DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
Environmental Impact Statement: Kern County, CA
AGENCY: Federal Highway Administration (FHWA), DOT.
ACTION: Notice of Intent.
-----------------------------------------------------------------------
SUMMARY: FHWA is issuing this notice to advise the public that a Tier 1
Environmental Impact Statement will be prepared for a proposed
transportation project in Kern County, California. The Tier 1 EIS is
intended to satisfy requirements for environmental evaluation of route
location and right-of-way acquisition for corridor protection. Prior to
facility construction, Tier 2 project-specific environmental
document(s) will be prepared.
FOR FURTHER INFORMATION CONTACT:
Leonard E. Brown, Chief, District Operations--C, California Division
(HC-CA), 980 9th Street, suite 400, Sacramento, California 95814-2724,
916/551-1307.
SUPPLEMENTARY INFORMATION: The FHWA, in cooperation with the California
Department of Transportation (Caltrans), will prepare a Tier 1
Environmental Impact Statement (EIS) to identify a route and protect a
corridor for Route 58 between Interstate 5 and State Route 99, a
distance of 32.2 kilometers (20 miles), in Kern County and the City of
Bakersfield. Existing Route 58 within the project limits is a two-lane
conventional highway from I-5 to Allen Road, a four-lane conventional
highway from Allen Road to SR 99, and a four-lane freeway east of SR
99. Existing development along the present roadway alignment constrains
opportunities to upgrade to freeway standards and to accommodate
additional travel modes. The existing facility operates at Level of
Service (LOS) C to E, and is expected to decline to LOS D to F by year
2010. Additional capacity is needed to meet future travel demand in the
transportation corridor.
Alternatives under consideration are: (1) The ``No-Project''
alternative; (2) a Transportation Systems Management alternative
providing low cost, incremental improvements; (3) a Mass Transit
Alternative providing commuter/light rail and or bus transit; (4) the
Seventh Standard alternative, a 32.2 kilometer (20 mile) corridor
parallel to Seventh Standard Road; (5) the Rosedale Highway
alternative, a 29 kilometer (18 mile) corridor primarily parallel to
and approximately 0.4 kilometer (one-fourth mile) from Rosedale
Highway; and (6) the Kern River alternative, a 24.1 kilometer (15 mile)
corridor north of the Kern River and Stockdale Highway. The roadway
alternative used for route planning purposes and right-of-way corridor
definition consists of an eight-lane freeway with an 18.3 meter (60-
foot) median and 3.1 meter (10-foot) shoulder. This corridor width
would also accommodate a six-lane freeway with capacity for a transit
or High Occupancy Vehicle (HOV) facility. Access control and
interchanges with existing highways and local streets are included in
determining the corridor examined.
Letters describing the proposed action and soliciting comments were
sent to the appropriate Federal, State and local agencies, and to
private organizations and citizens who have expressed or are known to
have interest in this proposal. Public scoping and community
participation meetings were held November 17, 1992 and August 12, 1993
at Fruitvale Junior High School, 2114 Calloway Drive, Bakersfield. An
agency scoping meeting is scheduled at the Kern County Public Services
Building, 2700 ``M'' Street in Bakersfield at 1 p.m. February 24, 1994.
The Public Participation Program for this study includes additional
community information meetings and a Public Hearing.
To ensure that the full range of issues related to this proposed
action is addressed and all significant issues identified, comments and
suggestions are invited from all interested parties. If you have any
information regarding cultural resources, endangered species or other
sensitive issues which could be affected by this project, please notify
this office. Also, please indicate if you would like to be notified at
the completion of the above technical studies.
Comments or questions concerning this proposed action and the
Environmental Impact Statement (EIS) should be directed to the FHWA at
the address provided above.
(Catalog of Federal Domestic Assistance Program Number 20.205,
Highway Research, Planning and Construction. The regulations
implementing Executive Order 12372 regarding intergovernmental
consultation on Federal programs and activities apply to this
program.)
Issued on: January 26, 1994.
Leonard E. Brown,
Chief, District Operations--C; Sacramento, California.