Start Preamble
February 1, 2007.
Take notice that Southern Natural Gas Company (Southern), Post Office Box 2563, Birmingham, Alabama 35202-2563, filed in Docket No. CP07-70-000 on January 26, 2005, an application pursuant to section 7(b) of the Natural Gas Act (NGA), to abandon, by removal, six compressor engines at its Toca Compressor Station in St. Bernard Parish, Louisiana (Toca Engines), all as more fully set forth in the application which is on file with the Commission and open to public inspection. This filing may be also viewed on the Web at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call (202) 502-8222 or TTY, (202) 208-1659.
To comply with the United States Environmental Protection Agency and its national emission standards for hazardous pollutants for stationary reciprocating internal combustion engines under the provisions of Code 40 of the Federal Regulation Part 63 Subpart ZZZZ on June 15, 2004, Southern proposes to abandon six essentially standby Toca Engines. In addition, Southern submits that, by abandoning these engines, it would avoid approximately $368,000 per year in maintenance expenses and would also avoid approximately $3,000,000 to bring the engines up to code. Furthermore, Southern states that it is capable of meeting the existing gas supplies in the area without the Toca Engines.
Pursuant to Section 157.9 of the Commission's rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all Federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.
Any questions regarding this application should be directed to Patrick B. Pope, Vice President and General Counsel, Southern Natural Gas Company, Post Office Box 2563, Birmingham, Alabama 35202-2563 at (205) 325-77126 (telephone), or Patricia S. Francis, Senior Counsel, Southern Natural Gas Company, Post Office Box 2563, Birmingham, Alabama 35202-2563 at (205) 325-7696.
There are two ways to become involved in the Commission's review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.
However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest.
Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission's environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission's environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenters will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission's final order.
Comments, protests and interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site under the “e-Filing” link.
Comment Date: February 22, 2007.
Start SignatureMagalie R. Salas,
Secretary.
[FR Doc. E7-2027 Filed 2-6-07; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Effective Date:
- 2/22/2007
- Published:
- 02/07/2007
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- E7-2027
- Dates:
- February 22, 2007.
- Pages:
- 5689-5689 (1 pages)
- Docket Numbers:
- Docket No. CP07-70-000
- EOCitation:
- of 2007-02-01
- PDF File:
- e7-2027.pdf