2024-04177. Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions; ...  

  • Start Preamble

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

    a. Type of Application: New Major License.

    b. Project No.: 1892–030.

    c. Date Filed: May 1, 2017; material amendment filed December 7, 2020.

    d. Applicant: Great River Hydro, LLC (Great River Hydro).

    e. Name of Project: Wilder Hydroelectric Project (project).

    f. Location: The project is located on the Connecticut River in Orange and Windsor Counties, Vermont, and Grafton County, New Hampshire.

    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r).

    h. Applicant Contact: John Ragonese, FERC License Manager, Great River Hydro, LLC, 40 Pleasant Street, Suite 202, Portsmouth, NH 03801; (603) 498–2851 or jragonese@greatriverhydro.com.

    i. FERC Contact: Steve Kartalia, (202) 502–6131 or stephen.kartalia@ferc.gov.

    j. Deadline for filing motions to intervene and protests, comments, recommendations, preliminary terms and conditions, and preliminary fishway prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice.

    The Commission strongly encourages electronic filing. Please file motions to intervene and protests, comments, recommendations, terms and conditions, and prescriptions using the Commission's eFiling system at https://ferconline.ferc.gov/​FERCOnline.aspx.Start Printed Page 14820 Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/​QuickComment.aspx. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–1892–030.

    The Commission's Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    k. This application has been accepted and is ready for environmental analysis at this time.

    l. Project Description: The Wilder Project consists of: (1) a 1,546-foot-long, 59-foot-high, concrete dam that includes: (a) a 400-foot-long non-overflow, earthen embankment (north embankment); (b) a 232-foot-long non-overflow, concrete bulkhead; (c) a 208-foot-long concrete forebay; (d) a 526-foot-long concrete, gravity spillway that includes: (i) six 30-foot-high, 36-foot-long tainter gates; (ii) four 17-foot-high, 50-foot-wide stanchion flashboards; (iii) a 15-foot-high, 20-foot-long skimmer gate (north gate); and (iv) a 10-foot-high, 10-foot-long skimmer gate (south gate); and (e) a 180-foot-long non-overflow, earthen embankment (south embankment); (2) a 45-mile-long, 3,100-acre impoundment with a useable storage volume of 13,350 acre-feet between elevations 380 and 385 feet National Geodetic Vertical Datum of 1929 (NGVD 29); (3) four approximately 25-foot-high, 20-foot-wide trashracks with 5-inch clear bar spacing and one approximately 28-foot-high, 20-foot-wide trashrack with 1.625-inch clear bar spacing; (4) a 181-foot-long, 50-foot-wide, 50-foot-high steel frame, brick powerhouse containing two 16.2-megawatt (MW) adjustable-blade Kaplan turbine-generator units and one 3.2–MW vertical Francis turbine-generator unit for a total project capacity of 35.6 MW; (5) three concrete draft tubes ranging from 9.5 to 20.5 feet in diameter; (6) 13.8-kilovolt generator leads that connect the turbine-generator units to two substation transformers; (7) an approximately 580-foot-long, 6-foot-wide fishway; and (8) appurtenant facilities.

    Great River Hydro operates the project in a peaking mode in coordination with its downstream Bellows Falls Project No. 1855 and Vernon Project No. 1904. Average annual generation is approximately 156,303 MW-hours. Great River Hydro is proposing changes to project operation that would reduce impoundment fluctuations and increase the stability of downstream flow releases relative to current project operation, including targeted water surface elevation levels and flow ramping rates. Great River Hydro also proposes several protection, mitigation, and enhancement measures for aquatic, terrestrial, cultural, recreation resources, and threatened and endangered species. The specific proposed changes are described in the amended application and the settlement agreement filed on August 4, 2022.

    m. A copy of the application can be viewed on the Commission's website at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support.

    n. Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.

    All filings must: (1) bear in all capital letters the title “PROTEST,” “MOTION TO INTERVENE,” “COMMENTS,” “REPLY COMMENTS,” “RECOMMENDATIONS,” “PRELIMINARY TERMS AND CONDITIONS,” or “PRELIMINARY FISHWAY PRESCRIPTIONS;” (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions, or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.

    The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ferc.gov.

    You may also register online at https://ferconline.ferc.gov/​FERCOnline.aspx to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

    o. The applicant must file no later than 60 days following the date of issuance of this notice: (1) a copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification.

    p. Procedural Schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate.

    MilestoneTarget date
    Deadline for filing motions to intervene, protests, comments, recommendations, preliminary terms and conditions, and preliminary fishway prescriptionsApril 2024.
    Deadline for filing reply commentsMay 2024.

    q. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of this notice.

    Start Signature
    Start Printed Page 14821

    Dated: February 22, 2024.

    Debbie-Anne A. Reese,

    Acting Secretary.

    End Signature End Preamble

    [FR Doc. 2024–04177 Filed 2–28–24; 8:45 am]

    BILLING CODE 6717–01–P

Document Information

Published:
02/29/2024
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2024-04177
Pages:
14819-14821 (3 pages)
Docket Numbers:
Project No. 1892-030
PDF File:
2024-04177.pdf