99-3114. Pacific Northwest-Pacific Southwest Intertie ProjectPoint-To- Point Transmission Service Rates for the 230/345-kV Transmission SystemRate Order No. WAPA-76  

  • [Federal Register Volume 64, Number 26 (Tuesday, February 9, 1999)]
    [Notices]
    [Pages 6344-6351]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-3114]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Western Area Power Administration
    [Rate Order No. WAPA-76]
    
    
    Pacific Northwest-Pacific Southwest Intertie Project--Point-To-
    Point Transmission Service Rates for the 230/345-kV Transmission 
    System--Rate Order No. WAPA-76
    
    AGENCY: Western Area Power Administration, DOE.
    
    ACTION: Notice of rate order.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Notice is given of the confirmation and approval by the Acting 
    Deputy Secretary of the Department of Energy (DOE) of Rate Order No. 
    WAPA-76 and Rate Schedule INT-FT3 placing provisional rates for the 
    230/345-kV Pacific Northwest-Pacific Southwest Intertie Project (AC 
    Intertie) firm point-to-point transmission service into effect on an 
    interim basis. The provisional rates will remain in effect on an 
    interim basis until the Federal Energy Regulatory Commission (FERC) 
    confirms, approves, and places them into effect on a final basis or 
    until they are replaced by other rates. The provisional rates will 
    provide sufficient revenue to pay all annual costs, including interest 
    expense, and repayment of required investment within the allowable 
    period.
    
    DATES: The provisional rates will be placed into effect on an interim 
    basis on January 1, 1999, and will be in effect until FERC confirms, 
    approves, and places the provisional rates in effect on a final basis 
    for a 5-year period ending December 31, 2003, or until superseded.
    
    FOR FURTHER INFORMATION CONTACT: Mr. Maher A. Nasir, Rates Team Lead, 
    Desert Southwest Customer Service Region, Western Area Power 
    Administration, P.O. Box 6457, Phoenix, AZ 85005-6457, telephone (602) 
    352-2768.
    
    SUPPLEMENTARY INFORMATION: The Deputy Secretary of Energy approved the 
    existing Rate Schedule INT-FT2 for AC Intertie firm transmission 
    service on January 31, 1996 (Rate Order No. WAPA-71, 61 FR 4650, 
    February 7, 1996); and FERC confirmed and approved the rate schedule on 
    July 24, 1996, under FERC Docket No. EF96-5191-000 (76 FERC para. 
    62,061). The existing Rate Schedule INT-FT2 became effective on 
    February 1, 1996, for the period ending September 30, 2002. Rate 
    Schedule INT-FT2 provides separate rates for firm transmission service 
    on the AC Intertie 230/345-kV transmission system and AC Intertie 500-
    kV transmission system. This Rate Order (WAPA-76) seeks to put into 
    place Rate Schedule INT-FT3 that will supersede Rate Schedule INT-FT2 
    as it relates to 230/345-kV firm transmission service only. Under Rate 
    Schedule INT-FT3, the firm point-to-point transmission service rate on 
    the AC Intertie 230/345-kV transmission system on January 1, 1999, is 
    $12.00/kW/year or $1.00/kW/month and includes the cost for the 
    ancillary service of scheduling, system control and dispatch service. 
    The remaining ancillary services, which comply with FERC Order Nos. 888 
    and 888-A, will be provided through Western Area Power Administration's 
    (Western) Open Access Transmission Service Tariff, published on January 
    6, 1998 (63 FR 521). The provisional rate of $12.00/kW/year represents 
    an increase of approximately 82 percent over the existing rate for firm 
    transmission service on the AC Intertie 230/345-kV transmission system.
        By Amendment No. 3 to Delegation Order No. 0204-108, published 
    November 10, 1993 (58 FR 59716), the Secretary of Energy delegated: (1) 
    The authority to develop long-term power and transmission rates on a 
    nonexclusive basis to the Administrator of Western; (2) the authority 
    to confirm, approve, and place such rates into effect on an interim 
    basis to the Deputy Secretary of Energy; and (3) the authority to 
    confirm, approve, and place into effect on a final basis, to remand, or 
    disapprove such rates to FERC.
        Rate Order No. WAPA-76 was prepared pursuant to Delegation Order 
    No. 0204-108, existing DOE procedures for public participation in power 
    rate adjustments in 10 CFR Part 903, and procedures for approving Power 
    Marketing Administration rates by the FERC in 18 CFR Part 300. Rate 
    Order No. WAPA-76, confirming, approving, and placing the proposed AC 
    Intertie 230/345-kV transmission system firm point-to-point 
    transmission service rate into effect on an interim basis, is issued, 
    and the new Rate Schedule INT-FT3 will be submitted promptly to FERC 
    for confirmation and approval on a final basis.
    
    
    [[Page 6345]]
    
    
        Dated: January 28, 1999.
    Ernest J. Moniz,
    Acting Deputy Secretary.
    
    Order Confirming, Approving, and Placing the Pacific Northwest-
    Pacific Southwest Intertie Firm Transmission Service Rates Into 
    Effect on an Interim Basis
    
    January 1, 1999.
        These rates are developed pursuant to the Department of Energy 
    Organization Act (42 U.S.C. 7101 et seq.), through which the power 
    marketing functions of the Secretary of the Interior and the Bureau of 
    Reclamation under the Reclamation Act of 1902 (43 U.S.C. 371 et seq.), 
    as amended and supplemented by subsequent enactments, particularly 
    section 9c of the Reclamation Project Act of 1939 (43 U.S.C. 485h(c)), 
    and other acts specifically applicable to the project involved, were 
    transferred to and vested in the Secretary of Energy (Secretary).
        By Amendment No. 3 to Delegation Order No. 0204-108, published 
    November 10, 1993 (58 FR 59716), the Secretary delegated: (1) the 
    authority to develop long-term power and transmission rates on a non-
    exclusive basis to the Administrator of Western Area Power 
    Administration (Western); (2) the authority to confirm, approve, and 
    place such rates into effect on an interim basis to the Deputy 
    Secretary of Energy; and (3) the authority to confirm, approve, and 
    place into effect on a final basis, to remand, or to disapprove such 
    rates to the Federal Energy Regulatory Commission (FERC). Existing DOE 
    procedures for public participation in power rate adjustments are found 
    at 10 CFR Part 903. Procedures for approving Power Marketing 
    Administration rates by FERC are found at 18 CFR Part 300.
    
    Acronyms and Definitions
    
        As used in this rate order, the following acronyms and definitions 
    apply:
    
    AC:  Alternating Current.
    AC Intertie:  Pacific Northwest-Pacific Southwest Intertie Project.
    Administrator:  The Administrator of Western Area Power Administration 
    (Western).
    BPA:  Bonneville Power Administration.
    Existing PRS:  The PRS used in this rate order, which was used to test 
    the adequacy of the existing rate.
    DC:  Direct Current.
    DOE:  Department of Energy.
    DOE Act:  Department of Energy Organization Act, August 4, 1977 (42 
    U.S.C. 7101 et seq.).
    DOE Order RA 6120.2:  An order dealing with power marketing 
    administration financial reporting and rate-making procedures.
    DSW:  Desert Southwest Customer Service Region.
    FERC:  Federal Energy Regulatory Commission.
    FRN:  Federal Register notice.
    FY:  Fiscal Year.
    kV:  Kilovolt.
    kW:  Kilowatt.
    $/kW/year:  Annual charge for capacity usage--($ per kilowatt per 
    year).
    kWh:  Kilowatthour.
    LCRBDF:  Lower Colorado River Basin Development Fund established under 
    Section 403 of the Colorado River Basin Project Act of 1968 (82 Stat. 
    885).
    MAP:  Mead-Adelanto Project. A 500-kV transmission system joint 
    participation construction project with termination points in southern 
    Nevada and southern California.
    MPP:  Mead-Phoenix Project. A 500-kV transmission system joint 
    participation construction project with termination points in Phoenix, 
    Arizona and southern Nevada.
    mills/kWh:  Mills per kilowatthour.
    Multi-Project Costs:  These are costs for facilities being charged to 
    one project that benefit other projects.
    MW:  Megawatt.
    O&M:  Operations and Maintenance.
    PRS:  Power Repayment Study.
    Proposed Rate:  A rate revision that the Administrator of Western 
    recommends to the Deputy Secretary of Energy for approval.
    Provisional Rate:  A rate which has been confirmed, approved, and 
    placed into effect on an interim basis by the Deputy Secretary.
    Ratesetting PRS:  The PRS that demonstrates that potential revenue 
    levels will satisfy the cost.
    Reclamation:  Bureau of Reclamation.
    Replacement:  A unit of property constructed or acquired as a 
    substitute for an existing unit of property for the purpose of 
    maintaining the power features of a project.
    Retirement Benefits:  Civil Service Retirement Costs and Post 
    Retirement Health Benefits.
    Secretary:  Secretary of Energy.
    Western:  Western Area Power Administration.
    
    Effective Date
    
        The new rate will become effective on an interim basis on the first 
    day of the first full billing period beginning on or after January 1, 
    1999, and will be in effect pending FERC's approval of it or a 
    substitute rate on a final basis for the 5-year period ending December 
    31, 2003, or until superseded. Western is implementing a rate for firm 
    point-to-point transmission service on the AC Intertie 230/345-kV 
    transmission system only.
    
    Public Notice and Comment
    
        The Procedures for Public Participation in Power and Transmission 
    Rate Adjustments and Extensions, 10 CFR Part 903, have been followed by 
    Western in the development of the firm point-to-point transmission 
    service rate. The provisional firm point-to-point transmission service 
    rate for the AC Intertie 230/345-kV transmission system represents a 
    rate increase of 82 percent over the existing rate. This rate is 
    classified as a major rate adjustment as defined at 10 CFR Part 
    903.2(e) and 903.2(f)(1). The distinction between a minor and a major 
    rate adjustment is used only to determine the public procedures for the 
    rate adjustment. The following summarizes the steps Western took to 
    ensure involvement of interested parties in the rate process:
        1. The first informal public information meeting was held on April 
    28, 1997, at the Desert Southwest Customer Service Region (DSW) office 
    located in Phoenix, Arizona. Approximately 13 customers of the AC 
    Intertie were present. Western explained the need for the proposed rate 
    adjustment and answered questions from those attending.
        2. Western held its second informal public information meeting on 
    June 25, 1997, at the DSW office. Approximately 11 customers of the AC 
    Intertie were present. Western staff provided and discussed responses 
    to data requested at the first informal public meeting.
        3. Western held its third informal public information meeting on 
    July 24, 1997, at the DSW office. Approximately 20 customers of the AC 
    Intertie were present. Western staff provided and discussed responses 
    to data requested at the second informal public meeting.
        4. Western provided responses to the questions and comments raised 
    at the third informal customer information meeting by letter dated 
    January 12, 1998.
        5. On April 3, 1998, Western announced in Federal Register notice 
    (FRN) 63 FR 16497 the start of the public process for the approval of 
    the proposed AC Intertie 230/345-kV transmission system firm point-to-
    point transmission service rate. The FRN identified the end of the 
    consultation and comment period as July 2, 1998.
        6. On May 4, 1998, beginning at 10 a.m., a public information forum 
    was held at Western's DSW office. At the start of the forum, a handout 
    containing
    
    [[Page 6346]]
    
    information regarding the updated rate was provided. Western publicly 
    presented the Proposed Rate for the AC Intertie 230/345-kV transmission 
    system, provided a detailed explanation of the changes to the Proposed 
    Rate, and answered questions from the public. On May 20, 1998, a 
    letter, responding to questions not answered at the public information 
    forum, was mailed to the AC Intertie customers.
        7. On June 1, 1998, beginning at 10 a.m., a public comment forum 
    was held at Western's DSW office. Western gave the public an 
    opportunity to comment for the record, verbally and in written form. 
    Eight representatives made oral comments.
        8. Twenty-four comment letters were received during the 
    consultation and comment period. The consultation and comment period 
    ended July 2, 1998. All formally submitted comments have been 
    considered in the preparation of this rate order.
    
    Project Description
    
        The AC Intertie was authorized by section 8 of the Pacific 
    Northwest Power Marketing Act of August 31, 1964. Originally, the AC 
    Intertie was to be a combined Alternating Current (AC) and Direct 
    Current (DC) system which was to connect the Pacific Northwest with the 
    southwest regions of the United States. As authorized, the overall 
    project was to be a cooperative construction venture between Federal 
    and non-Federal entities. In May 1969, the Department of the Interior 
    indefinitely postponed construction because of several delays in 
    congressional funding, revising the DC line's estimated in-service date 
    to the point that some of the potential users withdrew their interest. 
    Consequently, the facilities constructed provide only AC transmission 
    service.
        Western's portion of the AC Intertie consists of two parts, a 
    northern portion and a southern portion. The northern portion is 
    administered by Western's Sierra Nevada Customer Service Region and is 
    incorporated, for repayment, with the Central Valley Project. The 
    northern portion consists of a 94-mile (151 km), 500-kV line from Malin 
    Substation (Oregon) to Round Mountain to Cottonwood Substation 
    (California). By agreement, the Central Valley Project has transmission 
    rights for 400 MW of northern Intertie capacity.
        The southern portion is administered by Western's DSW office and is 
    treated as a separate project for repayment and operational purposes. 
    It consists of a 238-mile (383 km) 345-kV line from Mead Substation 
    (Nevada) to Liberty Substation (Arizona), a 19-mile, (31 km) 230-kV 
    line from Liberty to Westwing Substation (Arizona), a 22-mile (35 km), 
    230-kV line from Westwing to Pinnacle Peak Substation (Arizona), and 
    two new segments which came on-line in April 1996: the 260-mile (419 
    km) Mead-Phoenix 500-kV AC Transmission Line between Marketplace 
    Substation (Nevada) and Perkins Substation (Arizona) and the 202-mile 
    (325 km) Mead-Adelanto 500-kV AC Transmission Line between Marketplace 
    Substation and the existing Adelanto Switching Substation in southern 
    California.
    
    Existing and Provisional Rates
    
    AC Intertie Project Firm Point-to-Point Transmission Service
        The following table displays the existing rates and the Provisional 
    Rates for the AC Intertie 230/345-kV transmission system:
    
                                    Existing Point-to-Point Transmission Service Rate
    [AC intertie 230/345-kV transmission system rate schedule firm point-to-point transmission rate ($ per kW/year)]
    ----------------------------------------------------------------------------------------------------------------
                                             Existing  (effective 10/                               Percent change
               Effective period                 01/96 to 09/30/02)            Provisional         from existing rate
    ----------------------------------------------------------------------------------------------------------------
    01/01/99 to 12/31/03..................  $6.58/kW/Year............  $12.00/kW/Year...........               82.0
    ----------------------------------------------------------------------------------------------------------------
    
    Certification of Rate
    
        Western's Administrator has certified that the AC Intertie 230/345-
    kV transmission system firm point-to-point transmission service rate 
    placed into effect on an interim basis herein is the lowest possible 
    rate consistent with sound business principles. The Provisional Rate 
    has been developed in accordance with administrative policies and 
    applicable laws.
    
    Discussion
    
    AC Intertie Transmission Service
        The existing AC Intertie transmission service rate schedule was 
    placed into effect on February 1, 1996, under Rate Order WAPA-71 (61 FR 
    4850) until September 30, 2002, and was approved on a final basis by 
    FERC on July 24, 1996. Under Rate Order WAPA-71, three types of 
    transmission service rates were approved and they are: (1) a rate for 
    firm transmission service on the AC Intertie 230/345-kV transmission 
    system; (2) a rate for firm transmission service on the AC Intertie 
    500-kV transmission system; and (3) a rate for non-firm transmission 
    service on both the 230/345-kV and the 500-kV transmission systems. 
    Western proposes, through Rate Order WAPA-76, to supersede only the 
    rate for firm transmission service on the AC Intertie 230/345-kV 
    transmission system placed in effect under Rate Order WAPA-71.
    Basis for Rate Development
        Two major issues have prompted the transmission rate adjustment. 
    First, the Provisional Rate accounts for recovery of abandoned project 
    costs with interest. These costs were incurred primarily between 1964 
    and 1969 during the planning and early construction phases of the 
    Celilo-Mead-Los Angeles 750-kV DC Transmission Line. In May 1969, the 
    Department of the Interior indefinitely postponed construction because 
    of several delays in congressional funding, revising the DC line's 
    estimated in-service date to the point that some of the potential users 
    withdrew their interest.
        The second issue is that costs and revenues relating to the new AC 
    Intertie 500-kV transmission system are now being accounted for in the 
    Power Repayment Study (PRS). It is estimated that it will take 
    approximately 10 years for the AC Intertie 500-kV transmission system 
    to be subscribed to a level sufficient to meet its own revenue 
    repayment requirements. The Provisional Rate for firm transmission 
    service on the AC Intertie 230/345-kV transmission system takes into 
    account the phasing-in of the AC Intertie 500-kV transmission system 
    revenues starting with a revenue contribution of $1,500,000 in Fiscal 
    Year (FY) FY 1999, and increasing annually by $1,410,000 through FY 
    2008.
    Power Repayment Study
        As a result of phasing in the AC Intertie 500-kV transmission 
    system revenues, and in order to maintain a marketable rate of $12/kW/
    year, annual deficits are incurred through FY 2005. These deficits 
    allow for the very
    
    [[Page 6347]]
    
    acceptable industry practice of marketing, over time, a major capitol 
    improvement such as the AC Intertie 500-kV transmission system. The 
    annual deficits incurred are all repaid by FY 2017.
    
    Statement of Revenue and Related Expenses
    
        The following table provides a summary of revenues and expenses for 
    the 5-year rate period:
    
                                      AC Intertie Rate Period Revenues and Expenses
                                                        [$1,000]
    ----------------------------------------------------------------------------------------------------------------
                                                                        Provisional    Existing rate
                                                                       rate PRS  FY    PRS  FY 1999-    Difference
                                                                         1999-2003         2003
    ----------------------------------------------------------------------------------------------------------------
            Total Revenues..........................................          91,067          43,435          47,632
    Revenue Distribution:
        O&M.........................................................          20,690          13,226           7,464
        Abandoned Plant.............................................           1,837               0           1,837
        Interest....................................................          91,428          22,474          68,954
        Other.......................................................           4,056           1,848           2,208
        Investment Repayment........................................               0           5,887         (5,887)
        Capitalized Expenses........................................        (26,943)               0        (26,943)
    ----------------------------------------------------------------------------------------------------------------
    
        The following table provides a summary of the average annual 
    revenues and expenses for the 5-year rate period:
    
                 AC Intertie Comparison of Period Average Annual Revenues and Expenses for FY 1999-2003
                                                        [$1,000]
    ----------------------------------------------------------------------------------------------------------------
                                                                        Provisional
                                                                       rate average    Existing rate    Difference
                                                                          annual      average annual
    ----------------------------------------------------------------------------------------------------------------
            Total Revenues..........................................          18,213           8,687           9,526
    Revenue Distribution:
        O&M.........................................................           4,138           2,645           1,493
        Abandoned Plant.............................................             367               0             367
        Interest....................................................          18,286           4,495          13,791
        Other.......................................................             811             370             441
        Investment Repayment........................................               0           1,177         (1,177)
        Capitalized Expenses........................................         (5,389)               0         (5,389)
    ----------------------------------------------------------------------------------------------------------------
    
        The following table provides a summary of revenues and expenses for 
    the 50-year study period:
    
                              AC Intertie Cost Evaluation Rate Period Revenues and Expenses
                                                        [$1,000]
    ----------------------------------------------------------------------------------------------------------------
                                                                        Provisional    Existing rate
                                                                       rate PRS  FY    PRS  FY 1999-    Difference
                                                                         1999-2049         2049
    ----------------------------------------------------------------------------------------------------------------
            Total Revenues..........................................       1,369,275         441,987         927,288
                                                                     -----------------------------------------------
    Revenue Distribution:
        O&M.........................................................         222,164         132,885          89,279
        Abandoned Plant.............................................           9,921               0           9,921
        Interest....................................................         497,108          81,851         415,257
        Other.......................................................          23,191          12,468          10,723
        Investment Repayment........................................         269,849         116,159         153,690
        Capitalized Expenses........................................          22,550               0          22,550
        LCRBDF Transfer.............................................         324,492          98,543         225,949
    ----------------------------------------------------------------------------------------------------------------
    
        The following table provides a summary of the average annual 
    revenues and expenses for the 50-year study period:
    
       AC Intertie Comparison of Cost Evaluation Rate Period Average Annual Revenues and Expenses for FY 1999-2049
                                                        [$1,000]
    ----------------------------------------------------------------------------------------------------------------
                                                                        Provisional
                                                                       rate average    Existing rate    Difference
                                                                          annual      average annual
    ----------------------------------------------------------------------------------------------------------------
            Total Revenues..........................................          27,386           8,840          18,546
                                                                     -----------------------------------------------
    Revenue Distribution:
    
    [[Page 6348]]
    
     
            O&M.....................................................           4,443           2,658           1,785
        Abandoned Plant.............................................             198               0             198
        Interest....................................................           9,407           1,637           7,770
        Other.......................................................             464             249             215
        Investment Repayment........................................           4,230           2,323           1,907
        Capitalized Expenses........................................             451               0             451
        LCRBDF Transfer.............................................           8,192           1,971           6,221
    ----------------------------------------------------------------------------------------------------------------
    
    Comments
    
        During the public consultation and comment period, Western received 
    24 written comments on the rate adjustment. In addition, eight customer 
    representatives orally commented during the June 1, 1998, public 
    comment forum. All comments received by the end of the public 
    consultation and comment period, July 2, 1998, were reviewed and 
    considered in the preparation of this rate order.
        Written comments were received from the following sources:
    
    Aguila Irrigation District (Arizona)
    Arizona Power Authority (Arizona)
    Arizona Public Service Company (Arizona)
    BDJ Farms, LLC (Arizona)
    Central Arizona Project (Arizona)
    Charles A. Ditsch, Attorney at Law (Arizona)
    City of Safford (Arizona)
    Colorado River Commission of Nevada (Nevada)
    Colorado River Energy Distributors Association (Arizona)
    Electrical District No. 3 (Arizona)
    Electrical District No. 5 (Arizona)
    Electric Resource Strategies (Arizona)
    Gladden Farms II (Arizona)
    Harquahala Valley Power District (Arizona)
    James N. Warkomski, P.E., R.L.S. (Arizona)
    John DelMar, Electrical District No. 8 Member (Arizona)
    McMullen Valley Water Conservation and Drainage District (Arizona)
    Meyer, Hendricks, Bivens & Moyes, P.A. (Arizona)
    Nevada Power Company (Nevada)
    Robert S. Lynch, Attorney at Law (Arizona)
    Salt River Project (Arizona)
    Thatcher (Arizona)
    Tonopah Irrigation District (Arizona)
    
        The following is a summary of the comments received by the end of 
    the consultation and comment period and Western's responses to those 
    comments. The comments are paraphrased for brevity and responses are 
    presented below. Specific comments are used for clarification where 
    necessary.
        Comment: Several commentors protested the inclusion of the 
    abandoned project costs relating to the Celilo-Mead-Los Angeles 750-kV 
    DC transmission line in the rate order stating that doing so would be 
    inequitable and inconsistent with the financial reporting policies, 
    procedures, and methodology established under DOE Order RA 6120.2. The 
    commentors also referenced a longstanding rate making principle that 
    customers should only be required to pay for facilities that are 
    ``prudent'' investments and which are ``used and useful'' in providing 
    electric service.
        Response: Western held the abandoned project costs from 1969 until 
    1993 in a deferred asset account. In 1993, these costs were booked in 
    Western's financial statements as an expense against Operation and 
    Maintenance. Western has withheld the inclusion of these costs from the 
    PRS in any of the previous rate orders while it determined the 
    appropriate course of action. Western's auditors issued findings in 
    1994 and 1995 that the proper treatment of abandoned project costs is 
    the full cost recovery through project rates of the costs plus any 
    accrued interest. In 1996, Western's Administrator committed to comply 
    with the auditor recommendation before a Congressional subcommittee 
    hearing.
        Comment: Several commentors questioned Western's legal authority to 
    collect the abandoned project costs relating to the Celilo-Mead-Los 
    Angeles 750-kV DC transmission line.
        Response: Fundamental principles of Reclamation Law require the 
    recovery of the Government's construction investment, with interest 
    (Reclamation Project Act of 1939, Section 9(c); 53 Stat. 1187, 1194). 
    Western is not aware of any authority exempting the abandoned project 
    costs from this requirement.
        Comment: Several commentors questioned the difference in Western's 
    proposed treatment of the abandoned project costs relating to the 
    Celilo-Mead-Los Angeles 750-kV DC transmission line from the position 
    stated by the Bonneville Power Administration (BPA) with regard to 
    costs incurred under the Teton Dam Project. In 1976, the Teton Dam 
    Project failed, and a decision was subsequently made by the Bureau of 
    Reclamation (Reclamation) not to recommence construction. To date, the 
    costs associated with the Teton Dam Project have not been included in 
    BPA's customer rates for repayment.
        Response: The debt incurred by Western relating to the Celilo-Mead-
    Los Angeles 750-kV DC transmission line was funded through government 
    appropriations. The Reclamation Project Act of 1939 requires repayment 
    of appropriations. Through this rate order, these costs will be repaid 
    through the project rates. The costs associated with the Teton Dam 
    Project remain a part of BPA's appropriated debt balance. The debt 
    balance can be reduced through repayment or through Congressional 
    action to de-authorize the project and declare the costs as non-
    reimbursable. To Western's knowledge, BPA is currently not pursuing 
    either of the two options available for reducing appropriated debt. 
    Western, however, recognizes the AC Intertie customers' intention of 
    seeking, through Congressional action, to declare the abandoned project 
    costs related to the Celilo-Mead-Los Angeles 750-kV DC transmission 
    line as non-reimbursable. In order to avoid the costly process 
    associated with reversing the costs should the customers' efforts be 
    successful, Western is willing to allow the deposit of customer monies 
    associated with these disputed abandoned project costs in an escrow 
    account, for a 2-year period, thereby allowing sufficient time for the 
    customers' efforts to be concluded.
    
    [[Page 6349]]
    
        Comment: A commentor questioned the amount of funds appropriated 
    for the Celilo-Mead-Los Angeles 750-kV DC transmission line.
        Response: The specific amount of funds appropriated to Reclamation 
    for the construction of the Celilo-Mead-Los Angeles 750-kV DC 
    transmission line is not readily available. However, appropriations 
    funded construction activities from 1964 through 1969 were recorded as 
    capitalized costs in Reclamation's AC Intertie financial statements. 
    These capitalized costs, plus accrued interest, make up the abandoned 
    project costs.
        Comment: A commentor protested the inclusion of costs associated 
    with the AC Intertie 500-kV transmission system into the proposed 
    rates.
        Response: Western has maintained maximum flexibility for the AC 
    Intertie Project by maintaining independent transmission service rates 
    for the 230/345-kV transmission system and the 500-kV transmission 
    system. However, DSW is responsible for demonstrating repayment for 
    those AC Intertie facilities constructed with appropriated funds 
    allocated to DSW. The firm point-to-point transmission service rate 
    being proposed under this rate order will satisfy the repayment 
    criteria that Power Marketing Administrations are subject to while 
    maintaining the flexibility of a possible reduction to the 230/345-kV 
    transmission system rate in future years should revenues from the AC 
    Intertie 500-kV transmission system materialize as projected.
        Comment: A commentor questioned the existence of any specific Act 
    authorizing Western to construct the AC Intertie 500-kV transmission 
    system.
        Response: Construction of the Intertie was initially authorized by 
    the Pacific Northwest Preference Act of 1964 (P.L. 88-552; 78 Stat. 
    756). Subsequently, the Energy and Water Development Appropriation Act 
    of 1985, Public Law No. 98-360, 98 Stat. 403, 416, authorized Western's 
    participation in the construction of the AC Intertie 500-kV 
    transmission system.
        Comment: A commentor stated that the construction and inclusion in 
    the proposed rate of the AC Intertie 500-kV Intertie transmission 
    system violates Western's goals with regards to limiting increases in 
    annual operating expenses in order to maintain competitive rates.
        Response: Western's goal of limiting increases in annual operating 
    expenses, exclusive of debt service, in order to maintain competitive 
    rates in the markets served by Western was first published in September 
    1994 and was not in existence when construction began on the AC 
    Intertie 500-kV transmission system. Nevertheless, the overwhelming 
    majority of costs relating to the AC Intertie 500-kV transmission 
    system is for debt service and not annual operating expenses. 
    Furthermore, the proposed firm point-to-point transmission service rate 
    of $12/kW/year remains less than Western's Parker-Davis Project 
    transmission service rate of $12.99/kW/year and also less than the firm 
    point-to-point transmission rates offered by the other utilities that 
    operate in the same regional markets served by DSW.
        Comment: A commentor stated that the construction and inclusion in 
    the proposed rate of the AC Intertie 500-kV transmission system 
    violates Western's operating rules with regards to subjecting new 
    facilities for construction to at least one of three criteria: (1) 
    increased revenues from the new facilities must exceed the annual cost 
    over the cost evaluation period; (2) customers must benefit 
    sufficiently to support the new facilities in spite of a possible rate 
    increase; or (3) the new facilities must be funded by others.
        Response: Western's operating rules for construction of new 
    facilities were first published in September 1994 and were not in 
    existence when construction began on the AC Intertie 500-kV 
    transmission system. However, Western had conducted studies and surveys 
    prior to the construction of the AC Intertie 500-kV transmission system 
    that supported Western's participation in the Mead-Phoenix Project 
    (MPP) and Mead-Adelanto Project (MAP). Studies conducted in 1989 
    indicated that given Western's generation capability and load patterns, 
    Western's transmission system existing at the time of the studies did 
    not have the capacity to effectively market Federal power resources. 
    Western's decision to participate in the MPP and MAP was substantiated 
    by an independently-produced resources and transmission study conducted 
    in 1990. The MPP and MAP were joint participation construction projects 
    with 11 other entities. The entities are as follows: Arizona Public 
    Service Company; City of Anaheim; City of Azusa; City of Banning; City 
    of Burbank; City of Colton; City of Glendale; City of Pasadena; City of 
    Riverside; City of Vernon; Los Angeles Department of Water and Power; 
    Public Power Agency of Modesto, Santa Clara, and Redding; and Salt 
    River Project.
        This vast number of participants only underscores the perceived 
    need by the participants at the time of construction. Furthermore, 
    Western conducted a number of surveys between November 1990, and 
    January 1996, all of which resulted in substantial interest by 
    prospective customers for transmission capacity. In February 1996, 
    Western began contract negotiations with prospective customers. During 
    negotiations, it became apparent that various external industry issues 
    were emerging and that these issues were having an impact on the 
    negotiations. The prospective customers decided to delay contracting 
    for long-term firm transmission capacity over the AC Intertie 500-kV 
    transmission system. FERC Order No. 888 became effective July 9, 1996. 
    FERC Order No. 888 is designed to promote competition through open 
    access and has brought many new players to the wholesale bulk power 
    business. As a result, utilities are striving to improve their short-
    term competitive position, and prospective customers are staying away 
    from committing to long-term transmission contracts.
        Comment: A commentor referenced 10 CFR. 903.21(g) in conjunction 
    with a statement concerning the AC Intertie 500-kV transmission 
    facilities, that ``Western is not legally permitted to construct 
    speculative transmission facilities on the backs of the preference 
    customers it has a statutory obligation to serve at the lowest possible 
    rates consistent with sound business principles.''
        Response: The reference to 10 CFR 903.21(g) is erroneous because no 
    such section exists. Moreover, as explained previously, Western's 
    participation in the construction of the AC Intertie 500-kV 
    transmission system was specifically authorized by Public Law No. 98-
    360. In response to the criticism that the construction of the AC 
    Intertie 500-kV transmission system was a speculative enterprise, it 
    should be noted once again that the MPP and MAP were joint 
    participation construction projects with 11 other entities. The 
    entities are as follows: Arizona Public Service Company; City of 
    Anaheim; City of Azusa; City of Banning; City of Burbank; City of 
    Colton; City of Glendale; City of Pasadena; City of Riverside; City of 
    Vernon; Los Angeles Department of Water and Power; Public Power Agency 
    of Modesto, Santa Clara, and Redding; and Salt River Project. Due to 
    changes in the electric industry as a whole, utilities are having to 
    defend stranded investments that the electric utility industry has 
    undertaken. At the present time, many of the participants are trying to 
    effectively market their entitlement of the MPP and MAP. Stranded 
    investments, due to industry restructuring in California alone, are 
    projected to be more than $4 billion. At the time Western and other 
    utilities made the decision to participate in the
    
    [[Page 6350]]
    
    MPP and MAP, the decision was sound. As late as February 1996, 
    utilities were requesting 649 MW of capacity on the AC Intertie 500-kV 
    transmission system.
        Comment: Several commentors protested the inclusion of the unfunded 
    portion of the Civil Service Retirement Costs and Post-Retirement 
    Health and Life Insurance Benefits (Retirement Benefits) in the rate 
    order and in some cases stated that Western did not possess the legal 
    authority to either collect the funds, to divert the funds to the 
    Office of Personnel Management prior to their deposit in the 
    Reclamation Fund, or to withdraw the funds from the Reclamation Fund 
    for these same purposes.
        Response: Under a legal opinion provided by the General Counsel of 
    the DOE by memorandum dated July 1, 1998, the Power Marketing 
    Administrations have the authority to collect through the rates the 
    full costs of the Retirements Benefits. Based on the FY 1998 data 
    expected to be booked to the AC Intertie, this amounts to $120,359 for 
    FY 1999, representing less than one percent of the AC Intertie revenue 
    requirements for FY 1999. At this time, Western's only intention is to 
    deposit the funds into the Reclamation Fund.
        Comment: A commentor requested that the construction work planned 
    for replacing the 345-kV series capacitor banks at Mead and Liberty 
    Substations be reevaluated and that the projected cost be removed from 
    the rate order.
        Response: Western agrees with the commentor's request to reevaluate 
    the necessity of replacing the series capacitor banks and has removed 
    the projected costs from the rate order.
        Comment: A commentor requested an explanation as to why Multi-
    Project Costs are no longer being booked in the PRS.
        Response: Western had intended to separate the investment costs 
    that are the basis for the Multi-Project Cost calculation and allocate 
    them to their respective projects for repayment. Western has 
    reevaluated the benefit of such action and will continue to book the 
    Multi-Project Costs in the PRS consistent with previously established 
    procedures.
    
    Regulatory Flexibility Analysis
    
        The Regulatory Flexibility Act of 1980 (5 U.S.C. 601, et seq.) 
    requires Federal agencies to perform a regulatory flexibility analysis 
    if a final rule is likely to have a significant economic impact on a 
    substantial number of small entities and there is a legal requirement 
    to issue a general notice of proposed rulemaking. Western has 
    determined that this action does not require a regulatory flexibility 
    analysis since it is a rulemaking of particular applicability involving 
    rates or services applicable to public property.
    
    Small Business Regulatory Enforcement Fairness Act
    
        Western has determined that this rule is exempt from Congressional 
    notification requirements under 5 U.S.C. 801 because the action is a 
    rulemaking of a particular applicability relating to rates or services 
    and involves matters of procedure.
    
    Environmental Compliance
    
        In compliance with the National Environmental Policy Act of 1969, 
    42 U.S.C. 4321 et seq.; Council on Environmental Quality Regulations, 
    40 CFR Parts 1500-1508; and DOE NEPA Regulations, 10 CFR Part 1021, 
    Western has determined that this action is categorically excluded from 
    the preparation of an environmental assessment or an environmental 
    impact statement.
    
    Determination Under Executive Order 12866
    
        Western has an exemption from centralized regulatory review under 
    Executive Order 12866; accordingly, no clearance of this notice by the 
    Office of Management and Budget is required.
    
    Availability of Information
    
        Information regarding this rate adjustment, including project 
    repayment studies, comments, letters, memorandums, and other supporting 
    material made or kept by Western for the purpose of developing the 
    Provisional Rates, is available for public review in the Desert 
    Southwest Regional Office, Western Area Power Administration, Office of 
    the Power Marketing Manager, 615 South 43rd Avenue, Phoenix, Arizona.
    
    Submission to the Federal Energy Regulatory Commission
    
        The rates herein confirmed, approved, and placed into effect on an 
    interim basis, together with supporting documents, will be submitted to 
    FERC for confirmation and approval on a final basis.
    
    Order
    
        In view of the foregoing and pursuant to the authority delegated to 
    me by the Secretary of Energy, I confirm and approve on an interim 
    basis, effective January 1, 1999, Rate Schedule INT-FT3 for the Pacific 
    Northwest-Pacific Southwest Intertie Project 230/345-kV transmission 
    system of the Western Area Power Administration. The rate schedule 
    shall remain in effect on an interim basis, pending FERC confirmation 
    and approval of it or a substitute rate on a final basis through 
    December 31, 2003.
    
        Dated: January 28, 1999.
    Ernest J. Moniz,
    Acting Deputy Secretary.
    
    Schedule of Rate(s) for Long-Term and Short-Term 230/345-kV Firm 
    Point-to-Point Transmission Service
    
        Rate Schedule INT-FT3 (Supersedes Schedule INT-FT2) for 230/345-
    kV Firm Transmission.
    
        Effective: The first day of the first full billing period beginning 
    on or after January 1, 1999, and will remain in effect through December 
    31, 2003, or until superseded, whichever occurs first.
        Available: Within the marketing area served by the Pacific 
    Northwest-Pacific Southwest Intertie Project (AC Intertie) 230/345-kV 
    transmission system.
        Applicable: To firm transmission service customers where capacity 
    and energy are supplied to the AC Intertie 230/345-kV transmission 
    system at points of interconnection with other systems and transmitted 
    and delivered, less losses, to points of delivery on the AC Intertie 
    230/345-kV transmission system pursuant to the applicable firm point-
    to-point transmission service agreement and the rates referred to 
    below.
        Character and Conditions of Service: Alternating current at 60 
    Hertz, three-phase, delivered and metered at the voltages and points of 
    delivery established by contract over the AC Intertie 230/345-kV 
    transmission lines.
        Long-Term Rate on the AC Intertie 230/345-kV Transmission System: 
    For transmission service of longer than one year, the rate to be in 
    effect January 1, 1999, through December 31, 2003, is $12.00 per 
    kilowatt per year for each kilowatt delivered at the point of delivery, 
    as established by contract, payable monthly at the rate of $1.00 per 
    kilowatt per month.
        Short-Term Rates on the AC Intertie 230/345-kV Transmission System: 
    For transmission service up to one year, the maximum rate to be in 
    effect from January 1, 1999, through December 31, 2003, is as follows:
    
    Yearly:  $12.00/kW
    Monthly:  $1.00/kW
    Weekly:  $.23/kW
    Daily:  $.03/kW
    Hourly: $.00137/kWh
    
        Discounts may be offered from time-to-time in accordance with 
    Western's open access transmission service tariff.
    
    [[Page 6351]]
    
        Billing: The rates listed above will be applied to the amount of 
    capacity reserved, payable whether utilized or not.
        For Losses: Capacity and energy losses incurred in connection with 
    the transmission and delivery of capacity and energy under this rate 
    schedule shall be supplied by the customer in accordance with the 
    transmission service agreement.
    
    [FR Doc. 99-3114 Filed 2-8-99; 8:45 am]
    BILLING CODE 6450-01-P
    
    
    

Document Information

Effective Date:
1/1/1999
Published:
02/09/1999
Department:
Western Area Power Administration
Entry Type:
Notice
Action:
Notice of rate order.
Document Number:
99-3114
Dates:
The provisional rates will be placed into effect on an interim basis on January 1, 1999, and will be in effect until FERC confirms, approves, and places the provisional rates in effect on a final basis for a 5-year period ending December 31, 2003, or until superseded.
Pages:
6344-6351 (8 pages)
Docket Numbers:
Rate Order No. WAPA-76
PDF File:
99-3114.pdf