E9-4163. Tennessee Gas Pipeline Company; Notice of Application  

  • Start Preamble February 20, 2009.

    Take notice that on February 9, 2009, Tennessee Gas Pipeline Company (Tennessee), 1001 Louisiana Houston, Texas 77002, filed in the above referenced docket an abbreviated application pursuant to section 7(b) of the Natural Gas Act (NGA) and Part 157 of the Commission's regulations, for an order approving the abandonment of three pipeline segments that cross the Mississippi River in East Carroll Parish, Louisiana, and Issaquena County, Mississippi. The project named The Mississippi River Levee Abandonment Project includes the abandonment and removal of an associated side valve and aboveground appurtenances, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TTY, (202) 502-8659.

    Specifically, Tennessee proposes to (a) abandon in place the portion of the pipeline segments that lie between the east and west levees and across the Mississippi River, and (b) abandon by removal the portion of the pipeline segments that lie within the east and west levees, as well as a side valve and associated aboveground piping located within the east levee. The overall length of each line to be abandoned by removal and in place is approximately 4.17 miles.

    Any questions concerning this application may be directed to Susan T. Halbach, Senior Counsel, Tennessee Gas Pipeline Company, 1001 Louisiana Houston, Texas 77002, phone: (713) 420-5751, fax: (713) 420-1601, e-mail: susan.halbach@elpaso.com or Kathy Cash, Principal Analyst, Rates and Regulatory Affairs, Tennessee Gas Pipeline Company 1001 Louisiana Houston, TX 77002, phone: (713) 420-3290, fax: (713) 420-1605, e-mail: kathy.cash@elpaso.com.

    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.

    There are two ways to become involved in the Commission's review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.

    However, a person does not have to intervene in order to have comments considered. The second way to Start Printed Page 8925participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest.

    Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission's environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission's environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission's final order.

    The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the “eFiling” link at http://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street, NE., Washington, DC 20426.

    This filing is accessible on-line at http://www.ferc.gov,, using the “eLibrary” link and is available for review in the Commission's Public Reference Room in Washington, DC. There is an “eSubscription” link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For TTY, call (202) 502-8659.

    Comment Date: March 13, 2009.

    Start Signature

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. E9-4163 Filed 2-26-09; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Effective Date:
3/13/2009
Published:
02/27/2009
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
E9-4163
Dates:
March 13, 2009.
Pages:
8924-8925 (2 pages)
Docket Numbers:
Docket No. CP09-63-000
EOCitation:
of 2009-02-20