96-4683. Yankee Atomic Electric Company (License No. DPR-3); Issuance of Director's Decision Under 10 CFR 2.206  

  • [Federal Register Volume 61, Number 41 (Thursday, February 29, 1996)]
    [Notices]
    [Pages 7825-7832]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-4683]
    
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-029]
    
    
    Yankee Atomic Electric Company (License No. DPR-3); Issuance of 
    Director's Decision Under 10 CFR 2.206
    
        Notice is hereby given that the Director, Office of Nuclear Reactor 
    Regulation, has taken action with respect to a Petition, dated January 
    17, 1996, by Citizens Awareness Network and New England Coalition on 
    Nuclear Pollution (Petitioners). The Petitioners requested that the 
    Nuclear Regulatory Commission (NRC) take action with regard to 
    operation by Yankee Atomic Energy Company (YAEC or Licensee) of its 
    Nuclear Power Station at Rowe, Massachusetts (Yankee Rowe).
        Petitioners requested that the NRC comply with Citizens Awareness 
    Network Inc. v. United States Nuclear Regulatory Commission and Yankee 
    Atomic Electric Company, 59 F.3d 284 (1st Cir. 1995) (CAN v. NRC). 
    Specifically, Petitioners requested that the Commission immediately 
    order:
        (1) YAEC not to undertake, and the NRC staff not to approve, 
    further major 
    
    [[Page 7826]]
    dismantling activities or other decommissioning activities, unless such 
    activities are necessary to assure the protection of occupational and 
    public health and safety; (2) YAEC to cease any such activities; and 
    (3) NRC Region I to reinspect Yankee Rowe to determine whether there 
    has been compliance with the Commission's Order of October 12, 1995 
    (CLI-95-14), and to issue a report within ten days of the requested 
    order to Region I.
        The Petitioners' request for emergency action to cease 
    decommissioning activities was mooted in part by the Licensee's 
    completion of activities evaluated by the NRC staff in a letter of 
    November 2, 1995 to the licensee. Even if these activities have not 
    been completed, they would have been permissible under the Commission's 
    pre-1993 interpretation of its decommissioning regulations. By letter 
    dated February 2, 1996, Petitioners' request that shipments of low-
    level radioactive be prohibited was denied, and Petitioners' request 
    for reinspection of the Yankee Rowe facility to determine compliance 
    with CLI-94-14 and to issue an inspection report was granted. The 
    Director has determined to be moot the request that four other 
    activities be prohibited. Additionally, he has granted the request for 
    inspection of Yankee Rowe to determine compliance with CLI-95-14 and to 
    issue an inspection report. The reasons for these decisions are 
    explained in the ``Director's Decision Pursuant to 10 CFR 2.206'' (DD-
    96-01), the complete text of which follows this notice and is available 
    for public inspection at the Commission's Public Document Room, the 
    Gelman Building, 2120 L Street, NW., Washington, DC, and at the local 
    public document room located at the Greenfield Community College 
    Library, 1 College Drive, Greenfield, Massachusetts, 01301.
        A copy of the Decision will be filed with the Secretary of the 
    Commission for the Commission's review in accordance with 10 CFR 
    2.206(c) of the Commission's regulations. As provided by this 
    regulation, the Decision will constitute the final action of the 
    Commission 25 days after the date of issuance unless the Commission, on 
    its own motion, institutes a review of the Decision in that time.
    
        Dated at Rockville, Maryland, this 22nd day of February 1996.
    
        For the Nuclear Regulatory Commission.
    William T. Russell,
    Director, Office of Nuclear Reactor Regulation.
    
    Appendix A to This Document: Director's Decision Under 10 CFR 2.206; 
    Yankee Atomic Electric Company
    
    I. Introduction
    
        An ``EMERGENCY MOTION FOR COMPLIANCE WITH CIRCUIT COURT 
    OPINION'' (Petition), dated January 17, 1996, was submitted by 
    Citizens Awareness Network and New England Coalition on Nuclear 
    Pollution (Petitioners). Petitioners requested that the United 
    States Nuclear Regulatory Commission (NRC or Commission) take action 
    with respect to activities conducted by Yankee Atomic Electric 
    Company (YAEC or Licensee) at the Yankee Nuclear Power Station in 
    Rowe, Massachusetts (Yankee Rowe or the facility).
        By an Order of the Commission dated January 23, 1996, the 
    Emergency Motion was referred to the NRC staff for treatment as a 
    petition pursuant to 10 CFR 2.206 of the Commission's regulations. 
    The Commission ordered the staff to respond to the emergency aspects 
    of the Petition in 10 days and to issue a decision on the Petition 
    as a whole within 30 days.
        Petitioners request that the NRC comply with Citizens Awareness 
    Network Inc. v. United States Nuclear Regulatory Commission and 
    Yankee Atomic Electric Company, 59 F.3d 284 (1st Cir. 1995) (CAN v. 
    NRC). Specifically, Petitioners request that the Commission 
    immediately order:
        (A) YAEC not to undertake, and the NRC staff not to approve, 
    further major dismantling activities or other decommissioning 
    activities, unless such activities are necessary to assure the 
    protection of occupational and public health and safety;
        (B) YAEC to cease any such activities; and
        (C) NRC Region I to reinspect the Yankee Nuclear Power Station 
    in Rowe, Massachusetts (Yankee Rowe) to determine whether there has 
    been compliance with the Commission's Order of October 12, 1995 
    (CLI-95-14), and to issue a report within ten days of the requested 
    order to Region I.
        As the bases for their requests, Petitioners state that:
        (1) CAN v. NRC requires the cessation, and prohibits 
    commencement, of decommissioning activities at Yankee Rowe, pending 
    final approval of the licensee's decommissioning plan after 
    opportunity for a hearing. CLI-95-14 forbids YAEC from conducting 
    any further major dismantling or decommissioning activities until 
    final approval of its decommissioning plan after completion of the 
    hearing process;
        (2) CAN v. NRC obliges the Commission and the staff to provide 
    an opportunity to interested persons for a hearing to approve a 
    decommissioning plan;
        (3) CAN v. NRC requires the Commission to reinstate its pre-1993 
    interpretation of its decommissioning regulations, General 
    Requirements for Decommissioning Nuclear Facilities, 53 FR 24,018, 
    24,025-26 (June 27, 1988), limiting the scope of permissible 
    activities prior to approval of a decommissioning plan to 
    decontamination, minor component disassembly, and shipment and 
    storage of spent fuel, if permitted by the operating license and/or 
    10 CFR Sec. 50.59. Under Long Island Lighting Co. (Shoreham Nuclear 
    Power Station, Unit 1), CLI-90-08, 32 NRC 201, 207, n.3 (1990), this 
    means that the licensee may not take any action that would 
    materially affect the methods or options available for 
    decommissioning, or that would substantially increase the costs of 
    decommissioning, prior to approval of a decommissioning plan. Under 
    CLI-91-2, 33 NRC at 73, n.5, and CLI-92-2, 35 NRC at 61, n.7, other 
    decommissioning activities, in addition to major ones, are 
    prohibited, including offsite shipments of low-level radioactive 
    waste produced by decommissioning activities, until after approval 
    of a decommissioning plan;
        (4) Decommissioning activities permitted by NRC Inspection 
    Manual, Chapter 2561, Sec. 06.06, ``Modifications or Changes to the 
    Facility'', before approval of a decommissioning plan are limited to 
    maintenance, removal of relatively small radioactive components or 
    non-radioactive components, and characterization of the plant or 
    site;
        (5) YAEC is conducting decommissioning activities, with the 
    approval of the NRC technical staff, in flagrant violation of CAN v. 
    NRC and of CLI-95-14, thus threatening to render the decommissioning 
    process nugatory and to deprive Petitioners of their hearing rights 
    under Section 189a of the Atomic Energy Act;
        (6) By letter dated October 19, 1995, YAEC described nine 
    decommissioning activities in progress, and by letter dated October 
    24, 1995, interpreted permissible ``major'' dismantling as removal 
    of non-radioactive material required to support safe storage of 
    spent fuel and of those portions of the facilities which remain, or 
    to support future dismantlement;
        (7) By letter dated November 2, 1995, the NRC staff approved the 
    activities described by the Licensee in its letter of October 19, 
    1995;
        (8) Five of the nine activities approved by the NRC staff's 
    letter of November 2, 1995, are major dismantling or other 
    decommissioning activities, in the nature of Component Removal 
    Project activities, prohibited, until after approval of a 
    decommissioning plan, by CAN v. NRC and CLI-95-14. Petitioners 
    object to: (a) Completing removal of the remainder of the Upper 
    Neutron Shield Tank; (b) removal of Component Cooling Water System 
    pipes and components and Spent Fuel Cooling System pipes and 
    components; (c) Fuel Chute isolation; (d) Spent Fuel Pool electrical 
    conduit installation; and (e) radioactive waste shipments. 
    Petitioners do not object to Waste Tank removal, Ion Exchange Pit 
    clean-up, removal of Emergency Diesel Generators, or the Brookhaven 
    National Laboratory Cable Sampling Project.
        (9) Petitioners advocate the SAFSTOR decommissioning alternative 
    because it allows levels of radioactivity and waste volumes to 
    decrease, thus reducing 
    
    [[Page 7827]]
    occupational and public radiation exposures, and lowering 
    decommissioning costs;
        (10) NRC Inspection Report No. 50-29/95-05 (December 16, 1995) 
    concludes that the issue whether activities observed were in 
    compliance with CLI-95-14 is unresolved, but approves YAEC's 
    proposed activities, contrary to the requirements of NRC Inspection 
    Manual, Chapter 2561, Sec. 06.06, ``Modifications or Changes to the 
    Facility'' (March 20, 1992); and
        (11) YAEC's criterion for permissible decommissioning 
    activities, that any activity involving less than 1 percent of the 
    on-site radioactive inventory is not ``major'' and may take place 
    before approval of a decommissioning plan, violates CAN v. NRC 
    because it would allow completion of decommissioning before any 
    decommissioning plan could be approved in hearing, and constitutes 
    unlawful segmentation under the National Environmental Policy Act.
        By letter dated January 29, 1996, Yankee Atomic Electric Company 
    responded to the Petition. YAEC supplemented its response by letters 
    dated February 15, 1996, February 21, 1996, and February 22, 1996, 
    and by an E-mail message to the NRC staff on January 31, 1996.
        By letter dated February 2, 1996, the NRC staff denied in part 
    and granted in part Petitioners' requests for emergency action. The 
    Petition was also found moot in part. Petitioners' requests that the 
    NRC take emergency action to order (A) YAEC not to undertake and the 
    NRC staff not to approve further major dismantling activities or 
    other decommissioning activities, unless necessary to assure the 
    protection of occupational and public health and safety and (B) YAEC 
    to cease any such activities were found moot in part and denied in 
    part. Petitioners' request for emergency action to require NRC 
    Region I to reinspect Yankee Rowe to determine whether YAEC has 
    complied with the Commission's Order of October 12, 1995 (CLI-95-
    14), and to issue a report within ten days after the Commission 
    orders such an inspection, was granted.
        Petitioners then requested the Commission to reverse the NRC 
    staff's February 2, 1996, decision on the emergency aspects of the 
    Petition. See ``Citizens Awareness Network's and New England 
    Coalition on Nuclear Pollution's Motion for Exercise of Plenary 
    Commission Authority to Reverse NRC Staff 2.206 Decision, and 
    Renewed Emergency Request for Compliance with Circuit Court 
    Opinion.'' By Order dated February 15, 1996, the Commission declined 
    to grant the emergency relief requested, as there was no showing 
    that the Licensee would take any action before the issuance of a 
    Director's Decision on February 22, 1996. The Commission directed 
    the NRC staff to address the arguments advanced by Petitioners in 
    their February 9 motion in this Decision, with the exception of the 
    new issues raised on page 13 of the Motion, which are to be 
    addressed in a supplementary 10 CFR Sec. 2.206 decision.
        For the reasons discussed below, Petitioners' requests that the 
    NRC prohibit YAEC from undertaking or continuing five of the nine 
    activities evaluated by the NRC staff's letter of November 2, 1995, 
    are moot in part and denied in part. Of the nine activities, all 
    with the exception of radioactive waste shipments were completed 
    before submission of the January 17, 1996, Petition. Accordingly, 
    Petitioners' request for relief with respect to: (1) Completing 
    removal of the remainder of the Upper Neutron Shield Tank; (2) 
    removal of the Component Cooling Water System pipes and components 
    and Spent Fuel Cooling System pipes and components; (3) Fuel Chute 
    isolation; and (4) Spent Fuel Pool electrical conduit installation 
    is moot. Petitioners' request for relief with respect to radioactive 
    waste shipments is denied. As explained below, all five contested 
    activities were permissible, before approval of a decommissioning 
    plan, under the pre-1993 interpretation of the Commission's 
    decommissioning regulations, and thus are in compliance with CAN v. 
    NRC and CLI-95-14. Petitioners' request that the NRC inspect Yankee 
    Rowe to determine compliance with CLI-95-14, and issue an inspection 
    report, was granted.
    
    II. Background
    
        On February 27, 1992, YAEC announced its intention to cease 
    operations permanently at Yankee Rowe. On August 5, 1992, the NRC 
    issued a license amendment to limit the license to a Possession-
    Only-License. 57 FR 37558, 37579 (Aug. 19, 1992).
        In late 1992, YAEC proposed to initiate a Component Removal 
    Project (CRP). On December 20, 1993, YAEC submitted a 
    decommissioning plan based on a phased approach, starting with 
    DECON, then SAFSTOR, and then finally dismantlement. Notice of 
    Receipt of Decommissioning Plan and Request for Comments was 
    published in the Federal Register. (59 FR 14689 on March 29, 1994).
        On January 14, 1993, and on June 30, 1993, the Commission issued 
    two Staff Requirements Memoranda which, in pertinent part, 
    interpreted the Commission's regulations to permit many 
    decommissioning activities prior to approval of a decommissioning 
    plan, as long as the activities do not violate the terms of the 
    existing license or 10 CFR Sec. 50.59 with certain additional 
    restrictions. See ``Staff Requirements--Briefing by OGC on 
    Regulatory Issues and Options for Decommissioning Proceedings (SECY-
    92-382), 10:00 A.M., Tuesday, November 24, 1992, Commissioner's 
    Conference Room, One White Flint North, Rockville, Maryland (Open to 
    Public Attendance)'' (January 14, 1993) and ``SECY-92-382-
    Decommissioning--Lessons Learned'' (June 30, 1993).
        On several occasions between late 1992 and early 1994, CAN asked 
    the NRC to offer an opportunity for an administrative hearing 
    regarding decommissioning activities conducted by YAEC at Yankee 
    Rowe. The Commission denied each such request. CAN sought judicial 
    review and challenged the denials and the January 14, 1993, 
    interpretation of the Commission's decommissioning regulations.
        On July 20, 1995, the United States Court of Appeals held that 
    the Commission had: (1) Failed to provide an opportunity for hearing 
    to CAN, as required by Section 189 of the Atomic Energy Act, in 
    connection with the Commission's decision to permit the CRP 
    decommissioning activities; (2) changed its pre-1993 interpretation 
    of its decommissioning regulations without notice to the public and 
    in violation of the Administrative Procedure Act; and (3) 
    impermissibly allowed the licensee to conduct CRP decommissioning 
    activities prior to compliance with the National Environmental 
    Policy Act requirement to conduct an environmental analysis or 
    environmental impact statement. Citizens Awareness Network v. NRC 
    and Yankee Atomic Electric Company, 59 F. 3d 284, 291-2, 292-3, and 
    294-5 (1st Cir. 1995). The court remanded the matter to the 
    Commission for proceedings consistent with the court's opinion.
        In response, the Commission issued a Federal Register notice 
    advising: (1) That the Commission did not intend to seek further 
    review of CAN v. NRC; (2) that the Commission understood that 
    decision to require a return to the interpretation of NRC 
    decommissioning regulations that was in effect prior to January 14, 
    1993; and (3) that the Commission was requesting public comments on 
    whether the Commission should order YAEC to cease ongoing 
    decommissioning activities pending any required hearings and any 
    other matters connected with that issue. See 60 FR 46,317 (September 
    6, 1995).
        After consideration of comments filed in response to that 
    notice, the Commission implemented CAN v. NRC by issuing Yankee 
    Atomic Electric Company (Yankee Nuclear Power Station), CLI-95-14, 
    42 NRC 130 (1995). In CLI-95-14, the Commission reinstated its pre-
    1993 interpretation of its decommissioning policy, required the 
    issuance of a notice of opportunity for an adjudicatory hearing on 
    the Yankee Rowe decommissioning plan, held that YAEC may not conduct 
    further ``major'' decommissioning activities at Yankee Rowe until 
    approval of a decommissioning plan after completion of any required 
    hearing, and directed YAEC to inform the Commission within 14 days 
    of the steps it is taking to come into compliance with the 
    reinstated interpretation of the Commission's decommissioning 
    regulations. Yankee Atomic Electric Company, CLI-95-14, 42 NRC 130 
    (1995).
        Pursuant to CLI-95-14, a proceeding is now underway to offer an 
    opportunity for hearing on the Licensee's decommissioning plan for 
    Yankee Rowe. Petitioners have sought intervention and a hearing.
        As of July 20, 1995, when the court issued CAN v. NRC, YAEC had 
    completed its Component Removal Project. In response to CLI-95-14, 
    by letters dated October 19 and 24, 1995, YAEC identified nine 
    ongoing activities which YAEC believed were permissible under CAN v. 
    NRC and CLI-95-14.
        In its letter of November 2, 1995, the NRC staff evaluated those 
    nine activities and found them permissible under the Commission's 
    pre-1993 interpretation of its decommissioning regulations, and thus 
    under CAN v. NRC and CLI-95-14. The staff 
    
    [[Page 7828]]
    also identified certain activities, although not proposed by the 
    Licensee, which may not be conducted before reapproval of a 
    decommissioning plan. Those activities include dismantlement of 
    systems such as the main reactor coolant system, the lower neutron 
    shield tank, vessels that have significant radiological 
    contamination, pipes, pumps and other such components and the vapor 
    container (containment). The staff also identified segmentation or 
    removal of the reactor vessel from its support structure as a major 
    dismantlement not to be conducted until after the decommissioning 
    plan is reapproved.
    
    III. Discussion
    
        A. The nine activities were permissible, prior to approval of a 
    decommissioning plan, under the Commission's pre-1993 interpretation 
    of its decommissioning regulations, and thus are permissible under 
    CAN v. NRC and CLI-95-14.
        Petitioners contend that five of the nine activities evaluated 
    by the NRC staff's letter of November 2, 1995, are major dismantling 
    or other decommissioning activities prohibited until after approval 
    of a decommissioning plan, by CAN v. NRC and CLI-95-14. 
    Specifically, Petitioners object to: (1) Completing removal of the 
    remainder of the Upper Neutron Shield Tank; (2) removal of Component 
    Cooling Water System pipes and components and Spent Fuel Cooling 
    System pipes and components; (3) Fuel Chute isolation; (4) Spent 
    Fuel Pool electrical conduit installation; and (5) radioactive waste 
    shipments. Petitioners do not object to Waste Tank removal, Ion 
    Exchange Pit clean-up, removal of Emergency Diesel Generators, or 
    the Brookhaven National Laboratory Cable Sampling Project. 
    Petitioners acknowledge that completion of Waste Tank removal and 
    Ion Exchange Pit clean-up are required for safety reasons. 
    Petitioners also acknowledge that the removal of the Emergency 
    Diesel Generators is permissible because they are not radioactive, 
    and that the Brookhaven National Laboratory Cable Sampling Project 
    is a research project unrelated to decommissioning. Of the nine 
    activities, all with the exception of radioactive waste shipments 
    were completed before submission of the January 17, 1996, Petition.
        Under the Commission's pre-1993 interpretation of its 
    decommissioning regulations, a licensee ``may proceed with some 
    activities such as decontamination, minor component disassembly, and 
    shipment and storage of spent fuel if the activities are permitted 
    by the operating license and/or Sec. 50.59'', prior to final 
    approval of a licensee's decommissioning plan, \1\, as long as the 
    activity does not involve major structural or other major changes 
    and does not materially and demonstrably affect the methods or 
    options available for decommissioning or substantially increase the 
    costs of decommissioning. Long Island Lighting Company (Shoreham 
    Nuclear Power Station, Unit 1), CLI-90-8, 32 NRC 201, 207, n.3 
    (1990); Long Island Lighting Company (Shoreham Nuclear Power 
    Station, Unit 1), CLI-91-2, 33 NRC 61, 73. n.5 (1991); and 
    Sacramento Municipal Utility District (Rancho Seco Nuclear 
    Generating Station), CLI-92-2, 35 NRC 47, 61. n. 7 (1992).
    
        \1\ Statement of Consideration, ``General Requirements for 
    Decommissioning Nuclear Facilities'', 53 FR 24018, 24025-26 (June 
    27, 1988).
    ---------------------------------------------------------------------------
    
        Under the pre-1993 interpretation of the Commission's 
    decommissioning regulations, examples of activities which were 
    considered permissible and which were conducted at various 
    facilities under a Possession-Only license before approval of a 
    decommissioning plan included:
    
    Shoreham \2\
    
     Core borings in biological shield wall
    
        \2\ See letter dated December 11, 1991 from John D. Leonard, 
    Jr., Long Island Lighting Company, to U.S. Nuclear Regulatory 
    Commission, Docket No. 50-322.
    ---------------------------------------------------------------------------
    
     Core borings of the reactor pressure vessel
     Regenerative heat exchanger removal and disassembly
     Various sections of reactor water clean-up system piping 
    cut out and removed to determine effectiveness of chemical 
    decontamination processes being used
     Removal of approximately half of reactor pressure vessel 
    insulation and preparation for disposal
     Removal of fuel support castings and peripheral pieces 
    removed and shipment offsite for disposal at Barnwell, South 
    Carolina
     Reactor water clean-up system recirculation holding pump 
    removed and shipped to James A. FitzPatrick Nuclear Power Plant
     Control rod drive pump shipped to Brunswick Nuclear Station
     One full set of control rod blade guides sold to Carolina 
    Power and Light Company
     Control rod drives removed, cleaned, and stored in boxes 
    for salvage
     Process initiated for segmenting and removing reactor 
    pressure vessel cavity shield blocks
     Process initiated for removal of instrument racks, tubing, 
    conduits, walkways, and pipe insulation presenting interferences for 
    decommissioning activities and/or removal of salvageable equipment
    
    Fort St. Vrain \3\
    
     Control rod drive and orifice assemblies and control rods 
    removed from core during defueling and shipped offsite for 
    processing or disposal as low-level waste
    
        \3\ See letter dated September 4, 1992 from Donald M. 
    Warembourg, Public Service Company of Colorado, to the U.S. Nuclear 
    Regulatory Commission, Docket No. 50-267.
    ---------------------------------------------------------------------------
    
     All helium circulators removed and shipped offsite for 
    disposal
     Core region constraint devices (internals) removed and 
    approximately one-half shipped offsite for disposal
     About 50 core metal-clad reflector blocks (top layer of 
    core) removed and stored in fuel storage wells
     Removal of remaining hexagonal graphite reflector elements, 
    defueling elements, and metal-clad reflector blocks begun
     Pre-stressed concrete reactor vessel (PCRV) top cross-head 
    tendons and some circumferential tendons detensioned
     Some detensioned tendons removed from PCRV
     Work initiated to cut and remove PCRV liner cooling system 
    piping presenting interferences to detensioning of PCRV tendons, and
     Asbestos insulation completely removed from piping under 
    PCRV
    
        Activities such as normal maintenance and repairs, removal of 
    small radioactive components for storage or shipment, and removal of 
    components similar to that for maintenance and repair also were 
    permitted prior to approval of a decommissioning plan under the 
    Commission's pre-1993 interpretation of the Commission's 
    decommissioning regulations. See NRC Inspection Manual, Chapter 
    2561, Section 06.06. (Issue Date: 03/20/92).4
    
        \4\ ``Examples of modifications and activities, that are allowed 
    during the post-operational phase [the interval between permanent 
    shutdown and the NRC's approval of the licensee's decommissioning 
    plan] are (1) those that could be performed under normal maintenance 
    and repair activities, (2) removal of certain, relatively small 
    radioactive components, such as control rod drive mechanism, control 
    rods, and core internals for disassembly, and storage or shipment, 
    (3) removal of non-radioactive components and structures not 
    required for safety in the post-operational phase, (5) shipment of 
    reactor fuel offsite, and (6) activities related to site and 
    equipment radiation and contamination characterization.''
    ---------------------------------------------------------------------------
    
        Of course, licensees are also permitted to complete or to 
    conduct activities required for compliance with safety requirements 
    before approval of a decommissioning plan. In addition, special 
    consideration must be given to activities required to comply with 
    other federal and state safety requirements. See Memorandum of 
    Understanding Between the Nuclear Regulatory Commission and the 
    Occupational Safety and Health Administration, ``Worker Protection 
    at NRC-licensed Facilities'' (October 21, 1988), 53 FR 43950 
    (October 31, 1988). See also NRC Inspection Manual, Chapter 1007, 
    ``Interfacing Activities Between Regional Offices of NRC and OSHA''. 
    Petitioners concede that completion of activities already underway 
    is permissible if completion is required for immediate safety 
    purposes.
        The staff's November 2, 1995 letter evaluated the nine 
    activities identified in YAEC's letter of October 19, 1995, based on 
    the Commission's pre-1993 interpretation of its decommissioning 
    regulations,5 and determined that the nine activities were 
    permissible before approval of a decommissioning plan.
    
        \5\ Petitioners claim that YAEC's ``1 percent'' criterion for 
    determining what constitutes major structural or other major change 
    (and thus what activities are permissible before approval of a 
    decommissioning plan) would allow completion of decommissioning 
    before any decommissioning plan could be approved in hearing. The 
    staff does not accept or approve, and has not used this criterion to 
    determine whether any YAEC activities, including the nine 
    activities, are permissible before approval of a decommissioning 
    plan.
    ---------------------------------------------------------------------------
    
        Upon review of the Petition and its supplement of February 9, 
    1996, the staff took a fresh look at the nine activities and again 
    found them to be permissible before approval of a decommissioning 
    plan, under the pre-1993 interpretation of the Commission's 
    decommissioning regulations, and thus under CAN v. NRC and CLI-95-
    14:
    
    [[Page 7829]]
    
    
    (1) Completion of Removal of the Remaining Portions of the Upper 
    Neutron Shield Tank
    
        As stated in the NRC staff's letter of November 2, 1995, 
    completion of this activity was necessary to avoid a significant 
    lead hazard to plant personnel due to lead dust or powder deposits 
    on surfaces of the structure (particularly if the plant were to go 
    into an extended SAFSTOR configuration, as desired by Petitioners). 
    That contamination, if disturbed during licensee maintenance 
    activities or NRC inspections would pose a significant health hazard 
    to Licensee and NRC personnel.
        Petitioners object that this safety rationale is unsupported by 
    factual information regarding actual lead levels in the tank and 
    whether the lead levels violated OSHA standards.
        Dismantlement of the Upper Neutron Shield Tank required cutting 
    sections of the tank that had lead shielding. Cutting was completed 
    before November 2, 1995 and lead cleanup was completed by November 
    8, 1995. Lead dust was created by dismantlement of the tank, already 
    underway and completed before issuance of the November 2, 1995 staff 
    letter. Surface lead residue measurements in those areas ranged 
    between 13,000 micrograms/ft 2 and 390,000 micrograms/ft 
    2.
        The Licensee's operating procedures require the Licensee to 
    implement industrial hygiene control methods as specified by the 
    Occupational Safety and Health Administration in areas where there 
    is potential for employee exposure to lead. Procedure No. AP-0713, 
    ``Lead Control Program'', Revision 1 Major, Section C 
    (``Discussion''), p. 3. The target for removable lead contamination 
    is 200 micrograms/ft 2. Id., ``Discussion'', Section C., 
    ``Decontamination'', p. 4.
        Lead dust resulting from dismantlement of the Upper Neutron 
    Shield Tank was at a concentration such that surface lead 
    contamination exceeded the target for removable lead 
    contamination.6 Licensee personnel were and are required to 
    enter the area in order to conduct surveillances to monitor 
    radioactive contamination and for compliance with fire protection 
    requirements.
    
        \6\ The use of respiratory protection by workers would not have 
    satisfied the Licensee's operating procedures. Until a determination 
    is made that any employee working with lead will not be exposed to 
    lead at the action level, respiratory protection is required. 
    Procedure No. AP-0713, ``Procedure'', Section C (``Lead Work 
    Practices''), p. 11. The action level is employee exposure, without 
    regard to use of respirators, to an airborne concentration of lead 
    of 30 micrograms per cubic meter of air calculated as an 8-hour 
    time-weighted average, and the permissible exposure limit is 50 
    micrograms per cubic meter of air over an 8-hour time weighted 
    average, and 30 micrograms per cubic meter of air over a 10-hour 
    time weighted average. Id., ``Definitions'', p. 1. Between October 
    5, 1995 and October 11, 1995, airborne lead concentrations in the 
    areas affected ranged between 3 micrograms/m3 and 2500 
    micrograms/m3. Between October 12, 1995 and October 26, 1995, 
    airborne lead concentrations ranged between 1 microgram/m3 and 
    250 micrograms/m3.
    ---------------------------------------------------------------------------
    
        In view of the above, this activity was permissible for safety 
    reasons, and, therefore, would have been allowed in a comparable 
    situation before approval of a decommissioning plan, under the pre-
    1993 interpretation of the Commission's decommissioning regulations.
    
    (2) Waste Tank Removal (Activity Decay and Dilution Tank)
    
        Petitioners concede that completion of this activity was 
    required for safety reasons.
    
    (3) Removal of Component Cooling Water System Pipes and Components 
    and Spent Fuel Cooling System Pipes and Components
    
        Contrary to Petitioners' assertions, the staff's February 2, 
    1996, letter did not ``abandon'' the November 2, 1995, rationale for 
    finding this activity permissible. The staff's February 2 letter 
    repeated the November 2 rationale and provided a more detailed 
    explanation for the staff's conclusion that this activity is 
    permissible under the pre-1993 interpretation of the Commission's 
    decommissioning regulations.
        The Licensee had installed a self-contained spent fuel pool 
    cooling system, isolated from the fluid components and installed 
    conduit to allow future electrical isolation from other systems, in 
    order to enhance safety and integrity of the spent fuel pool for 
    prolonged storage of fuel. As a result, the Component Cooling Water 
    System pipes and components and Spent Fuel Cooling System pipes and 
    components were rendered redundant and were no longer useful.
        Removal of the no-longer useful pipes and components was not 
    decommissioning, but maintenance that would have been allowed, 
    before approval of a decommissioning plan, under the pre-1993 
    interpretation of the Commission's decommissioning 
    regulations.7 Petitioners erroneously contend that removal of 
    this equipment is not maintenance. Removal of replaced equipment (as 
    opposed to removal of dismantled equipment not intended to be 
    replaced) is a normal maintenance activity.
    
        \7\ Petitioners assert that the staff provided no factual 
    support for its conclusion that leaving the Component Cooling Water 
    System and Spent Fuel Cooling System pipes and components in place 
    would pose a safety hazard. Upon further review, the staff has 
    determined that removal was not necessary to prevent a safety 
    hazard.
    ---------------------------------------------------------------------------
    
        In view of the above, this activity was permissible, before 
    approval of a decommissioning plan, under the pre-1993 
    interpretation of the Commission's decommissioning regulations.
    
    (4) Ion Exchange Pit Clean-up
    
        Petitioners concede that completion of this activity was 
    required for safety reasons.
    
    (5) Fuel Chute Isolation
    
        The Licensee made a commitment to NRC to complete a Fuel Chute 
    isolation project, needed to enhance spent fuel pool integrity and 
    long-term reliability, in response to NRC Bulletin 94-01, 
    ``Potential Fuel Pool Draindown Caused by Inadequate Maintenance 
    Practices at Dresden Unit 1'' (April 14, 1994). NRC Bulletin 94-01 
    explicitly identified potential siphon or drainage paths and 
    freezing failures as hazards that could lead to drainage of the 
    spent fuel pool.8 NRC Bulletin 94-01 required licensees to 
    identify which of the suggested actions that the licensees would 
    take to prevent such hazards, or to identify an alternative course 
    of action, if the licensees needed to take such measures to bring 
    themselves into compliance as described in NRC Bulletin 94-01.
    
        \8\ Requested action number 2 was: ``Ensure that systems for 
    essential area heating and ventilation are adequate and appropriate 
    maintenance so that potential freezing failures that could cause 
    loss of SFP water inventory are precluded.'' Requested action number 
    3 was: ``Ensure that piping or hoses in or attached to the SFP 
    cannot serve as siphon or drainage paths in the event of piping or 
    hose degradation or failure or the mispositioning of system 
    valves.''
    ---------------------------------------------------------------------------
    
        YAEC's Fuel Chute isolation project eliminated a potential 
    freezing threat and siphon path that could lead to drainage of the 
    spent fuel pool. The NRC staff determined actions taken to prevent 
    potential siphon paths and freezing hazards connected with the Fuel 
    Chute to be adequate. NRC Inspection Report No. 50-029/94-80 
    (December 9, 1994).
        Petitioners erroneously maintain that isolation of the upper 
    Fuel Chute is not necessary to prevent a risk of siphoning or 
    freezing, because the upper Fuel Chute lies above the fuel pool and 
    cannot serve as a siphon for liquid in the pool. The fuel chute pipe 
    originally ran from the lower lock valve at the outside wall at the 
    bottom of the spent fuel pit (SFP) on a diagonal path to the outer 
    shell of the vapor container (VC), through the shell and into the 
    VC. During former plant operations a blank flange was inserted in 
    the pipe, outside the VC shell, in order to maintain VC leak tight 
    integrity.
        As part of the NRC Bulletin 94-01 project, one 8-foot length of 
    this 12 inch diameter fuel chute pipe was removed from the top of 
    the lower lock valve and a blank flange placed over the lower lock 
    valve so that the valve could be encased in concrete. This, in 
    effect, made the valve part of the SFP wall. The removal of this 
    section of pipe also eliminated a potential leak path through the 
    pipe out of the SFP wall.
        Isolation of the Fuel Chute, accomplished by removing the lowest 
    flanged pipe section and sealing the lower portion of the Fuel Chute 
    with concrete, eliminated a freezing and siphon hazard. Sealing the 
    Fuel Chute with concrete prevents accumulation of water in the Fuel 
    Chute. Accumulated water could freeze during severe winter weather 
    and possibly damage the lower lock valve outside the spent fuel pool 
    wall, thus opening a leak path near the bottom of the spent fuel 
    pool.
        Petitioners incorrectly maintain that the Licensee did not need 
    to remove the upper Fuel Chute in order to comply with NRC Bulletin 
    94-01. The licensee did not remove the upper fuel chute. The 
    licensee has fastened a blank flange at the wall of the VC by 
    wedging open a flanged joint. This was a maintenance activity. This 
    blank flange is normally in place and was removed, in the past, when 
    fuel transfer operations took place. These transfers are now 
    prohibited by the POL. The Fuel Chute isolation project was 
    necessary to prevent potential siphon 
    
    [[Page 7830]]
    and freezing risks, was one of the actions determined to be an adequate 
    response to NRC Bulletin 94-01, and brought the Licensee into 
    compliance with NRC requirements.
        In any event, this activity is not decommissioning, but 
    maintenance and a safety upgrade that would have been allowed under 
    the pre-1993 interpretation of the Commission's decommissioning 
    regulations.
        In view of the above, this activity was permissible, before 
    approval of a decommissioning plan, under the pre-1993 
    interpretation of the Commission's decommissioning regulations.
    
    (6) Removal of Emergency Diesel Generators
    
        Petitioners acknowledge that removal of the emergency diesel 
    generators is a permissible activity prior to final approval of a 
    decommissioning plan.
    
    (7) Spent Fuel Pool Electrical Conduit Installation
    
        This activity involved underground installation of a power cable 
    and its protective covering and did not involve the removal of 
    radioactive material. The modification also enhanced the integrity 
    and long-term safe storage of spent fuel in the Spent Fuel Pool, by 
    isolating Spent Fuel Pool power supplies from potential problems 
    that could be caused by power circuits in other systems or heavy 
    load impacts at the plant. The activity was part of the Licensee's 
    overall project to enhance the safety of the Spent Fuel Pool by 
    establishing independent systems dedicated to Spent Fuel Pool 
    reliability.
        The conduit installation was also consistent with NRC Bulletin 
    94-01, specifically the first requested action, which involves 
    ensuring the integrity of structures and systems, necessarily 
    including electrical systems, required for containing, cooling, 
    cleaning, level monitoring and makeup of water in the Spent Fuel 
    Pool. The conduit installation project enhanced integrity of the 
    spent fuel pool by ensuring operability and adequacy of structures 
    and systems required for spent fuel pool integrity, specifically the 
    electrical system.
        Petitioners object that the November 2, 1995 letter implies that 
    this activity is a decommissioning activity because it will provide 
    a separate power supply for future decommissioning activities. 
    Petitioners contend that there is no present threat to the integrity 
    of the spent fuel pool, and that as long as the Licensee performs no 
    major dismantlement activities, there is no immediate need for 
    conduit installation.
        While it is true that conduit installation will isolate the 
    spent fuel power supply from potential problems associated with 
    future decommissioning of other systems, conduit installation also 
    serves the larger purpose of isolating spent fuel pool power 
    supplies from potential problems that could be caused by power 
    circuits in other systems at the plant, wholly apart from the 
    conduct of any decommissioning activities. This activity represents 
    a safety enhancement.
        In view of the above, this activity was permissible, before 
    approval of a decommissioning plan, under the pre-1993 
    interpretation of the Commission's decommissioning regulations.
    
    (8) Brookhaven National Laboratory Cable Sampling Project
    
        Petitioners acknowledge that this activity is a research project 
    unrelated to decommissioning.
    
    (9) Radioactive Materials Shipments
    
        Under the pre-1993 interpretation of the Commission's 
    decommissioning regulations and 10 CFR Sec. 50.59, the NRC has 
    permitted shipment of radioactive waste and contaminated components 
    prior to approval of a decommissioning plan, as long as it does not 
    materially and demonstrably affect the methods or options available 
    for decommissioning or substantially increase the cost of 
    decommissioning, and because such shipments do not constitute a 
    ``major'' activity.
        NRC staff practice prior to 1993 permitted activities such as 
    shipment of waste or contaminated components at a permanently 
    defueled facility pursuing decommissioning. Prior to approval of a 
    decommissioning plan, the licensee may dismantle and dispose of 
    nonradioactive components and structures not required for safety in 
    the shutdown condition. After issuance of a possession-only license, 
    the licensee also may dismantle and dispose of radioactive 
    components not required for safety in the shutdown condition, 
    provided that such activity does not involve major structural or 
    other major changes and does not foreclose alternative 
    decommissioning methods or materially affect the cost of 
    decommissioning. Long Island Lighting Company (Shoreham Nuclear 
    Power Station, Unit 1), CLI-91-08, 33 NRC 461, 471 (1991), approving 
    staff recommendations in SECY-91-129, ``Status and Developments at 
    the Shoreham Nuclear Power Station'' (May 13, 1991). See also NRC 
    Inspection Manual, Chapter 2561, Secs. 06.06 and 06.07 (March 20, 
    1992); Fort St. Vrain Nuclear Generating Station Amendment No. 82 to 
    Facility Operating License No. DPR-34 (Possession-Only License, May 
    21, 1991); and Rancho Seco Nuclear Generating Station Amendment No. 
    117 to Facility Operating License No. DPR-54 (Possession-Only 
    License, March 17, 1992).
        Petitioners contend that the February 2, 1996, letter of the NRC 
    staff applied the post-1993 interpretation of the Commission's 
    decommissioning regulations to determine that shipment of low-level 
    radioactive waste is permissible,\9\ based on the staff's citation 
    to SECY 92-382 and the associated June 30, 1993 SRM. The particular 
    language Petitioners point to is:
    
        \9\ Petitioners incorrectly contend that the staff's conclusion, 
    that the methods or options available for decommissioning will not 
    be materially or demonstrably affected because the Licensee's 
    activities involve approximately 2.3 curies of residual activity, 
    constitutes application of the Licensee's one percent criterion. The 
    Licensee had proposed in its letter of October 24, 1995, that 
    decommissioning activities involving less than one percent of the 
    total curies of non-fuel components not including greater than Class 
    C components, are not ``major'' decommissioning activities and thus 
    are permissible under the pre-1993 interpretation of the 
    Commission's decommissioning regulations. As previously stated, the 
    NRC staff does not accept or approve, and did not use, this 
    criterion in its February 2, 1996 (or its November 2, 1995) letter 
    to determine whether activities proposed by the Licensee, including 
    shipping, are ``major'' activities for purposes of permissible 
    decommissioning before approval of a decommissioning plan. See, 
    e.g., note 5, supra. The staff in fact stated that since the 
    Licensee's activities involve only 2.3 curies out of a total 4448 
    curies residual activity which must be decommissioned, shipment of 
    low-level radioactive waste will not demonstrably affect the methods 
    or options available for decommissioning.
    ---------------------------------------------------------------------------
    
        Shipment of contaminated reactor internals needed for operation 
    could proceed after issuance of a possession-only license because 
    such components are not ``major'': i.e., they are not needed to 
    maintain safety in the defueled condition. See SECY 92-382, 
    ``Decommissioning--Lessons Learned'' (November 10, 1992) and Staff 
    Requirements Memorandum, ``SECY-92-382--Decommissioning--Lessons 
    Learned'' (June 30, 1993).
    
    The staff's February 2, 1996, letter derived this language from a 
    discussion at pages 22-24 of SECY-92-382, ``Decommissioning--Lessons 
    Learned''.
        The Commission had in fact permitted shipment of low-level waste 
    prior to approval of a decommissioning plan under its pre-1993 
    interpretation of its decommissioning regulations, as explained 
    above. SECY 92-382 accurately stated that the Commission had in fact 
    permitted shipment of not only low-level radioactive waste and some 
    components, but also some reactor internals, before approval of a 
    decommissioning plan.\10\ The particular reference to ``major'' 
    components in SECY 92-382 was in the context of permissible shipment 
    of waste; that language did not define ``major'' for the purpose of 
    determining what components may be dismantled or removed prior to 
    approval of a decommissioning plan. No component can be shipped 
    unless it is first removed or dismantled, and authority to ship a 
    component already removed or dismantled does not ipso facto 
    constitute authority to remove or dismantle the component in the 
    first place. Likewise, the citation in the NRC staff's February 2, 
    1996, letter to Petitioners was not intended to define ``major'' for 
    the purpose of determining what components could be dismantled or 
    removed prior to approval of a decommissioning plan, but referred to 
    what could be shipped. The staff's reference to SECY 92-382 was made 
    in the context of permissible shipments only, not permissible 
    component dismantling or removal. Regrettably, the staff's February 
    2, 1995, reference to SECY 92-382 may have been insufficiently 
    detailed to make the purpose of the reference clear.
    
        \10\ See Long Island Lighting Company (Shoreham Nuclear Power 
    Station, Unit 1), CLI-91-8, 33 NRC 461, 471 (1991). See also SECY-
    91-129, ``Status and Developments at the Shoreham Nuclear Power 
    Station (SNPS)'', p. 3 (May 13, 1991) (contaminated fuel support 
    castings and peripheral pieces).
    ---------------------------------------------------------------------------
    
        In the case at hand, the Licensee's proposal was to ship low-
    level radioactive waste.\11\ 
    
    [[Page 7831]]
    The NRC staff's conclusion that the Licensee's proposal to ship 
    radioactive waste\12\ is permissible under the pre-1993 
    interpretation of the Commission's decommissioning regulations was 
    based on the understanding that the proposal was to ship low-level 
    radioactive waste, and was not intended to be and was not a 
    determination that the removal or dismantling of major components 
    was permissible under the pre-1993 interpretation of the 
    Commission's decommissioning regulations,\13\ under CAN v. NRC, or 
    under CLI-94-14.
    
        \11\ Petitioners contend that there is no basis to determine the 
    accuracy of the Licensee's estimate that it will make 54 shipments 
    of low-level radioactive waste between October 1995 and July 1996. 
    Petitioners, however, fail to set forth any facts or rationale which 
    raise a question as to the reasonableness of the Licensee's estimate 
    of the number of shipments.
        \12\ Petitioners state that neither YAEC nor the NRC staff 
    provided any information about the radioactivity levels in the 54 
    shipments that YAEC estimates it shipped and will ship between 
    October 1995 and July 1996, and that the Licensee's January 29, 
    1996, estimate of 2.3 curies involved in activities already 
    completed does not provide information about radioactivity levels of 
    the 54 shipments that YAEC estimates it will have shipped before the 
    end of July 1996. The Licensee has now provided that information and 
    estimates the total radioactivity involved in the packaging and 
    shipment of low-level radioactive waste between November 1, 1995 and 
    July 1996, to be 1817 curies. See letter dated February 21, 1996, 
    from K. J. Heider, YAEC, to Morton B. Fairtile, NRC. The four 
    contested activities, other than shipping, amounted to only 
    approximately 8.2001 curies of residual radioactivity.
        \13\ Petitioners assert that the NRC staff's February 2, 1966, 
    letter states that the shipment of low-level radioactive waste is 
    permitted under the pre-1993 criteria because the radioactivity of 
    the shipments amounts to 2.3 curies or less out of the remaining 
    4448 curies of residual radioactivity to be decommissioned in the 
    form of Class C or less waste. What the staff said was that because 
    the Licensee's activities involve approximately 2.3 curies of the 
    remaining 4448 curies of residual radioactivity to be decommissioned 
    in the form of Class C or less waste, shipment of low-level 
    radioactive waste produced by the activities evaluated in the 
    staff's November 2, 1995 letter will not materially or demonstrably 
    affect the methods or options available for decommissioning the 
    Yankee Rowe site.
    ---------------------------------------------------------------------------
    
        The Commission's decisions in Long Island Lighting Company 
    (Shoreham Nuclear Power Station, Unit 1), CLI-92-1, 33 NRC 61, 73, 
    n. 5 (1991) and Sacramento Municipal Utility District (Rancho Seco 
    Nuclear Generating Station), CLI-92-2, 35 NRC 47, 61, n. 7 (1992) do 
    not, as Petitioners contend, prohibit shipment of low-level 
    radioactive waste. No issue concerning such shipments was addressed 
    in those decisions. The language cited by Petitioners paraphrases 
    the general guideline, that ``major dismantling and other activities 
    that constitute decommissioning under the NRC's regulations must 
    await NRC approval of a decommissioning plan'', and is derived from 
    the 1988 Statement of Consideration, ``General Requirements for 
    Decommissioning Nuclear Facilities'', supra. As explained above, it 
    was agency practice before 1993 to permit shipment of low-level 
    radioactive waste and contaminated components before approval of a 
    decommissioning plan.
        Rather than store low-level radioactive waste on-site for 
    extended periods, it has long been agency policy that such waste 
    should be shipped to disposal sites if the ability to dispose of 
    waste at a licensed disposal site exists. Shipping of waste at the 
    earliest practicable time minimizes the need for eventual waste 
    reprocessing due to possibly changing burial ground requirements and 
    reduces occupational and non-occupational exposures and potential 
    accident consequences. NRC Generic Letter 81-38, ``Storage of Low-
    Level Radioactive Wastes at Power Reactor Sites'' (November 10, 
    1981).
        Petitioners contend that YAEC may not ship low-level radioactive 
    waste because the Yankee Rowe Possession-Only-License does not 
    permit it.14 Although Petitioners are correct that no language 
    in the Yankee Rowe POL explicitly states that shipment of low-level 
    radioactive waste is authorized, the Yankee Rowe POL does authorize 
    that activity. Section 1.H. of the POL, issued August 5, 1992, 
    authorizes Yankee Rowe to receive, possess and use byproduct, source 
    and special nuclear materials in accordance with the Commission's 
    regulations in 10 CFR Parts 30, 40 and 70. Authority to ship low-
    level radioactive waste is conferred upon all byproduct material, 
    source material and special nuclear material licensees by NRC 
    regulations at 10 CFR Parts 30, 40 and 70. Byproduct materials 
    licensees, source materials licensees, and special nuclear materials 
    licensees, including Yankee Rowe, are authorized to transfer such 
    material, as long as the recipient is authorized, see 10 CFR 
    Secs. 30.41, 40.51, and 70.42, and as long as preparation for 
    shipment and transport is in accordance with the requirements of 10 
    CFR Part 71. See 10 CFR Secs. 30.34(c), 40.41(c), 70.41(a). In 
    particular, Section 2.C. of the Yankee Rowe POL states that the POL 
    is deemed to contain and is subject to 10 CFR Secs. 30.34 and 40.41. 
    Accordingly, the POL authorizes the transport of low-level 
    radioactive waste from Yankee Rowe.
    
        \14\  Petitioners claim that the Commission's decommissioning 
    regulations prohibit low-level radioactive waste shipments that are 
    not authorized by YAEC's license, citing the 1988 Statement of 
    Consideration. See ``General Requirements for Decommissioning 
    Nuclear Facilities'', 53 FR 24025-26 (June 27, 1988). The Statement 
    of Consideration makes no mention of shipment of low-level 
    radioactive waste. The language cited gives examples of activities 
    which licensees may conduct before approval of a decommissioning 
    plan, but does not state or imply that the list is inclusive: 
    ``Although the Commission must approve the decommissioning 
    alternative and major structural changes to radioactive components 
    of the facility or other major changes, the licensee may proceed 
    with some activities such as decontamination, minor component 
    disassembly, and shipment and storage of spent fuel if these 
    activities are permitted by the operating license and/or 
    Sec. 50.59''. (Emphasis added)
    ---------------------------------------------------------------------------
    
        Petitioners state that the ``cardinal consideration'' which 
    determines whether a decommissioning activity is ``major'' should be 
    the radiation dose it yields, not the radioactivity of the component 
    involved 15, and thus the NRC staff's February 2, 1996, letter 
    erroneously relied upon the number of curies shipped rather than the 
    radioactive doses involved in shipping low-level waste to determine 
    whether the activity is permissible.16
    
        \15\  The Commission has not articulated as a criterion, for 
    determining what constitutes a ``major'' decommissioning activity, 
    the radiation dose yielded by the activity, and Petitioners cite no 
    authority for this argument. Nor has the Commission articulated the 
    radioactivity involved as a criterion for determining what 
    constitutes ``major'' decommissioning activity.
        \16\ The staff mistakenly understood the License's letter of 
    January 29, 1996 to mean that the activities evaluated by the 
    staff's November 2, 1995 letter involved 2.3 curies. The 
    radioactivity involved in the four contested activities, other than 
    shipping of low-level radioactive waste, amounted to approximately 
    8.2001 curies of residual radioactivity. (Removal of the Upper 
    Neutron Shield Tank involved less than 5 curies, and removal of the 
    Component Cooling Water System pipes and components and Spent Fuel 
    Cooling System pipes and components involved 1.2001 curies. See 
    letter dated October 19, 1995, from Russell A. Mellor, YAEC, to 
    Morton B. Fairtile, NRC. Fuel Chute Isolation involved 2 curies, and 
    spent fuel pool electrical conduit installation involved no curies. 
    See letter dated February 21, 1996, from K. J. Heider, YAEC, to 
    Morton B. Fairtile, NRC.) In addition, the Licensee estimated that 
    since completion of the activities described in the NRC letter, 
    activities have been authorized by the Licensees' Manager of 
    Operations which remove components containing a total of 2.3 curies 
    of radioactive material. See letter dated January 29, 1996, from 
    Andrew C. Kadak, YAEC, to William T. Russell, NRC.
    ---------------------------------------------------------------------------
    
        The criteria for determining whether shipments of low-level 
    radioactive waste will demonstrably affect the methods or options 
    available for decommissioning have not been well-defined. During 
    review of the Petition and its supplement, the NRC staff has 
    continued to examine the question of whether the Licensee's 
    shipments of low-level radioactive waste will demonstrably affect 
    the methods or options available for decommissioning. In this case, 
    the staff has now also compared the radiation dose involved in the 
    packaging and shipping of the low-level radioactive waste with the 
    radiation dose estimated for decommissioning of the Licensee's 
    facility. This is because, under Petitioners' theory regarding the 
    choice of the decommissioning option, as we understand it, it seems 
    that adoption of a different decommissioning option would most 
    likely be required to reduce dose. The Licensee estimates that the 
    radiation dose involved in the packaging and shipment of low-level 
    radioactive waste between November 1, 1995 and July 1996 to be 17 
    person-rem.17 The estimated total radiation exposure for 
    decommissioning the facility is 755 person-rem.18 The estimated 
    dose from packaging and shipping is approximately 2% of the total 
    dose from decommissioning. As can be seen, most of the dose will be 
    incurred in activities other than shipment of low-level radioactive 
    waste. As the Commission has previously held in this case, even 
    potential dose reductions on the order of 900 person-rem, unless 
    there is some extraordinary aspect to the case not apparent, cannot 
    have ALARA significance such that one decommissioning option 
    
    [[Page 7832]]
    would be preferable to another.19 Accordingly, the staff concludes 
    that the Licensee's shipment of low-level radioactive waste will not 
    demonstrably affect the methods and options available for 
    decommissioning.
    
        \17\ See letter dated February 21, 1996, from K. J. Heider, 
    YAEC, to Morton B. Fairtile, NRC.
        \18\ Order Approving the Decommissioning Plan and Authorizing 
    Decommissioning of Facility (Yankee Nuclear Power Station), 
    ``Environmental Assessment by the U.S. Nuclear Regulatory Commission 
    Related to the Request to Authorize Facility Decommissioning'', p. 
    22.
        \19\ Yankee Atomic Electric Company, CLI-96-01 (January 16, 
    1996).
    ---------------------------------------------------------------------------
    
        In view of the above, the shipments of low-level radioactive 
    waste between October 1995 and July 1996, before approval of a 
    decommissioning plan, is permissible under the pre-1993 
    interpretation of the Commission's decommissioning regulations.
        B. The five contested activities will neither individually nor 
    collectively substantially increase the costs of decommissioning.
        YAEC estimates the cost of shipment and disposal of all low-
    level radioactive waste between the October 1995 issuance of CLI-95-
    14 and the scheduled date of completion of the hearing in mid-July 
    1996, to be $6.5 million, or approximately 1.75 percent of the 
    estimated $368.8 million total decommissioning cost. It would be 
    speculative to conclude that the decommissioning method proposed by 
    Petitioners, SAFSTOR, would be less expensive. There is no evidence 
    that the Licensee's shipments will increase decommissioning costs or 
    that continued storage of the waste will decrease the ultimate 
    costs. Thus, the staff concludes that YAEC's shipment of low-level 
    radioactive waste will not substantially increase the costs of 
    decommissioning.
        Petitioners erroneously contend that the cost of shipments of 
    low-level radioactive waste could be reduced by postponing the 
    packaging and shipment of low-level waste, presumably because some 
    waste may decay to levels such that the volume of waste which will 
    require shipment would decrease. Delay will not significantly reduce 
    the volume of waste shipped because the waste is not segregated by 
    the radioactive isotope involved, and some of the radioactive 
    isotopes involved have very long half-lives, i.e., nickel-63 has a 
    half-life of 100 years. Cobalt-60, which has a half-life of 5.27 
    years, was the isotope selected by the Petitioners to postulate a 
    reduction in waste volume. Moreover, delay could possibly increase 
    decommissioning costs because shipping and burial costs may 
    increase.
        The Licensee estimates costs for the five activities contested 
    by Petitioners to be $6.5 million for shipments of low-level waste 
    between October 1995 and July 1996 and $2.4 million for the four 
    other contested activities,20 for a total of $8.9 million, or 
    2.1% of the $368.8 million estimated total decommissioning costs. 
    There is no evidence that these activities will give rise to 
    consequences that will increase the total cost of decommissioning. 
    Accordingly, the five contested activities will not substantially 
    increase decommissioning costs, either individually or collectively.
    
        \20\ The Licensee spent $610,000 on the four activities in the 
    fourth quarter of 1995, which is approximately 25 percent of the 
    estimated total cost for these four activities. See Letter dated 
    February 15, 1996, from Russell A. Mellor to Morton B. Fairtile.
    ---------------------------------------------------------------------------
    
        C. Petitioners' Request for an Inspection and Inspection Report 
    Was Granted.
        Petitioners' request for reinspection of Yankee Rowe to 
    determine compliance with CLI-95-14 and for issuance of an 
    inspection report was granted. NRC Region I inspected the Yankee 
    Rowe facility for a second time on December 5-18, 1995, to determine 
    compliance with CLI-95-14. NRC Inspection Report No. 50-029/95-07 
    was issued January 31, 1996. The Inspection Report concludes that 
    the Licensee's activities were conducted in accord with the 
    specifications of the staff's November 2, 1995 letter. The first 
    inspection was conducted in October 1995, before the provision of 
    technical guidance or criteria to assist the Region in determining 
    compliance with CLI-95-14. Subsequently, the NRC staff issued its 
    letter of November 2, 1995, evaluating the nine activities, all of 
    which are permitted by CAN v. NRC and CLI-95-14, as explained above.
        Petitioners claim that the January 31, 1996 Inspection Report 
    merely repeats the staff's erroneous interpretation of the 
    Commission's decommissioning standards, and thus constitutes no 
    relief. The inspection report explicitly states that the nine 
    activities evaluated by the staff's November 2, 1995 letter were 
    inspected and that the Licensee limited the scope of its work to 
    those activities. Petitioners' disagreement with the staff's 
    conclusion that the nine activities are in compliance with CAN v. 
    NRC and CLI-95-14 does not constitute denial of Petitioners' request 
    for an inspection and an inspection report to determine compliance 
    with CAN v. NRC and CLI-95-14.
    
    IV. Conclusion
    
        For the reasons given above, Petitioner's request that shipments 
    of low-level radioactive waste be prohibited is denied, and 
    Petitioners' request that four other activities be prohibited is 
    moot.21 Additionally, Petitioners' request for an inspection of 
    Yankee Rowe to determine compliance with CLI-95-14 and an inspection 
    report was granted.
    
        \21\ Petitioners claim that the NRC erroneously found on 
    February 2, 1996, that the request for emergency relief was moot in 
    part. Petitioners assert that the Licensee continues to unlawfully 
    ship low-level radioactive waste and that on January 29, 1996, the 
    Licensee stated that it is considering whether to conduct seven 
    activities, in addition to the nine evaluated by the staff's 
    November 2, 1995, letter. The February 2, 1996, letter of the staff 
    and this Decision explicitly denied Petitioner's request to prohibit 
    shipment of low-level radioactive waste, and made no finding that 
    this request is moot. The February 2, 1996, letter and this Decision 
    explicitly state that Petitioners' request for emergency relief 
    regarding the remaining four contested activities was moot because 
    those activities had been completed before the submission of the 
    Petition. Nonetheless, both the February 2, 1996 letter and this 
    Decision found that those four activities were permissible, prior to 
    approval of a decommissioning plan, under the pre-1993 
    interpretation of the Commission's decommissioning regulations. 
    Neither the staff's February 2, 1996, letter, nor this decision 
    address the seven activities which the Licensee states it is now 
    considering. The staff will address those activities in a 
    supplemental Director's Decision, as required by the Commission's 
    order of February 15, 1996.
    ---------------------------------------------------------------------------
    
        As provided by 10 CFR Sec. 2.206(c), a copy of this Decision 
    will be filed with the Secretary of the Commission for the 
    Commission's review. The Decision will become the final action of 
    the Commission 25 days after issuance, unless the Commission on its 
    own motion institutes review of the Decision within that time.
    
        Dated at Rockville, Maryland this 22nd of February, 1996.
    
        For the Nuclear Regulatory Commission.
    William. T. Russell,
    Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 96-4683 Filed 2-28-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
02/29/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
96-4683
Dates:
03/20/92).4
Pages:
7825-7832 (8 pages)
Docket Numbers:
Docket No. 50-029
PDF File:
96-4683.pdf