96-2838. Canspec Materials Testing, Inc., Middlesex, NJ; Order Imposing Civil Monetary Penalty  

  • [Federal Register Volume 61, Number 28 (Friday, February 9, 1996)]
    [Notices]
    [Pages 5038-5040]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-2838]
    
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 030-32380, License No. 29-28659-01 EA 95-163]
    
    
    Canspec Materials Testing, Inc., Middlesex, NJ; Order Imposing 
    Civil Monetary Penalty
    
    I
    
        Canspec Materials Testing, Inc. (Licensee) is the holder of 
    byproduct Materials License No. 29-28659-01 issued by the Nuclear 
    Regulatory Commission (NRC or Commission) on August 12, 1991. The 
    license authorizes the Licensee to possess and use byproduct material 
    for industrial radiography and replacement of sources in accordance 
    with the conditions specified therein.
    
    II
    
        An inspection of the Licensee's activities was conducted on July 19 
    and 25, 1995. The results of this inspection indicated that the 
    Licensee had not conducted its activities in full compliance with NRC 
    requirements. A written Notice of Violation and Proposed Imposition of 
    Civil Penalty (Notice) was served upon the Licensee by letter dated 
    September 13, 1995. The Notice states the nature of the violations, the 
    provisions of the NRC's requirements that the Licensee had violated, 
    and the amount of the civil penalty proposed for the violations.
        The Licensee responded to the Notice in two letters, both dated 
    October 11, 1995. In its responses, the Licensee admitted Violations A 
    through D and F through H; denied Violation E; and requested that the 
    proposed civil penalty be reduced if not dismissed.
    
    III
    
        After consideration of the Licensee's response and the statements 
    of fact, explanation, and argument for mitigation contained therein, 
    the NRC staff has determined, as set forth in the Appendix to this 
    Order, that the violations occurred as stated and that the penalty 
    proposed for the violations designated in the Notice should be imposed.
    
    [[Page 5039]]
    
    
    IV
    
        In view of the foregoing and pursuant to Section 234 of the Atomic 
    Energy Act of 1954, as amended (Act), 42 U.S.C. 2282, and 10 CFR 2.205, 
    it is hereby ordered That:
        The Licensee pay a civil penalty in the amount of $5,000 within 30 
    days of the date of this Order, by check, draft, money order, or 
    electronic transfer, payable to the Treasurer of the United States and 
    mailed to Mr. James Lieberman, Director, Office of Enforcement, U.S. 
    Nuclear Regulatory Commission, One White Flint North, 11555 Rockville 
    Pike, Rockville, MD 20852-2738.
    
    V
    
        The Licensee may request a hearing within 30 days of the date of 
    this Order. Where good cause is shown, consideration will be given to 
    extending the time to request a hearing. A request for extension of 
    time must be made in writing to the Director, Office of Enforcement, 
    U.S. Nuclear Regulatory Commission Washington, D.C. 20555, and include 
    a statement of good cause for the extension. A request for a hearing 
    should be clearly marked as a ``Request for an Enforcement Hearing'' 
    and shall be addressed to the Director, Office of Enforcement, U.S. 
    Nuclear Regulatory Commission, Washington, D.C. 20555, with a copy to 
    the Commission's Document Control Desk, Washington, D.C. 20555. Copies 
    also shall be sent to the Assistant General Counsel for Hearings and 
    Enforcement at the same address and to the Regional Administrator, NRC 
    Region I, 475 Allendale Road, King of Prussia, Pennsylvania 19406-1415.
        If a hearing is requested, the Commission will issue an Order 
    designating the time and place of the hearing. If the Licensee fails to 
    request a hearing within 30 days of the date of this Order (or if 
    written approval of an extension of time in which to request a hearing 
    has not been granted), the provisions of this Order shall be effective 
    without further proceedings. If payment has not been made by that time, 
    the matter may be referred to the Attorney General for collection.
        In the event the Licensee requests a hearing as provided above, the 
    issues to be considered at such hearing shall be:
        (a) whether the Licensee was in violation of the Commission's 
    requirements as set forth in Violation E of the Notice referenced in 
    Section II above; and
        (b) whether, on the basis of such violation, and the additional 
    violations set forth in the Notice that the Licensee admitted, this 
    Order should be sustained.
    
        For The Nuclear Regulatory Commission.
    James Lieberman,
    Director, Office of Enforcement.
        Dated at Rockville, Maryland, this 2nd day of February 1996.
    
    Appendix--Evaluations and Conclusion
    
        On September 13, 1995, a Notice of Violation and Proposed 
    Imposition of Civil Penalty (Notice) was issued for violations 
    identified during an NRC inspection. Canspec Materials Testing, Inc. 
    (Licensee or CTI) responded to the Notice on October 11, 1995. The 
    Licensee admitted seven violations (Violations A-D and F-H), denied 
    one violation (Violation E) and requested mitigation or dismissal of 
    the civil penalty. The NRC's evaluation and conclusion regarding the 
    licensee's requests are as follows:
    
    1. Restatement of Violation E
    
        10 CFR 34.24 requires, in part, that each survey instrument used 
    to conduct physical radiation surveys be calibrated at intervals not 
    to exceed three months and after each instrument servicing.
        Contrary to the above,
        1. on June 8, 1995, a licensee employee conducted physical 
    radiation surveys with a survey instrument (Serial Number 3369) 
    which was last calibrated on February 17, 1995, an interval 
    exceeding three months.
        2. on July 11, 1995, a licensee employee conducted physical 
    radiation surveys with a survey instrument (Serial Number 2015) 
    which was last calibrated on March 28, 1995, an interval exceeding 
    three months.
        3. on August 15, 1994, a licensee radiographer conducted 
    physical radiation surveys with a survey instrument (Serial Number 
    3369) which was last calibrated on April 4, 1994, an interval 
    exceeding three months.
        This is a repetitive violation.
    
    2. Summary of the Licensees Response to Violation E
    
        The Licensee denied this violation, and stated that there was 
    always a calibrated meter in use for surveys. The Licensee's 
    president stated that he must have misunderstood a conversation he 
    had with an NRC inspector regarding the use of survey instruments. 
    The Licensee's president also stated that he was under the 
    impression that as long as the survey meter used for compliance 
    surveys was calibrated, a second meter could be used for information 
    only.
        Further, the Licensee's president stated that when an audit was 
    performed in the field and the equipment was found to be out of 
    calibration they only had to go to ``our trailer'' to obtain 
    properly calibrated equipment. In addition, the Licensee stated that 
    an NRC inspector allowed them to return to work because there was 
    properly calibrated functional equipment on site for use. The 
    Licensee also stated that the company had the appropriate equipment 
    in place for use. However, the workers did not take the time to 
    check calibration dates before starting to work.
    
    3. NRC Evaluation of the Licensees Response to Violation E
    
        10 CFR 34.24 requires, in part, that each survey instrument used 
    to conduct physical radiation surveys be calibrated at intervals not 
    to exceed three months and after each instrument servicing. The 
    inspection findings were based on a review of documentation of 
    survey instrument use and calibration, maintained by the Licensee, 
    which indicated instances where the survey instrument used to show 
    compliance had not been calibrated at the required frequency. While 
    the Licensee may have had in its possession survey instruments which 
    were calibrated as required, the Licensee did not comply with the 
    requirement as stated in 10 CFR 34.24. Specifically, survey meters 
    used by the Licensee to perform physical radiation surveys to ensure 
    compliance with 10 CFR 34.24 on the dates specified in the Notice 
    had not been calibrated within the previous three months as 
    required.
        Having appropriately calibrated instruments on site or available 
    for use does not demonstrate compliance with this requirement. It is 
    the licensee's responsibility to assure that the instrument used is 
    calibrated as required. Therefore, the NRC concludes that the 
    Licensee has not provided an adequate basis for withdrawal of the 
    violation.
        On November 14, 1995, Mr. Frank Costello, Chief, Nuclear 
    Materials Safety Branch 3, NRC, contacted the Licensee's president 
    by telephone for clarification of the Licensee's statement, in its 
    October 11, 1995 response, concerning an NRC inspector allowing the 
    Licensee to return to work because properly calibrated functional 
    equipment was on site. During the telephone conversation, the 
    Licensee's president stated that the NRC inspector allowed the 
    radiographers to return to work only after assuring that they were 
    using calibrated equipment.
    
    4. Summary of Licensee's Request for Mitigation
    
        In its responses, the Licensee requested that the proposed civil 
    penalty be reviewed for reduction if not dismissal. In June of 1995, 
    Canspec was purchased by the current president. The president stated 
    his contention that prior to this purchase, time was not spent where 
    it should have been and now that he has assumed the position of 
    president he will spend the time required to ensure that policy is 
    followed ``to the letter.'' The president stated that now he has 
    greater control over the operation and will be able to spend the 
    time necessary sorting out any problems with individuals and if they 
    fail to conform, they will be replaced. The Licensee also stated its 
    belief that the violations were not entirely the company's 
    responsibility. Further, the president stated that the company had 
    fulfilled the calibration requirements, yet the men made a mistake 
    by not checking the calibration dates before starting to work.
    
    5. NRC Evaluation of Licensee's Request for Mitigation
    
        The NRC determined that the violations, given their number, 
    nature, and the fact that three were repetitive, were of significant 
    
    
    [[Page 5040]]
    regulatory concern and appeared to be indicative of the lack of 
    management control over licensed activities. The lack of management 
    control was evidenced by the fact that 13 violations were identified 
    during the two NRC inspections in 1994. Therefore, the violations 
    were appropriately characterized at Severity Level III in accordance 
    with the ``General Statement of Policy and Procedure for NRC 
    Enforcement Actions'' (Enforcement Policy), NUREG-1600 (60 FR 34381; 
    June 30, 1995).
        As to the president's statements concerning his increased 
    control over the Licensee's operation, the NRC considers that such 
    actions are part of the Licensee's corrective action and expects 
    licensees to exercise adequate management control over licensed 
    activities consistently to ensure the protection of the public and 
    the environment. Regardless of who committed the violations, the 
    Licensee is responsible for the acts of its employees and for 
    assuring that it is in compliance with all applicable regulations.
        Therefore, the NRC concludes that the Licensee has not provided 
    an adequate basis for mitigation or withdrawal of the civil penalty.
    
    6. NRC Conclusion
    
        The NRC has concluded that the violation occurred as stated and 
    that an adequate basis for mitigation of the civil penalty was not 
    provided by the Licensee. Consequently, the proposed civil penalty 
    in the amount of $5,000 should be imposed.
    [FR Doc. 96-2838 Filed 2-8-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
02/09/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
96-2838
Pages:
5038-5040 (3 pages)
Docket Numbers:
Docket No. 030-32380, License No. 29-28659-01 EA 95-163
PDF File:
96-2838.pdf