NUCLEAR REGULATORY COMMISSION
Maintenance Inspection Procedure Public Workshop
SUMMARY: The United States Nuclear Regulatory Commission (USNRC) will
hold a public workshop on March 31, 1994, to conduct initial
discussions regarding the draft maintenance inspection procedure
developed for use by NRC inspectors to verify the implementation of 10
CFR 50.65, ``Requirements for Monitoring the Effectiveness of
Maintenance at Nuclear Power Plants'' (the Maintenance Rule). The
effective date of the Maintenance Rule is July 10, 1996.
NRC draft Inspection Procedure ``Maintenance Inspection Procedure
XXXXX'' has been developed to ascertain compliance with the Maintenance
Rule and to verify that licensees using NUMARC 93-01 ``Industry
Guidance for Monitoring the Effectiveness of Maintenance at Nuclear
Power Plants'' have satisfactorily implemented the Maintenance Rule.
The commission believes that it would be beneficial to obtain
public comment on this procedure from all interested parties at a
public workshop. Participants are encouraged to ask questions and
provide written comments on the procedure during the workshop. Written
comments received from interested parties unable to attend the workshop
will also be considered through April 14, 1994.
At the workshop, NRC representatives will present an overview of
the inspection program, the contents of the maintenance inspection
procedure and, as applicable, issues related to the Maintenance Rule
and the NUMARC 93-01 industry guidance. NRC regional inspection
representatives will be available to participate in the discussions.
The workshop will provide the participants an opportunity to ask
questions, make comments during the discussion or submit written
comments for NRC consideration. The workshop will conclude with a
summary of the major issues identified at the meeting. The planned use
of the procedure during pilot inspections will also be discussed.
In order to ensure that adequate seating is available for the
meeting, persons planning to attend the workshop are requested to
either call the contact designated below or complete and forward the
attached registration form to the same contact by March 25, 1994. A
block of rooms has been reserved at the Holiday Inn Crown Plaza Hotel
(1-800-638-5963) for the convenience of meeting attendees. These rooms
will be available at a reduced group rate until March 9, 1994.
Attendees should identify themselves with the NRC Maintenance Workshop,
#4093, in order to ensure the group rate. The NRC however, does not
encourage nor support frequenting this or any other specific
establishment. The hotel will collect a ten dollar fee at room check in
or the morning of the workshop to cover expenses for morning and
afternoon refreshments.
The draft procedure ``Maintenance Inspection Procedure XXXXX'' is
publicly available at the NRC Public Document Room, 2120 L Street, NW.,
Washington, DC 20555 by referencing a memorandum from Gary G. Zech to
Elizabeth J. Yeates, dated January 25, 1994.
DATE AND LOCATION: The meeting will be held from 9 a.m.-5 p.m. on March
31, 1994 at: Holiday Inn Crown Plaza, 1750 Rockville Pike, Rockville,
Maryland 20852, (301) 468-1100.
WRITTEN COMMENTS, REGISTRATION FORMS OR FURTHER INFORMATION SHOULD BE
ADDRESSED TO: Thomas Foley, M/S 10-A-19, U.S. Nuclear Regulatory
Commission, Office of Nuclear Reactor Regulation, Washington, DC 20555,
Telephone (301) 504-1036.
SUPPLEMENTARY INFORMATION: On July 10, 1991, the NRC published the
``Requirements for Monitoring the Effectiveness of Maintenance at
Nuclear Power Plants'' as Sec. 50.65 of 10 CFR part 50, ``Domestic
Licensing of Production and Utilization Facilities.'' The Commission
determined that a Maintenance Rule was needed because proper
maintenance is essential to plant safety, especially as plants age. The
Maintenance Rule will become effective on July 10, 1996. The five year
period to implement the rule permits time to develop implementation
guidance, inspection procedures and sufficient time for licensees to
implement the rule requirements to ensure full conformance by July 10,
1996.
Shortly after the Maintenance Rule was published, the NRC and the
Nuclear Management and Resource Council (NUMARC) embarked on parallel
efforts to develop rule implementation guidance. The NRC staff
determined that the NUMARC document provided an acceptable method for
licensees to implement the requirements of the Maintenance Rule. In
June 1993, the Commission issued Regulatory Guide 1.160, ``Monitoring
the Effectiveness of Maintenance at Nuclear Power Plants,'' which
endorsed the NUMARC guidance, NUMARC 93-01, ``Industry Guideline for
Monitoring the Effectiveness of Maintenance at Nuclear Power Plants,''
dated May 1993. Subsequently, NUMARC conducted a verification and
validation (V & V) program, with NRC staff observation, to test their
guidance on several representative systems at nine nuclear units. The V
& V effort concluded that the guidelines were adequate to implement the
Maintenance Rule.
The NRC staff has developed an inspection procedure to be used by
NRC inspectors to verify the implementation of the Maintenance Rule
requirements. The NRC staff expects to validate the inspection
procedure during pilot inspections at selected nuclear power facilities
following the March 1994 workshop.
After considering the comments obtained from the workshop and
information obtained during the implementation of the pilot
inspections, the NRC staff expects to revise the inspection procedure
as necessary, and conduct another workshop to provide interested
parties an opportunity to participate in discussions on the results of
the pilot inspections and any revisions to the inspection procedure.
For the Nuclear Regulatory Commission.
Thomas Foley,
Senior Operations Engineer, Division of Reactor Inspection and Licensee
Performance, Office of Nuclear Reactor Regulation.
REGISTRATION FORM
UNITED STATES NUCLEAR REGULATORY COMMISSION MAINTENANCE RULE INSPECTION
PROCEDURE WORKSHOP
March 31, 1994.
(PLEASE PRINT)
NAME:------------------------------------------------------------------
(LAST) (FIRST) (MI)
COMPANY/ORGANIZATION:--------------------------------------------------
----------------------------------------------------------------------
----------------------------------------------------------------------
POSITION/TITLE:--------------------------------------------------------
----------------------------------------------------------------------
ADDRESS:---------------------------------------------------------------
----------------------------------------------------------------------
----------------------------------------------------------------------
TELEPHONE NUMBER:------------------------------------------------------
Send Registration form to: Thomas Foley M/S 10-A-19, U.S.
Nuclear Regulatory Commission, Washington, DC 20555.
[FR Doc. 94-2533 Filed 2-3-94; 8:45 am]