    Oglethorpe Power Corp.; Finding of No Significant Impact
    
    AGENCY: Rural Electrification Administration, USDA.
    
    ACTION: Notice of finding of no significant impact.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Notice is hereby given that the Rural Electrification 
    Administration (REA) has made a Finding of No Significant Impact with 
    respect to the potential environmental impacts resulting from a 
    proposal by Oglethorpe Power Corporation to construct a 500 kV 
    transmission line between its Rocky Mountain Switching Station at its 
    Rocky Mountain Pumped Storage Hydro-Generation Facility located 
    northwest of the City of Rome, in Floyd County, Georgia, to Georgia 
    Power Company's 230/115 kV Pinson Substation located near Pinson, also 
    in Floyd County, Georgia.
        The Finding of No Significant Imapct is based on a Borrower's 
    Environmental Report prepared by Oglethorpe Power Corporation and 
    submitted to REA. REA conducted an independent evaluation of the report 
    and concurs with its scope and content. In accordance with REA 
    Environmental Policies and Procedures, 7 CFR 1794.61, REA has adopted 
    the Borrower's Environmental Report as its Environmental Assessment for 
    the 500 kV Rocky Mountain to Pinson Transmission Line.
    
    FOR FURTHER INFORMATION CONTACT: Lawrence R. Wolfe, Chief, 
    Environmental Compliance Branch, Electric Staff Division, Rural 
    Electrification Administration, South Agriculture Building, Washington, 
    DC 20250, telephone (202) 720-1784.
    
    SUPPLEMENTARY INFORMATION: The length of the transmission line is 
    approximately 18 miles. The proposed transmission line would require a 
    180 foot wide right-of-way easement. The right-of-way width may 
    increase to 200 feet in areas where a transmission line span (spacing 
    between structures) will exceed 1,500 feet. Lattice steel towers with 
    four ``feet'' anchored to concrete piers will be used to construct the 
    proposed transmission line. A triple bundle 1113 ACSR conductor has 
    been selected for the transmission line. It is projected that the 
    transmission line will be constructed by the summer of 1995. Although 
    the transmission line will be designed for 500 kV operation, it will be 
    initially energized and operated at 230 kV.
        Alternatives considered to the project as proposed were no action, 
    construction of a 230 kV transmission line now and a 500 kV 
    transmission line at a later date, and three transmission line 
    corridors for the proposed transmission line.
        Copies of the Environmental Assessment and Finding Of No 
    Significant Imapct are available for review at, or can be obtained 
    from, REA at the address provided herein or from Mr. John Lasseter, 
    Oglethorpe Power Corporation, 2100 East Exchange Place, Tucker, Georgia 
    30085-1349, telephone (404) 270-7600.
    
        Dated: February 17, 1994.
    Wally Beyer,
    Administrator.
    [FR Doc. 94-4232 Filed 2-24-94; 8:45 am]
    BILLING CODE 3410-15-P
    
    
    

Document Information

Published:
02/25/1994
Department:
Agriculture Department
Entry Type:
Uncategorized Document
Action:
Notice of finding of no significant impact.
Document Number:
94-4232
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: February 25, 1994