03-4705. Notice of Application Accepted for Filing and Soliciting Comments, Protests, and Motions To Intervene
-
Start Preamble
February 21, 2003.
Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary permit.
b. Project No.: 12389-000.
c. Date filed: October 3, 2002.
d. Applicant: Universal Electric Power Corporation.
e. Name and Location of Project: The H.K. Thatcher L&D Hydroelectric Project would be located on the Ouachita River in Union County, Arkansas. The proposed project would utilize the existing H.K. Thatcher Lock and Dam administered by the U.S. Army Corps of Engineers.
f. Filed pursuant to: Federal Power Act, 16 U.S.C. 791(a)—825(r).
g. Applicant contact: Mr. Raymond Helter, Universal Electric Power Corporation, 1145 Highbrook Street, Akron, OH 44301, (330) 535-7115.
h. FERC Contact: Tom Papsidero, (202) 502-6002.
i. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice.
The Commission's rules of practice and procedure require all interveners filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.
j. Description of Project: The proposed project, using the Corps' existing H.K. Thatcher Lock and Dam and Reservoir, would consist of: (1) two proposed 240-Start Printed Page 9071foot-long, 8-foot-diameter steel penstocks, (2) a proposed powerhouse containing two generating units with a combined installed capacity of 3 megawatts, (3) a proposed 500-foot-long, 14.7-kv transmission line, and (4) appurtenant facilities. The project would operate in a run-of-river mode and would have an average annual generation of 18 GWh.
k. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “FERRIS” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1-866-208-3676 or e-mail ferconlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is also available for inspection and reproduction at the applicant's address in item g above.
l. Competing Preliminary Permit—Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36.
m. Competing Development Application—Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36.
n. Notice of Intent—A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice.
o. Proposed Scope of Studies under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project.
p. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of rules of practice and procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.
q. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title “COMMENTS”, “NOTICE OF INTENT TO FILE COMPETING APPLICATION”, “COMPETING APPLICATION”, “PROTEST”, or “MOTION TO INTERVENE”, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing an original and eight copies to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application.
Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site under the “e-Filing” link. The Commission strongly encourages electronic filings.
r. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency's comments must also be sent to the Applicant's representatives.
Start SignatureMagalie R. Salas,
Secretary.
[FR Doc. 03-4705 Filed 2-26-03; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Published:
- 02/27/2003
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 03-4705
- Pages:
- 9070-9071 (2 pages)
- EOCitation:
- of 2003-02-21
- PDF File:
- 03-4705.pdf