94-2902. Texas Eastern Transmission Corp.; Amendment and Motion to Vacate  

  • [Federal Register Volume 59, Number 27 (Wednesday, February 9, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-2902]
    
    
    [[Page Unknown]]
    
    [Federal Register: February 9, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP92-184-007]
    
     
    
    Texas Eastern Transmission Corp.; Amendment and Motion to Vacate
    
    February 3, 1994.
        Take notice that on January 27, 1994, Texas Eastern Transmission 
    Corporation (Texas Eastern), P.O. Box 1642, Houston, Texas 77056-1642, 
    filed in Docket No. CP92-184-007 pursuant to Section 7(c) to amend and 
    to partially vacate the Commission's order issued July 16, 1993, in 
    Docket Nos. CP92-184-000 et al. in order to modify the construction 
    program associated with the Integrated Transportation Project (ITP) and 
    to make corresponding adjustments to the approved initial ITP rates, 
    all as more fully set forth in the application, which is on file and 
    open to public inspection.
        It is indicated that on July 16, 1993, the Commission issued an 
    order approving construction and operation of incremental facilities on 
    Texas Eastern's mainline system which would permit Texas Eastern to 
    render part 284 transportation service for specific shippers. Texas 
    Eastern explains that the facilities and associated services were 
    designated as the Integrated Transportation Project (ITP). The order 
    authorized discrete construction programs for 1993 and 1994, consistent 
    with Texas Eastern's plan to implement the underlying transportation 
    service in two stages: 111,000 Dekatherms per day (Dthd) to commence 
    November 1, 1993, and the remaining 90,000 Dthd to commence November 1, 
    1994, for an aggregate ITP service level of 201,000 Dthd. Reflecting 
    the staged construction approved for ITP facilities, the order also 
    authorized an incremental rate with a built-in step-up, i.e., an 
    initial rate effective November 1, 1993, based on 1993 ITP 
    construction, with a step-up effective November 1, 1994, incorporating 
    1994 ITP construction costs.
        Texas Eastern states that because of the narrow window available 
    for 1993 construction and changes in ITP customer requirements, it has 
    been compelled to reschedule implementation of ITP service. As shown 
    below, the adjustments include deferral to 1994 and 1995 of portions of 
    the service originally scheduled to be initiated in 1993 and deferral 
    until 1995 of some service originally scheduled for implementation in 
    1994. While there is some reallocation of ITP service among customers, 
    there is no planned change in the ultimate total level of ITP service.
    
    I. Timing of ITP Service Levels Underlying July 16, 1993 Order
    
    ------------------------------------------------------------------------
                                                                  Total ITP 
                             11/01/93                              service  
         ITP shipper           Dthd      11/01/94 Dthd volumes       Dthd   
                             volumes                               volumes  
    ------------------------------------------------------------------------
    UGI..................       40,000                        0       40,000
    PSE&G................       25,000                   75,000      100,000
    Delmarva.............       40,000                        0       40,000
    PGW..................        6,000                        0        6,000
    Yankee...............            0                   15,000       15,000
                          --------------------------------------------------
        Total............      111,000                   90,164      201,000
                                                                            
    ------------------------------------------------------------------------
    
    II. Revised Allocations and Timing for ITP Implementation
    
    ------------------------------------------------------------------------
                            11/01/93     11/01/94     11/01/95    Cumulative
         ITP shipper          Dthd         Dthd         Dthd         Dthd   
                            volumes      volumes      volumes      volumes  
    ------------------------------------------------------------------------
    UGI.................       20,000       10,000       10,000       40,000
    PSE&G...............       13,000       47,000       50,000      110,000
    Delmarva............            0       20,000       10,000       30,000
    PGW.................            0        6,000            0        6,000
    Yankee..............            0       15,164            0       15,164
                         ---------------------------------------------------
        Total...........       33,000       98,164       70,000      201,164
                                                                            
    ------------------------------------------------------------------------
    
        Texas Eastern asserts that the ITP service modifications set forth 
    above necessitate changes in the timing, configuration and extent of 
    facility construction required to support ITP service as well as 
    corresponding adjustments in the initial rates for ITP service. Based 
    on a reevaluation of its ITP facility design analysis, Texas Eastern 
    has determined that it no longer requires approximately 8.92 miles of 
    authorized pipeline along with certain approved compressor 
    modifications. In addition, Texas Eastern states that it will require a 
    total of 11.02 miles of new pipeline which is not already authorized 
    while deferring some of the remaining authorized facilities.,
        In order to conform its facility and rate authorizations to the 
    revised ITP service levels and implementation schedule, Texas Eastern 
    requests the following specific authorizations:
        (1) To defer construction of a portion of the authorized ITP 
    facilities until 1995;
        (2) To vacate certificate authorization as it relates to 8.92 miles 
    of authorized pipeline;
        (3) To construct, install, own, and operate an additional 11.02 
    miles of 36'' pipeline for 1995 ITP service; and
        (4) To charge revised section 7(c) initial rates for 1994 ITP 
    service and new initial rates for 1995 ITP service.
        Texas Eastern states that it has certificate authority under the 
    July 16, 1993, order to construct the authorized facilities necessary 
    to provide 1994 ITP services. Texas Eastern requests authorization of 
    the proposed additional facilities required for 1995 ITP service by 
    September 1, 1994. Texas Eastern states that it will not install any of 
    the proposed additional facilities or the authorized facilities no 
    longer required until the requested authorizations are granted. Texas 
    Eastern estimates that the capital cost of the proposed additional 
    facilities in $13,966,000 and that the revised cost of all 1994 and 
    1995 ITP facilities in $100,724,000 and $91,987,000, respectively. 
    Texas Eastern proposes the following revised initial rate for 1994 and 
    new initial rate for 1995 ITP services.
    
    ------------------------------------------------------------------------
                     Rate Per Dth                      1994          1995   
    ------------------------------------------------------------------------
    Demand Rate...................................      $19.974      $21.078
    ------------------------------------------------------------------------
    
        Texas Eastern states that the subject amended application 
    supersedes other pending ITP applications. Specifically, Texas Eastern 
    states that it will withdraw its applications in Docket Nos. CP92-184-
    004 and CP94-5-000.
        Any person desiring to be heard or to make any protest with 
    reference to said amendment and motion to vacate should on or before 
    February 24, 1994, file with the Federal Energy Regulatory Commission, 
    Washington, DC 20426, a motion to intervene or a protest in accordance 
    with the requirements of the Commission's Rules of Practice and 
    Procedure (18 CFR 385.214 or 385.211) and the Regulations under the 
    Natural Gas Act (18 CFR 157.10). All protests filed with the Commission 
    will be considered by it in determining the appropriate action to be 
    taken but will not serve to make the protestants parties to the 
    proceeding. Any person wishing to become a party to a proceeding or to 
    participate as a party in any hearing therein must file a motion to 
    intervene in accordance with the Commission's Rules. Any person who has 
    heretofore filed need not file again.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 94-2902 Filed 2-8-94; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
02/09/1994
Department:
Energy Department
Entry Type:
Uncategorized Document
Document Number:
94-2902
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: February 9, 1994, Docket No. CP92-184-007