E5-449. Jewell Ridge Pipeline Company LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Jewell Ridge Pipeline Project and Request for Comments on Environmental Issues  

  • Start Preamble January 31, 2005.

    The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Jewell Ridge Pipeline Project involving construction and operation of facilities by the Jewell Ridge Pipeline Company, LLC (JRP) in (Tazwell, Smyth, and Russell counties, VA).[1] These facilities would consist of approximately 30 miles of 20 inch diameter pipeline and modification to the existing compressor station facility. This EA will be used by the Commission in its decision-making process to determine whether the project is in the public convenience and necessity.

    If you are a landowner receiving this notice, you may be contacted by a pipeline company representative about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The pipeline company would seek to negotiate a mutually acceptable agreement. However, if the project is approved by the Commission, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings in accordance with state law.

    A fact sheet prepared by the FERC entitled “An Interstate Natural Gas Facility On My Land? What Do I Need To Know?” was attached to the project notice JRP provided to landowners. This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission's proceedings. It is available for viewing on the FERC Internet Web site (http://www.ferc.gov).

    Summary of the Proposed Project

    JRP wants to expand the capacity of its facilities in Virginia to transport an Start Printed Page 5995additional 100,000 dekatherms per day of natural gas to the existing East Tennessee Gas Pipeline System. JRP seeks authority to construct and operate:

    Facilities (2005/2006)

    • Approximately 30 miles of 20-inch-diameter pipeline and associated facilities; and to
    • Modify the existing Jewell Ridge Compressor Station in Tazewell County, Virginia; The general location of the project facilities and alternative routes under consideration are shown in Appendix 1.[2]

    Land Requirements for Construction

    Construction of the proposed facilities would require about 363 acres of land. Following construction, about 120 acres would be maintained as permanent Right-Of-Way. The remaining 243 acres of land would be restored and allowed to revert to its former use.

    The EA Process

    The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us to discover and address concerns the public may have about proposals. This process is referred to as “scoping”. The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this Notice of Intent, the Commission staff requests public comments on the scope of the issues to address in the EA. All comments received are considered during the preparation of the EA. State and local government representatives are encouraged to notify their constituents of this proposed action and encourage them to comment on their areas of concern.

    In the EA we [3] will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings:

    • Geology and soils.
    • Land use.
    • Water resources, fisheries, and wetlands.
    • Cultural resources.
    • Vegetation and wildlife.
    • Air quality and noise.
    • Endangered and threatened species.
    • Public safety.

    We will also evaluate possible alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas.

    Our independent analysis of the issues will be in the EA. Depending on the comments received during the scoping process, the EA may be published and mailed to federal, state, and local agencies, public interest groups, interested individuals, affected landowners, newspapers, libraries, and the Commission's official service list for this proceeding. A comment period will be allotted for review if the EA is published. We will consider all comments on the EA before we make our recommendations to the Commission.

    To ensure your comments are considered, please carefully follow the instructions in the public participation section beginning on page 4.

    Currently Identified Environmental Issues

    We have already identified several issues that we think deserve attention based on a preliminary review of the proposed facilities and the environmental information provided by JRP. This preliminary list of issues may be changed based on your comments and our analysis.

    • Several federally/State listed endangered or threatened species may occur in the project area.
    • An un-quantified amount of prime farmland soils would be impacted during construction activity.
    • Three alternative routes are under consideration, although JRP has identified Alternative Route 3 as the likely preferred alternative (see Appendix 1).

    Public Participation

    You can make a difference by providing us with your specific comments or concerns about the project. By becoming a commentor, your concerns will be addressed in the EA and considered by the Commission. You should focus on the potential environmental effects of the proposal, alternatives to the proposal (including alternative routes), and measures to avoid or lessen environmental impact. The more specific your comments, the more useful they will be. Please carefully follow these instructions to ensure that your comments are received in time and properly recorded:

    • Send an original and two copies of your letter to: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First St., NE., Room 1A, Washington, DC 20426.
    • Label one copy of the comments for the attention of Gas Branch 3, DG2E.
    • Reference Docket No. PF05-3-000.
    • Mail your comments so that they will be received in Washington, DC on or before March 4, 2005.

    Please note that we are continuing to experience delays in mail deliveries from the U.S. Postal Service. As a result, we will include all comments that we receive within a reasonable time frame in our environmental analysis of this project. However, the Commission strongly encourages electronic filing of any comments or interventions or protests to this proceeding. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site at http://www.ferc.gov under the “e-Filing” link and the link to the User's Guide. Before you can file comments you will need to create a free account, which can be created by clicking on “Login to File” and then “New User Account.” You will be asked to select the type of filing you are making. This filing is considered a “Comment on Filing.”

    Public Scoping Meeting and Site Visit

    In addition to or in lieu of sending written comments, we invite you to attend the public scoping meeting we will conduct in the project area. The location and time for the meeting is listed below:

    February 22, 2005; 7 p.m. (e.s.t.),

    Chilhowie High School,

    1160 East Lee Highway,

    P.O. Box 2280,

    Chilhowie, Virginia 24319.

    Phone: (276) 646-8966.

    Fax: (276) 646-5951.

    Principal—Steve Reedy.

    February 23, 2005; 7 p.m. (e.s.t.),

    Southwest Virginia Community College,

    369 College Road, Route 19,

    Richlands, Virginia 24641.

    Contact: Pauline Taylor.

    (276) 964-7619.

    The public scoping meeting is designed to provide state and local agencies, interested groups, affected landowners, and the general public with more detailed information and another opportunity to offer your comments on the proposed project. Interested groups and individuals are encouraged to attend the meeting and to present comments on the environmental issues Start Printed Page 5996they believe should be addressed in the EA. A transcript of the meeting will be made so that your comments will be accurately recorded.

    If you do not want to send comments at this time but still want to remain on our mailing list, please return the Information Request (Appendix 4). If you do not return the Information Request, you will be taken off the mailing list.

    We may mail the EA for comment. If you are interested in receiving it, please return the Information Request (Appendix 4). If you do not return the Information Request, you will be taken off the mailing list.

    Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want to become an official party to the proceeding known as an “intervenor”. Intervenors play a more formal role in the process. Among other things, intervenors have the right to receive copies of case-related Commission documents and filings by other intervenors. Likewise, each intervenor must send one electronic copy (using the Commission's eFiling system) or 14 paper copies of its filings to the Secretary of the Commission and must send a copy of its filings to all other parties on the Commission's service list for this proceeding. If you want to become an intervenor you must file a motion to intervene according to Rule 214 of the Commission's Rules of Practice and Procedure (18 CFR 385.214) (see Appendix 2).[4] Only intervenors have the right to seek rehearing of the Commission's decision.

    Affected landowners and parties with environmental concerns may be granted intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which would not be adequately represented by any other parties. You do not need intervenor status to have your environmental comments considered.

    Environmental Mailing List

    An effort is being made to send this notice to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. This includes all landowners who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within distances defined in the Commission's regulations of certain aboveground facilities. By this notice we are also asking governmental agencies, especially those in Appendix 3, to express their interest in becoming cooperating agencies for the preparation of the EA.

    Additional Information

    Additional information about the project is available from the Commission's Office of External Affairs, at 1-866-208-FERC or on the FERC Internet Web site (http://www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on “General Search” and enter the docket number excluding the last three digits in the Docket Number field. Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings.

    In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries and direct links to the documents. Go to http://www.ferc.gov/​esubscribenow.htm.

    FERC conferences are accessible under section 508 of the Rehabilitation Act of 1973. For accessibility accommodations please send an e-mail to accessibility@ferc.gov or call toll free (866) 208-3372 (voice) or (202) 208-1659 (TTY), or send a FAX to (202) 208-2106 with the required accommodations.

    Finally, public meetings or site visits will be posted on the Commission's calendar located at http://www.ferc.gov/​EventCalendar/​EventsList.aspx along with other related information.

    Start Signature

    Magalie R. Salas,

    Secretary.

    End Signature End Preamble

    Footnotes

    1.  JRP is beginning NEPA pre-filing of an application with the Commission under section 7 of the Natural Gas Act and Part 157 of the Commission's regulations.

    Back to Citation

    2.  The appendices referenced in this notice are not being printed in the Federal Register. Copies of all appendices, other than Appendix 1 (maps), are available on the Commission's Web site at the “eLibrary” link, and all appendices, including Appendix 1are available from the Commission's Public Reference Room, 888 First Street, NE., Washington, DC 20426, or call (202) 502-8371. For instructions on connecting to eLibrary refer to the last page of this notice. Copies of the appendices were sent to all those receiving this notice in the mail.

    Back to Citation

    3.  ”We”, “us”, and “our” refer to the environmental staff of the Office of Energy Projects (OEP).

    Back to Citation

    4.  Interventions may also be filed electronically via the Internet in lieu of paper. See the previous discussion on filing comments electronically.

    Back to Citation

    [FR Doc. E5-449 Filed 2-3-05; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
02/04/2005
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
E5-449
Pages:
5994-5996 (3 pages)
Docket Numbers:
Docket No. PF05-3-000
EOCitation:
of 2005-01-31
PDF File:
e5-449.pdf