96-2552. Tennessee Gas Pipeline Company; Notice of Proposed Changes in FERC Gas Tariff  

  • [Federal Register Volume 61, Number 26 (Wednesday, February 7, 1996)]
    [Notices]
    [Pages 4648-4649]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-2552]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. RP96-73-002]
    
    
    Tennessee Gas Pipeline Company; Notice of Proposed Changes in 
    FERC Gas Tariff
    
    February 1, 1996.
        Take notice that on January 30, 1996, Tennessee Gas Pipeline 
    Company (Tennessee) submitted for filing to become part of its FERC Gas 
    Tariff, Fifth Revised Volume No. 1, the following revised tariff 
    sheets, to be effective on the dates stated thereon:
    
    Substitute Fourth Revised Sheet No. 20
    Substitute Fifth Revised Sheet No. 20
    Substitute Fourth Revised Sheet No. 23
    Substitute Fifth Revised Sheet No. 23
    Substitute First Revised Sheet No. 23A
    First Revised Original Sheet No. 23B
    First Revised Second Substitute Original Sheet No. 30
    Substitute First Revised Sheet No. 30
    Second Substitute Second Revised Sheet No. 30
    Second Substitute Third Revised Sheet No. 30
    Second Substitute Fifth Revised Sheet No. 30
    Substitute Sixth Revised Sheet No. 30
    Substitute Seventh Revised Sheet No. 30
    Substitute Eighth Revised Sheet No. 30
    
    [[Page 4649]]
    
    Substitute First Revised Substitute Ninth Revised Sheet No. 30
    
        Tennessee states that the purpose of this filing is to comply with 
    the Commission's order issued on December 29, 1995 in Docket Nos. RP96-
    73-000, et al., Tennessee Gas Pipeline Co., 73 FERC para. 61,398.
        Tennessee states that the revised tariff sheets produce a TCRA 
    monthly demand surcharge of $0.27 per dth for Rate Schedules FT-A and 
    FT-G and a volumetric surcharge of $0.0148 for Rate Schedule FT-GS. 
    Tennessee states that the revised tariff sheets comply with the 
    foregoing December 29, 1995 order. Tennessee states that the instant 
    filing complies with the Commission's requirement in the December 29, 
    1995 order that it refile its TCRA tariff sheets to reconcile the 
    balances in the Unrecovered Transportation Costs Account pursuant to 
    Article XXIV of its tariff, along with certain other conditions.
        Any person desiring to protest this filing should file a protest 
    with the Federal Energy Regulatory Commission, 888 First Street, N.E., 
    Washington, D.C. 20426, in accordance with Section 211 of the 
    Commission's Rules of Practice and Procedure, 18 CFR 385.211. All such 
    protests must be filed as provided in Section 154.210 of the 
    Commission's Regulations. Protests will be considered by the Commission 
    in determining the appropriate action to be taken, but will not serve 
    to make protestants parties to the proceeding. Any person wishing to 
    become a party must file a motion to intervene. Copies of this filing 
    are on file with the Commission and are available for public inspection 
    in the Public Reference Room.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-2552 Filed 2-6-96; 8:45 am]
    BILLING CODE 6717-01-M
    
    

Document Information

Published:
02/07/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-2552
Pages:
4648-4649 (2 pages)
Docket Numbers:
Docket No. RP96-73-002
PDF File:
96-2552.pdf