99-4816. Wolf Creek Nuclear Operating Corporation; Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing  

  • [Federal Register Volume 64, Number 38 (Friday, February 26, 1999)]
    [Notices]
    [Pages 9546-9549]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-4816]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-482]
    
    
    Wolf Creek Nuclear Operating Corporation; Notice of Consideration 
    of Issuance of Amendment to Facility Operating License and Opportunity 
    for a Hearing
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an amendment to Facility Operating License No. 
    NPF-42, issued to the Wolf Creek Nuclear Operating Corporation (WCNOC 
    or the licensee), for operation of the Wolf Creek Generating Station 
    (WCGS), located in Coffey County, Kansas.
        The initial Notice of Consideration of Issuance of Amendment to 
    Facility Operating License and Opportunity for Hearing was published in 
    the Federal Register on October 5, 1998 (63 FR 53471). The information 
    included in the supplemental letters indicates that the original 
    notice, that included fourteen proposed beyond-scope issues (BSIs) to 
    the Improved Technical Specifications (ITS) conversion, needs to be 
    expanded to add sixteen new BSIs and revised to delete 8 previous BSIs. 
    This includes a total of twenty-two BSIs.
        The proposed amendment, requested by the licensee in a letter dated 
    May 15, 1997, as supplemented by letters dated June 30, August 5, 
    August 28, September 24, October 16, October 23, November 24, December 
    2, December 17, December 21, 1998 and February 4, 1999, would represent 
    a full conversion from the current Technical Specifications (CTS) to a 
    set of improved Technical Specifications (ITS) based on NUREG-1431, 
    ``Standard Technical Specifications, Westinghouse Plants,'' Revision 1, 
    dated April 1995. NUREG-1431 has been developed by the Commission's 
    staff through working groups composed of both NRC staff members and 
    industry representatives, and has been endorsed by the staff as part of 
    an industry-wide initiative to standardize and improve the Technical 
    Specifications for nuclear power plants. As part of this submittal, the 
    licensee has applied the criteria contained in the Commission's ``Final 
    Policy Statement on Technical Specification Improvements for Nuclear 
    Power Reactors (Final Policy Statement),'' published in the Federal 
    Register on July 22, 1993 (58 FR 39132), to the CTS, and, using NUREG-
    1431 as a basis, proposed an ITS for WCGS. The criteria in the Final 
    Policy Statement were subsequently added to 10 CFR 50.36, ``Technical 
    Specifications,'' in a rule change that was published in the Federal 
    Register on July 19, 1995 (60 FR 36953) and became effective on August 
    18, 1995.
        This conversion is a joint effort in concert with three other 
    utilities: Pacific Gas & Electric Company for Diablo Canyon Power 
    Plant, Units 1 and 2 (Docket Nos. 50-275 and 323); TU Electric for 
    Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 
    and 50-446); and Union Electric Company for Callaway Plant (Docket No. 
    50-483). It is a goal of the four utilities to make the ITS for all the 
    plants as similar as possible. This joint effort includes a common 
    methodology for the licensees in marking-up the CTS and NUREG-1431 
    Specifications, and the NUREG-1431 Bases, that has been accepted by the 
    staff. This includes the convention that, if the words in the CTS 
    specification are not the same as the words in the ITS specification 
    but they mean the same or have the same requirements as the words in 
    the ITS specification, the licensee does not indicate or describe the 
    change to the CTS.
        This common methodology is discussed at the end of Enclosure 2, 
    ``Mark-Up of Current TS''; Enclosure 5a, ``Mark-Up of NUREG-1431 
    Specifications''; and Enclosure 5b, ``Mark-Up of NUREG-1431 Bases, for 
    each of the 14 separate ITS sections that were submitted with the 
    licensee's application. For each of the 14 ITS sections, there is also 
    the following: Enclosure 1, the cross reference table connecting each 
    CTS specification (i.e., limiting condition for operation, required 
    action, or surveillance requirement) to the associated ITS 
    specification, sorted by both CTS and ITS Specifications; Enclosure 3, 
    the description of the changes to the CTS section and the comparison 
    table showing which plants (of the four licensees in the joint effort) 
    that each change applies to; Enclosure 4, the no significant hazards 
    consideration (NHSC) of 10 CFR 50.91 for the changes to the CTS with 
    generic NHSCs for administrative, more restrictive, relocation, and 
    moving-out-of-CTS changes, and individual NHSCs for less restrictive 
    changes and with the organization of the NHSC evaluation discussed in 
    the beginning of the enclosure; and Enclosure 6, the descriptions of 
    the differences from NUREG-1431 specifications and the comparison table 
    showing which plants (of the four licensees in the joint effort) that 
    each difference applies to. Another convention of the common 
    methodology is that the technical justifications for the less 
    restrictive changes are included in the NHSCs.
        The licensee has categorized the proposed changes to the CTS into 
    four general groupings. These groupings are characterized as 
    administrative changes, relocated changes, more restrictive changes and 
    less restrictive changes.
        Administrative changes are those that involve restructuring, 
    renumbering, rewording, interpretation and complex rearranging of 
    requirements and other changes not affecting technical content or 
    substantially revising an operating requirement. The reformatting, 
    renumbering and rewording process reflects the attributes of NUREG-1431 
    and does not involve technical changes to the existing TS. The proposed 
    changes include (a) providing the appropriate numbers, etc., for NUREG-
    1431 bracketed information (information that must be supplied on a 
    plant-specific basis, and which may change from plant to plant), (b) 
    identifying plant-specific wording for system names, etc., and (c) 
    changing NUREG-1431 section wording to conform to existing licensee 
    practices. Such changes are administrative in nature and do not impact 
    initiators of analyzed events or assumed mitigation of accident or 
    transient events.
        Relocated changes are those involving relocation of requirements 
    and surveillances for structures, systems, components, or variables 
    that do not meet the criteria for inclusion in TS. Relocated changes 
    are those current TS requirements that do not satisfy or fall within 
    any of the four criteria specified in the Commission's policy statement 
    and may be relocated to appropriate licensee-controlled documents. 
    There will be a license condition to require the licensee to implement 
    the relocations as described in its letters.
        The licensee's application of the screening criteria is described 
    in Attachment 2 to its June 2, 1997, submittal, which is entitled, 
    ``General Description and Assessment.'' The affected structures, 
    systems, components or variables are not
    
    [[Page 9547]]
    
    assumed to be initiators of analyzed events and are not assumed to 
    mitigate accident or transient events. The requirements and 
    surveillances for these affected structures, systems, components, or 
    variables will be relocated from the TS to administratively controlled 
    documents such as the quality assurance program, the updated safety 
    analysis report (USAR), the ITS BASES, the Technical Requirements 
    Manual (TRM) incorporated by reference in the USAR, the Core Operating 
    Limits Report (COLR), the Offsite Dose Calculation Manual (ODCM), the 
    Inservice Testing (IST) Program, or other licensee-controlled 
    documents. Changes made to these documents will be made pursuant to 10 
    CFR 50.59 or other appropriate control mechanisms, and may be made 
    without prior NRC review and approval. In addition, the affected 
    structures, systems, components, or variables are addressed in existing 
    surveillance procedures that are also subject to 10 CFR 50.59. These 
    proposed changes will not impose or eliminate any requirements.
        More restrictive changes are those involving more stringent 
    requirements compared to the CTS for operation of the facility. These 
    more stringent requirements do not result in operation that will alter 
    assumptions relative to the mitigation of an accident or transient 
    event. The more restrictive requirements will not alter the operation 
    of process variables, structures, systems, and components described in 
    the safety analyses. For each requirement in the CTS that is more 
    restrictive than the corresponding requirement in NUREG-1431 that the 
    licensee proposes to retain in the ITS, they have provided an 
    explanation of why they have concluded that retaining the more 
    restrictive requirement is desirable to ensure safe operation of the 
    facility because of specific design features of the plant.
        Less restrictive changes are those where CTS requirements are 
    relaxed or eliminated, or new plant operational flexibility is 
    provided. The more significant ``less restrictive'' requirements are 
    justified on a case-by-case basis. When requirements have been shown to 
    provide little or no safety benefit, their removal from the TS may be 
    appropriate. In most cases, relaxations previously granted to 
    individual plants on a plant-specific basis were the result of (a) 
    generic NRC actions, (b) new NRC staff positions that have evolved from 
    technological advancements and operating experience, or (c) resolution 
    of the Owners Groups' comments on the Improved Standard Technical 
    Specifications. Generic relaxations contained in NUREG-1431 were 
    reviewed by the staff and found to be acceptable because they are 
    consistent with current licensing practices and NRC regulations. The 
    licensee's design will be reviewed to determine if the specific design 
    basis and licensing basis are consistent with the technical basis for 
    the model requirements in NUREG-1431, thus providing a basis for these 
    revised TS, or if relaxation of the requirements in the current TS is 
    warranted based on the justification provided by the licensee.
        These administrative, relocated, more restrictive, and less 
    restrictive changes to the requirements of the CTS do not result in 
    operations that will alter assumptions relative to mitigation of an 
    analyzed accident or transient event. Some of these changes will revise 
    or add new surveillance requirements (SRs) compared to the SRs in the 
    CTS. There may be scheduling issues with performance of these new or 
    revised SRs. There will be a license condition to define the schedule 
    to begin performing these SRs.
        In addition to the proposed changes solely involving the 
    conversion, there are also changes proposed that are different than the 
    requirements in both the CTS and the improved Standard Technical 
    Specifications (NUREG-1431). The first six BSIs listed below were 
    included in the initial notice and still apply to the conversion, 
    however there are sixteen additional BSIs. The additional beyond-scope 
    issues (BSIs) are discussed in the licensee's response to requests for 
    additional information (RAIs) from the NRC staff. These proposed 
    beyond-scope issues to the ITS conversion are as follows:
        1. ITS LCOs 3.4.5, 3.4.10, 3.4.11, and 3.4.12--revise applicability 
    and add a note (to ITS 3.4.5) to add reactor coolant pump start 
    restrictions for low temperature overpressure protection for the 
    reactor coolant system.
        2. ITS LCO 3.4.7 and SRs 3.4.5.2, 3.4.6.2, and 3.4.7.2--revise 
    steam generator level requirements in Modes 3, 4, and 5 to ensure tubes 
    are covered.
        3. ITS SR 3.6.3.7--note added to not require leak rate test of 
    containment purge valves with resilient seals when penetration flow 
    path is isolated by leak-tested blank flange.
        4. ITS LCO 3.8.6--revise battery float voltage in Table 3.8.6-1.
        5. ITS SRs 3.8.4.1 and 3.8.4.6--revises the minimum allowable 
    battery voltage.
        6. ITS SR 3.8.4.8--revise restriction for rated capacity for the 
    installed AT&T round cell batteries.
        The sixteen additional BSIs are listed below with the associated 
    change number, RAI number, RAI response submittal date, and description 
    of the change.
        7. Change 4-05-LS-31(ITS3/4.4), question Q3.4.11-3, response letter 
    dated December 21, 1998. The change would revise actions of CTS LCO 
    3.4.4 for inoperable power-operated relief valves and their associated 
    block valves to be in hot shutdown by replacing it with the requirement 
    to reduce Tavg to <500 deg.f.="" for="" consistency,="" the="" actions="" of="" cts="" lco="" 3.4.7,="" for="" specific="" activity="" of="" the="" reactor="" coolant,="" would="" be="" similarly="" revised="" and="" the="" time="" to="" reach="" the="" required="">avg 
    extended by 6 hours.
        8. Change 1-22-M (ITS3/4.3), question Q3.3-49, response letter 
    dated November 24, 1998. The change was requested in the original 
    application. Quarterly channel operational tests (COTs) would be added 
    to CTS Table 4.3-1 for the power range neutron flux-low, intermediate 
    range neutron flux, and source range flux trip functions. The CTS only 
    require a COT prior to startup for these functions. New Note 19 would 
    be added to require that the new quarterly COT be performed within 12 
    hours after reducing power below P-10 for the power range and 
    intermediate range instrumentation (P-10 is the dividing point marking 
    the Applicability for these trip functions), if not performed within 
    the previous 92 days. New Note 20 would be added such that the P-6 and 
    P-10 interlocks are verified to be in their required state during all 
    COTs on the power range neutron flux-low and intermediate range neutron 
    flux trip functions.
        9. Change 1-7-LS-3 (ITS 3/4.3), question Q3.3-107, response letter 
    dated December 2, 1998. The change was requested in the original 
    application and would (1) extend the completion time for CTS Action 3.b 
    from no time specified to 24 hours for channel restoration or changing 
    the power level to either below P-6 or above P-10, (2) reduce the 
    applicability of the intermediate range neutron flux channels and 
    delete CTS Action 3.a as being outside the revised applicability, and 
    (3) add a less restrictive new action that requires immediate 
    suspension of operations involving positive reactivity additions and a 
    power reduction below P-6 within 2 hours, but no longer require a 
    reduction to Mode 3.
        10. Change 1-9-A (ITS 5.0), question Q5.2-1, response letter dated 
    September 24, 1998. A new administrative change was added. The CTS 
    6.2.2.e requirements concerning overtime would be replaced by a 
    reference to
    
    [[Page 9548]]
    
    administrative procedures for the control of working hours.
        11. Change 1-15-A (ITS 5.0), question Q5.2-1, response letter dated 
    September 24, 1998. A new administrative change was added. The proposed 
    change would revise CTS 6.2.2.G to eliminate the title of Shift 
    Technical Advisor. The engineering expertise is maintained on shift, 
    but a separate individual would not be required as allowed by a 
    Commission Policy Statement.
        12. Change 2-18-A (ITS 5.0), question Q5.2-1, response letter dated 
    September 24, 1998. The proposed change is a revision to the original 
    application. The dose rate limits in the Radioactive Effluent Controls 
    Program for releases to areas beyond the site boundary would be revised 
    to reflect 10 CFR Part 20 requirements.
        13. Change 2-22-A (ITS 5.0), question Q5.2-1, response letter dated 
    September 24, 1998. A new administrative change is added. The 
    Radioactive Effluents Controls Program would be revised to include 
    clarification statements denoting that the provisions of CTS 4.0.2 and 
    4.0.3, which allow extensions to surveillance frequencies, are 
    applicable to these activities.
        14. Change 3-11-A (ITS 5.0), question Q5.2-1, response letter dated 
    September 24, 1998. The proposed change is a revision to the original 
    application. CTS 6.12, which provides high radiation area access 
    control alternatives pursuant to 10 CFR 20.203(c)(2), would be revised 
    to meet the current requirements in 10 CFR Part 20 and the guidance in 
    NRC Regulatory Guide 8.38, ``Control of Access to High and Very High 
    Radiation Areas in Nuclear Power Plants,'' on such access controls.
        15. Change 3-18-LS-5 (ITS 5.0), question Q5.2-1, response letter 
    dated September 24, 1998. Proposed change 3-18-A was requested in the 
    original application and is revised to be a new less restrictive 
    change. The CTS 6.9.1.8 requirement to provide documentation of all 
    challenges to the power operated relief valves (PORVs) and safety 
    valves on the reactor coolant system would be deleted. This is based on 
    NRC Generic Letter 97-02, ``Revised Contents of the Monthly Operating 
    Report,'' which reduced the requirements for submitting such 
    information to the NRC. The GL did not include these valves for 
    information to be submitted.
        16. Change 9-17-LS-24 (ITS 3.4/4), question Q 9-17-LS-24, response 
    letter dated September 24, 1998. The proposed change was requested in 
    the original application. The proposed change would add four notes to 
    CTS LCO 3.4.9.3, to reflect CTS SR 4.5.3.2, LCO 3.5.4 actions, LCO 
    3.5.4 applicability notes, and the accumulator action added in CN 9-10-
    M for CTS 3/4.4. Note 1 on centrifugal charging pump (CCP) swap 
    operations would be a relaxation of the CTS because it allows both CCPs 
    to be capable of injecting into the RCS for up to 4 hours throughout 
    low temperature overpressure protection (LTOP) applicability.
        17. Change 10-20-LS-39 (ITS 3/4.7), question Q3.7.10-14, response 
    letter dated October 16, 1998. The proposed change was requested in the 
    original application and would revise and add an action to CTS LCOs 
    3.7.6 and 3.7.7 for ventilation system pressure envelope degradation 
    that allows 24 hours to restore the control room pressure envelope 
    through repairs before requiring the unit to perform an orderly 
    shutdown. The new action has a longer allowed outage time than LCO 
    3.0.4 which the CTS would require to be entered immediately. This 
    change recognizes that the ventilation trains associated with the 
    pressure envelope would still be operable.
        18. Change 4-8-LS-34 (ITS 3/4.4), question Q3.4.11-2, response 
    letter dated September 24, 1998. The proposed change was requested in 
    the original application. The proposed change would limit the CTS SRs 
    4.4.4.1 and 4.4.4.2 requirements to perform the 92 day surveillance of 
    the pressurizer PORV block valves and the 18 month surveillance of the 
    pressurizer PORVs (i.e., perform one complete cycle of each valve) to 
    only Modes 1 and 2.
        19. Change 4-9-LS-36, (ITS 3/4.4), question Q3.4.11-4, response 
    letter dated September 24, 1998. The proposed change in the original 
    application is revised to add a note to Action d for CTS LCO 3.4.4 that 
    would state that the action does not apply when the PORV block valves 
    are inoperable as a result of power being removed from the valves in 
    accordance with Action b or c for an inoperable PORV.
        20. Change 1-60-A, (ITS3/4.3), question TR3.3-0073.3, response 
    letter dated December 21, 1998. A new administrative change is being 
    added. The frequency for conducting the trip actuating device 
    operational test (TADOT) for the turbine trip of the reactor trip 
    instrumentation surveillance requirements in CTS Table 4.3-1 would be 
    changed from ``prior to reactor startup'' to ``prior to exceeding the 
    P-9 interlock whenever the unit has been in Mode 3.''
        21. Change 1-70-M (ITS 3/4.8), question Q3.8.2-04, response letter 
    dated December 17, 1998. A new more restrictive change is being added. 
    The change would add shutdown requirements (including actions) for the 
    load shedder and emergency load sequencer (LSELS) to CTS LCO 3.8.1.2 
    and surveillance requirements in SR 4.8.1.2. These requirements would 
    reflect current practice.
        22. Change 2-25-LS-23 (ITS 3/4.8). The proposed change was 
    requested in the original application and would allow substitution of 
    the service test with a performance discharge test or modified 
    performance discharge test.
        Before issuance of the proposed license amendment, the Commission 
    will have made findings required by the Atomic Energy Act of 1954, as 
    amended (the Act) and the Commission's regulations.
        By March 29, 1999, the licensee may file a request for a hearing 
    with respect to issuance of the amendment to the subject facility 
    operating license and any person whose interest may be affected by this 
    proceeding and who wishes to participate as a party in the proceeding 
    must file a written request for a hearing and a petition for leave to 
    intervene. Requests for a hearing and a petition for leave to intervene 
    shall be filed in accordance with the Commission's ``Rules of Practice 
    for Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested 
    persons should consult a current copy of 10 CFR 2.714 which is 
    available at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document rooms located at the Emporia State University, William Allen 
    White Library, 1200 Commercial Street, Emporia, Kansas, 66801, and 
    Washburn University School of Law Library, Topeka, Kansas 66621. If a 
    request for a hearing or petition for leave to intervene is filed by 
    the above date, the Commission or an Atomic Safety and Licensing Board, 
    designated by the Commission or by the Chairman of the Atomic Safety 
    and Licensing Board Panel, will rule on the request and/or petition; 
    and the Secretary or the designated Atomic Safety and Licensing Board 
    will issue a notice of hearing or an appropriate order.
        As required by 10 CFR 2.714, a petition for leave to intervene 
    shall set forth with particularity the interest of the petitioner in 
    the proceeding, and how that interest may be affected by the results of 
    the proceeding. The petition should specifically explain the reasons 
    why intervention should be permitted with particular reference to the 
    following factors: (1) the nature of the petitioner's right under the 
    Act to be made a party to the proceeding; (2) the nature and extent of 
    the petitioner's property, financial, or other interest in
    
    [[Page 9549]]
    
    the proceeding; and (3) the possible effect of any order which may be 
    entered in the proceeding on the petitioner's interest. The petition 
    should also identify the specific aspect(s) of the subject matter of 
    the proceeding as to which petitioner wishes to intervene. Any person 
    who has filed a petition for leave to intervene or who has been 
    admitted as a party may amend the petition without requesting leave of 
    the Board up to 15 days prior to the first prehearing conference 
    scheduled in the proceeding, but such an amended petition must satisfy 
    the specificity requirements described above.
        Not later than 15 days prior to the first prehearing conference 
    scheduled in the proceeding, a petitioner shall file a supplement to 
    the petition to intervene which must include a list of the contentions 
    which are sought to be litigated in the matter. Each contention must 
    consist of a specific statement of the issue of law or fact to be 
    raised or controverted. In addition, the petitioner shall provide a 
    brief explanation of the bases of the contention and a concise 
    statement of the alleged facts or expert opinion which support the 
    contention and on which the petitioner intends to rely in proving the 
    contention at the hearing. The petitioner must also provide references 
    to those specific sources and documents of which the petitioner is 
    aware and on which the petitioner intends to rely to establish those 
    facts or expert opinion. Petitioner must provide sufficient information 
    to show that a genuine dispute exists with the applicant on a material 
    issue of law or fact. Contentions shall be limited to matters within 
    the scope of the amendment under consideration. The contention must be 
    one which, if proven, would entitle the petitioner to relief. A 
    petitioner who fails to file such a supplement which satisfies these 
    requirements with respect to at least one contention will not be 
    permitted to participate as a party.
        Those permitted to intervene become parties to the proceeding, 
    subject to any limitations in the order granting leave to intervene, 
    and have the opportunity to participate fully in the conduct of the 
    hearing, including the opportunity to present evidence and cross-
    examine witnesses.
        A request for a hearing or a petition for leave to intervene must 
    be filed with the Secretary of the Commission, U.S. Nuclear Regulatory 
    Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
    Adjudications Staff, or may be delivered to the Commission's Public 
    Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, 
    by the above date. A copy of the petition should also be sent to the 
    Office of the General Counsel, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555-0001, and to Mr. Jay Silberg, Esq., Shaw, Pittman, 
    Potts and Trowbridge, 2300 N Street, N.W., Washington, D.C. 20037, 
    attorney for the licensee.
        Nontimely filings of petitions for leave to intervene, amended 
    petitions, supplemental petitions and/or requests for hearing will not 
    be entertained absent a determination by the Commission, the presiding 
    officer or the presiding Atomic Safety and Licensing Board that the 
    petition and/or request should be granted based upon a balancing of the 
    factors specified in 10 CFR 2.714(a)(1)(I)-(v) and 2.714(d).
        If a request for a hearing is received, the Commission's staff may 
    issue the amendment after it completes its technical review and prior 
    to the completion of any required hearing if it publishes a further 
    notice for public comment of its proposed finding of no significant 
    hazards consideration in accordance with 10 CFR 50.91 and 50.92.
        For further details with respect to this action, see the 
    application for amendment dated May 15, 1997, as supplemented by 
    letters dated June 30, August 5, August 28, September 24, October 16, 
    October 23, November 24, December 2, December 17, December 21, 1998, 
    and February 4, 1999, which is available for public inspection at the 
    Commission's Public Document Room, the Gelman Building, 2120 L Street, 
    NW., Washington, DC, and at the local public document rooms located at 
    the Emporia State University, William Allen White Library, 1200 
    Commercial Street, Emporia, Kansas, 66801, and Washburn University 
    School of Law Library, Topeka, Kansas 66621.
    
        Dated at Rockville, Maryland, this 22nd day of February 1999.
    
        For the Nuclear Regulatory Commission.
    Mel Gray,
    Project Manager, Project Directorate IV-2, Division of Licensing 
    Project Management, Office of Nuclear Reactor Regulation.
    [FR Doc. 99-4816 Filed 2-25-99; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
02/26/1999
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
99-4816
Pages:
9546-9549 (4 pages)
Docket Numbers:
Docket No. 50-482
PDF File:
99-4816.pdf