain Pumped Storage Hydro-Generation Facility located
northwest of the City of Rome, in Floyd County, Georgia, to Georgia
Power Company's 230/115 kV Pinson Substation located near Pinson, also
in Floyd County, Georgia.
The Finding of No Significant Imapct is based on a Borrower's
Environmental Report prepared by Oglethorpe Power Corporation and
submitted to REA. REA conducted an independent evaluation of the report
and concurs with its scope and content. In accordance with REA
Environmental Policies and Procedures, 7 CFR 1794.61, REA has adopted
the Borrower's Environmental Report as its Environmental Assessment for
the 500 kV Rocky Mountain to Pinson Transmission Line.
FOR FURTHER INFORMATION CONTACT: Lawrence R. Wolfe, Chief,
Environmental Compliance Branch, Electric Staff Division, Rural
Electrification Administration, South Agriculture Building, Washington,
DC 20250, telephone (202) 720-1784.
SUPPLEMENTARY INFORMATION: The length of the transmission line is
approximately 18 miles. The proposed transmission line would require a
180 foot wide right-of-way easement. The right-of-way width may
increase to 200 feet in areas where a transmission line span (spacing
between structures) will exceed 1,500 feet. Lattice steel towers with
four ``feet'' anchored to concrete piers will be used to construct the
proposed transmission line. A triple bundle 1113 ACSR conductor has
been selected for the transmission line. It is projected that the
transmission line will be constructed by the summer of 1995. Although
the transmission line will be designed for 500 kV operation, it will be
initially energized and operated at 230 kV.
Alternatives considered to the project as proposed were no action,
construction of a 230 kV transmission line now and a 500 kV
transmission line at a later date, and three transmission line
corridors for the proposed transmission line.
Copies of the Environmental Assessment and Finding Of No
Significant Imapct are available for review at, or can be obtained
from, REA at the address provided herein or from Mr. John Lasseter,
Oglethorpe Power Corporation, 2100 East Exchange Place, Tucker, Georgia
30085-1349, telephone (404) 270-7600.
Dated: February 17, 1994.
Wally Beyer,
Administrator.
[FR Doc. 94-4232 Filed 2-24-94; 8:45 am]