94-2391. Use of Decommissioning Trust Funds Before Decommissioning Plan Approval; Draft Policy Statement  

  • [Federal Register Volume 59, Number 23 (Thursday, February 3, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-2391]
    
    
    [[Page Unknown]]
    
    [Federal Register: February 3, 1994]
    
    
    -----------------------------------------------------------------------
    
    
    NUCLEAR REGULATORY COMMISSION
     
    
    Use of Decommissioning Trust Funds Before Decommissioning Plan 
    Approval; Draft Policy Statement
    
    AGENCY: Nuclear Regulatory Commission.
    
    ACTION: Draft policy statement.
    
    -----------------------------------------------------------------------
    
    SUMMARY: This draft policy statement presents the criteria the U.S. 
    Nuclear Regulatory Commission (NRC) proposes to follow in addressing 
    requests from power reactor licensees that have permanently shut down 
    their power reactors to make withdrawals from external decommissioning 
    sinking funds to pay for the removal of components and other 
    decommissioning-related activities before the NRC approves these 
    licensees' decommissioning plans submitted pursuant to 10 CFR 50.82. 
    This draft policy statement also covers de minimis withdrawals from 
    external decommissioning sinking funds to pay for developing the 10 CFR 
    50.82 decommissioning plan and for other post-shutdown administrative 
    expenses.
    
    DATE: Comment period expires April 19, 1994. Comments received after 
    this date will be considered if it is practical to do so, but the 
    Commission is able to ensure consideration only for comments received 
    on or before this date.
    
    ADDRESSES: Mail written comments to: Secretary, U.S. Nuclear Regulatory 
    Commission, Washington, DC 20555, Attention: Docketing and Service 
    Branch.
    
        Deliver comments to: 11555 Rockville Pike, Rockville, Maryland, 
    between 7:45 am and 4:15 pm on Federal workdays.
    
    FOR FURTHER INFORMATION CONTACT:
    Robert Wood, Office of Nuclear Reactor Regulation, U.S. Nuclear 
    Regulatory Commission, Washington, DC 20555, telephone: (301) 504-1255.
    
    SUPPLEMENTARY INFORMATION:
    
    Background
    
        The NRC decommissioning regulations in 10 CFR 50.75 and 50.82 are 
    silent on whether approval of the decommissioning plan must precede 
    withdrawals from the decommissioning trust fund. Appendix B.3.1, p. B-
    12 of Regulatory Guide 1.159, ``Assuring the Availability of Funds for 
    Decommissioning Nuclear Reactors,'' contains sample trust language that 
    indicates that the fund trustee should only release funds upon 
    certification ``that decommissioning is proceeding pursuant to an NRC-
    approved plan.'' However, not all licensees have used this sample 
    language. When the NRC evaluated trust funds as part of the initial 
    certification required by 10 CFR 50.75(b) and submitted in July 1990, 
    it found trusts acceptable if, along with other provisions, they 
    contained language limiting trust fund withdrawals to legitimate 
    decommissioning purposes. Thus, many licensees have acceptable trusts 
    that nevertheless do not expressly limit the withdrawal of trust funds 
    before NRC approves a decommissioning plan.
        Because of a request by Yankee Atomic Electric Company (YAEC)1 
    and in anticipation of future requests by other power reactor licensees 
    of permanently shutdown facilities, the Commission directed the NRC 
    staff to provide an analysis and recommendation to the Commission on 
    permitting licensees to use their decommissioning funds for 
    decommissioning activities prior to approval of the decommissioning 
    plans. The Commission approved the criteria developed by the staff to 
    evaluate early withdrawals from external decommissioning sinking funds 
    and directed the staff to publish the details of this policy in the 
    Federal Register for information and public comment.2 This 
    proposed policy and implementing criteria are provided below:
    ---------------------------------------------------------------------------
    
        \1\In a letter to the Commission dated November 25, 1992, YAEC 
    stated its intention to use its decommissioning trust funds to 
    remove reactor core internals, steam generators and the pressurizer 
    from Yankee-Rowe before the NRC approves YAEC's decommissioning 
    plan. (YAEC plans to submit its decommissioning plan for NRC review 
    in late 1993.) By letter dated April 16, 1993, the NRC did not 
    object to YAEC's proposed use of decommissioning trust funds before 
    NRC approval of the Yankee-Rowe decommissioning plan, using criteria 
    consistent with those discussed in this policy statement.
        2This policy statement does not apply to licensees with 
    operating nuclear reactors. The staff is separately evaluating the 
    issue of whether and under what circumstances the NRC should allow 
    licensees of operating plants to withdraw decommissioning trust 
    funds.
    ---------------------------------------------------------------------------
    
    Statement of Policy
    
        If a licensee of a permanently shutdown facility spends 
    decomissioning trust funds on legitimate decommissioning activities, 
    the timing of these expenditures, either before or after NRC approves a 
    licensee's decommissioning plan, should not adversely affect public 
    health and safety, provided adequate funds are maintained to restore 
    the facility to a safe storage configuration in case decommissioning 
    activities are interrupted unexpectedly. Consequently, the timing of 
    the NRC review of a licensee's decommissioning plan in relation to 
    withdrawals from trust funds is not as important as the purpose of 
    those withdrawals.
        In its decommissioning plan reviews, the NRC evaluates proposed 
    licensee activities in the planned decommissioning process to determine 
    whether the proposed plan adequately ensures protection of public 
    health and safety. The NRC will also assess a licensee's overall 
    decommissioning fund balance in relation to total cost. The NRC review 
    of decommissioning costs is focused on seeing that they fall within a 
    normal range of costs and is not focused on examining the timing, 
    scope, and cost of specific component removal or other decommissioning 
    activities. Therefore, although the NRC believes that it should guard 
    against misuse or waste of decommissioning trust funds by licensees, it 
    is not clear that prior NRC review of the decommissioning plan would 
    identify such misuse or waste unless it resulted in costs far higher 
    than would normally be expected. The NRC would find it difficult to 
    identify the misuse of funds if a licensee's estimates were within a 
    reasonable range of the costs estimated for similar facilities. 
    Further, the NRC does not supervise or review the actual expenditure of 
    funds during decommissioning and would not have an opportunity to 
    identify serious cost overruns that might jeopardize the adequacy of 
    funding available for remaining decommissioning activities.
        However, there appears to be little motivation for utilities to 
    misuse these funds. Most NRC power reactor licensees are subject to 
    rate regulation by State public utility commissions (PUCs) or the 
    Federal Energy Regulatory Commission (FERC). Utilities are normally 
    allowed to earn a return on assets, including nuclear plants, once they 
    are determined to be ``used and useful'' and placed in the rate base. 
    Decommissioning costs, however, are normally treated by PUCs and FERC 
    as non-rate-base expenses. They are passed on to ratepayers as 
    expenses, but the utility and its stockholders do not earn a return on 
    these collections. Consequently, there is little financial incentive 
    for a licensee to ``pad'' or dissipate collected decommissioning funds 
    to increase the rate base, because the stockholders would not benefit.
        Further, PUCs and FERC are unlikely to allow utilities under their 
    jurisdictions to squander funds obtained from ratepayers. Rate 
    regulators hold prudency reviews to determine whether utilities have 
    spent funds properly throughout all aspects of plant operation, from 
    initial planning to final decommissioning. The NRC expects that PUCs 
    and FERC will continue to exercise their oversight of utilities' 
    expenditures, including those being paid from decommissioning trust 
    funds, throughout the decommissioning process. A utility has an 
    incentive to spend decommissioning funds prudently if it knows that its 
    stockholders will be liable for decommissioning costs in excess of 
    those already collected from ratepayers.
        Although NRC approval of the decommissioning plan does not ensure 
    prevention of misuse or waste of decomissioning funds, the NRC believes 
    that withdrawal of funds for decommissioning activities before a 
    decommissioning plan is developed and approved should require NRC 
    review. This is consistent with Commission guidance which provided that 
    the staff may permit licensees to use their decommissioning funds for 
    the decommissioning permitted above (as the term decommission is 
    defined in 10 CFR 50.2), notwithstanding the fact that their 
    decommissioning plans have not yet been approved by the NRC.
    
    Criteria
    
        The criteria and supporting rationale developed to evaluate 
    licensee proposals for early withdrawals from external decommissioning 
    sinking funds are as follows:
        1. The withdrawals are for expenses for legitimate decommissioning 
    activities as defined in 10 CFR 50.2 that would necessarily occur under 
    most reasonable decommissioning scenarios. Section 10 CFR 50.2 defines 
    ``decommission'' as meaning ``to remove (as a facility) safely from 
    service and reduce residual radioactivity to a level that permits 
    release of the property for unrestricted use and termination of 
    licensee.''
        This criterion calls for a licensee to demonstrate that the early 
    withdrawal is for activities that would occur under reasonable 
    decommissioning scenarios and would prevent funds being used for 
    activities that do not reduce radioactivity at the site and ultimately 
    permit release of the property for unrestricted use. A licensee that 
    has already prepared its Sec. 50.82 decommissioning plan (which must be 
    submitted within 2 years after a permanent cessation of operations) 
    could reference the appropriate part of this plan. A licensee that has 
    not yet completed its Sec. 50.82 decommissioning plan would have to 
    provide other documentation to demonstrate that its proposed activities 
    were clearly decommissioning activities.
        2. The expenditures would not reduce the value of the 
    decommissioning trust below an amount necessary to place and maintain 
    the licensee's reactor in a safe storage (SAFSTOR) condition if 
    unforeseen conditions or expenses arise. (For example, if the waste 
    shipments were rejected by the disposal site because of lack of storage 
    space or legal impediments, a licensee would have to show it had the 
    funds to return and store any affected components on site and to store 
    any radioactive components and materials that had remained on-site.)
        Consistent with the purpose of the decommissioning funding 
    regulations, assurance of availability of funds to safely decommission 
    a facility, and the principle that a preapproval activity does not 
    foreclose the release of the site for possible unrestricted use, this 
    criterion calls for a licensee to show that it can maintain the status 
    quo at a facility and that the proposed activities will not preclude 
    the ultimate unrestricted use of the site. A licensee would have to 
    document the rationale for the minimum amount estimated to be needed to 
    return to a safe storage condition if decontamination or removal 
    activities are interrupted and the components and equipment involved 
    have to be stored safely at the site. Such on-site storage after 
    shipment could, in the worst case, require construction of a storage 
    facility. This criterion ensures that decommissioning activities that 
    occur before approval of the Sec. 50.82 decommissioning plan do not 
    reduce funds below a level that would ensure continued maintenance of 
    safety at a defueled, shutdown facility until the decommissioning plan 
    is reviewed and approved. A licensee could satisfy this criterion by 
    demonstrating that it has sufficient funds in either its 
    decommissioning fund or other available funds to maintain the status 
    quo at the facility, that is, maintain safety in the defueled, shutdown 
    condition. It should be noted that this criterion is also pertinent to 
    the normal, end-of-life decommissioning; licensees are to accommodate 
    the possibility of unforeseen occurrences by providing for 
    contingencies. (See Regulatory Guide 1.159 at 1.159-10, Item 1.4.4.3. 
    The general guidance of Regulatory Guide 1.159 concerning provisions 
    for ``contingencies,'' however, does not explicitly identify the nature 
    of such contingencies. The NRC's proposed criterion is more explicit.)
        The NRC notes that 10 CFR 50.82(c)(1) requires that, ``funds needed 
    to complete decommissioning be placed into an account segregated from 
    licensee assets and outside the licensee's administrative control 
    during the storage or surveillance period, or a surety method or fund 
    statement of intent be maintained in accordance with the criteria of 
    Sec. 50.75(e).'' Because the definition of decommissioning in 10 CFR 
    50.2 implicitly includes the costs of placing and maintaining a reactor 
    in safe storage, a licensee should continue to provide assurance of 
    adequate funds for these expenses at all times during the SAFSTOR 
    period. Thus, licensees are required to maintain this assurance both 
    before and after the NRC approves a licensee's Sec. 50.82 
    decommissioning plan.
        3. The withdrawals would not inhibit the ability of the licensee to 
    complete funding of any shortfalls in the decommissioning trust needed 
    to ensure availability of funds to ultimately release the site for 
    unrestricted use.
        This criterion encompasses the principle that activities allowed 
    before approval of the decommissioning plan do not significantly 
    increase decommissioning costs. A licensee would be required to 
    document the effect of the withdrawals on the decommissioning funding 
    plan, addressing the current fund balance and collection schedule, and 
    demonstrate that the use of funds before NRC approval of a 
    decommissioning plan for the facility would not impair the licensee's 
    ability to fully fund the plan submitted to the NRC (or, if no plan has 
    been filed, the actions necessary to permit release of the site for 
    unrestricted use). A licensee would, for example, have to show that the 
    decommissioning actions potentially taken out of sequence of any 
    decommissioning plan submitted (or reasonable decommissioning 
    alternatives if no plan has been submitted) would not significantly 
    increase decommissioning costs or impair its ability to obtain the 
    funds necessary to complete decommissioning.
        4. Before the NRC approves a decommissioning plan, licensees can be 
    allowed to undertake any decommissioning activity (as the term 
    ``decommission'' is defined in 10 CFR 50.2) that does not: (a) 
    Foreclose the release of the site for possible unrestricted use, (b) 
    significantly increase decommissioning costs, (c) cause any significant 
    environmental impact not previously reviewed, or (d) violate the terms 
    of the licensee's existing license (e.g., OL, POL, or OL with 
    confirmatory shutdown order) or 10 CFR 50.59 as applied to the existing 
    license.
        This criterion seeks to ensure that funds are only used for those 
    decommissioning activities that would be allowed to proceed before the 
    NRC approves a decommissioning plan. Items (a) and (b) have already 
    been addressed by this policy statement. For items (c) and (d), a 
    licensee and the NRC would evaluate the proposed activity to ensure 
    that the activity may proceed under the current license and that the 
    proposed activity will not result in any significant environmental 
    impact not previously reviewed.
        As stated above, the NRC may permit licensees to use their 
    decommissioning funds for the decommissioning activities permitted 
    above (as the term ``decommission'' is defined in 10 CFR 50.2), 
    notwithstanding the fact that their decommissioning plans have not yet 
    been approved by the NRC. After review of the licensee's proposed 
    activities and fund withdrawal using the above criteria, the NRC would 
    permit the licensee to use decommissioning funds and to undertake the 
    proposed activities by tacitly consenting to the proposed withdrawals 
    by not interposing, within a specified time, an objection to the 
    licensee's proposal. The NRC would need 60 days to complete an 
    effective review of a licensee's proposal and justification of how the 
    above criteria will be met.
    
    Ancillary Issue
    
        In the past, licensees have asked the NRC informally whether they 
    would be able to withdraw funds from their trusts to pay for developing 
    the Sec. 50.82 decommissioning plan and for other post-shutdown 
    administrative expenses. The NRC believes that these withdrawals should 
    be allowed before the NRC approves the final decommissioning plan, 
    provided the licensee meets the following guidelines:
    
    1. The sum of withdrawals for such purposes should be de minimis, that 
    is, less than $5 million.\3\
    ---------------------------------------------------------------------------
    
        \3\In talking informally with several licensees, the NRC 
    understands that most licensees expect to spend from $1 million to 
    $3 million for completing decommissioning plans and for immediate 
    post-shutdown administrative expenses. The amount of $5 million, 
    therefore, is based on a ``best-guess'' estimated, but is small 
    enough not to significantly deplete the decommissioning trust.
    ---------------------------------------------------------------------------
    
    2. The decommissioning trust balance would not fall below an amount 
    needed for safe storage.
    3. The licensee provided for these costs in its site-specific 
    decommissioning cost estimate and increased its overall trust fund 
    balances accordingly.
    
        Dated at Rockville, Maryland, this 12th day of January, 1994.
    
        For the Nuclear Regulatory Commission.
    James L. Blaha,
    Acting Executive Director for Operations.
    [FR Doc. 94-2391 Filed 2-2-94; 8:45 am]
    BILLING CODE 7590-01-M
    
    
    

Document Information

Published:
02/03/1994
Department:
Nuclear Regulatory Commission
Entry Type:
Uncategorized Document
Action:
Draft policy statement.
Document Number:
94-2391
Dates:
Comment period expires April 19, 1994. Comments received after this date will be considered if it is practical to do so, but the Commission is able to ensure consideration only for comments received on or before this date.
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: February 3, 1994