99-5935. Preparation of an Environmental Impact Statement for the Proposed Restoration of a Portion of Icicle Creek Near Leavenworth National Fish Hatchery, Chelan County, WA  

  • [Federal Register Volume 64, Number 46 (Wednesday, March 10, 1999)]
    [Notices]
    [Page 11945]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-5935]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    DEPARTMENT OF THE INTERIOR
    
    Fish and Wildlife Service
    
    
    Preparation of an Environmental Impact Statement for the Proposed 
    Restoration of a Portion of Icicle Creek Near Leavenworth National Fish 
    Hatchery, Chelan County, WA
    
    AGENCY: Fish and Wildlife Service, Interior. Cooperating Agency: Forest 
    Service, U.S. Department of Agriculture.
    
    ACTION: Notice of intent to prepare an Environmental Impact Statement.
    
    -----------------------------------------------------------------------
    
    SUMMARY: This notice advises the public that the U.S. Fish and Wildlife 
    Service (Service) and U.S. Forest Service intend to gather information 
    necessary for the preparation of an Environmental Impact Statement 
    (EIS). The EIS will consider, analyze and disclose the potential 
    environmental impacts of a site specific restoration project on Icicle 
    Creek. The proposed restoration site is approximately 3 miles south of 
    the town of Leavenworth, Washington on the grounds of the Leavenworth 
    National Fish Hatchery. The restoration objectives include: (1) 
    Providing passage to habitat above the hatchery to native fish, and (2) 
    restoring the historic Icicle Creek channel within the hatchery 
    grounds. To achieve these objectives, alternative restoration 
    strategies may include the following actions: modification or removal 
    of weirs in the original channel; removal of the diversion dam from 
    Icicle Creek and restoration of streamflow in the historic channel; 
    removal of silt that has built up in holding ponds in the historic 
    channel; and removal of the canal and energy dispersion spillway. This 
    notice is being furnished pursuant to the Council on Environmental 
    Quality Regulations for Implementing the Procedural Provisions of the 
    National Environmental Policy Act (NEPA) Regulations (40 CFR 1501.7 and 
    1508.22) to obtain suggestions and information from other agencies and 
    the public on the scope of issues and alternatives to be considered in 
    preparation of the EIS.
    
    DATES: Comments concerning the scope and analysis of this proposal 
    should be received by June 1, 1999.
    
    ADDRESSES: Comments regarding the scope of the EIS should be addressed 
    to Greg Pratschner, National Fish Hatchery Manager, 12790 Fish Hatchery 
    Road, Leavenworth, Washington 98826. Comments should be received on or 
    before June 1, 1999, at the above address. Written comments may also be 
    sent by facsimile to (509) 548-6263. Comments received will be 
    available for public inspection by appointment during normal business 
    hours (8:00 a.m. to 4:00 p.m., Monday through Friday) at the above 
    office; please call for an appointment. All comments received will 
    become part of the administrative record and may be released.
    
    FOR FURTHER INFORMATION CONTACT: Corky Broaddus, Public Information 
    Officer, Leavenworth National Fish Hatchery, 12790 Fish Hatchery Road, 
    Leavenworth, Washington 98826; phone (509) 548-7641.
    
    SUPPLEMENTARY INFORMATION: The proposed Icicle Creek Restoration 
    Project was prompted by citizens interested in re-establishing fish 
    passage to upper Icicle Creek. The original design of the Leavenworth 
    National Fish Hatchery involved diverting the majority of the flow of 
    Icicle Creek to a canal and construction of holding dams and ponds in 
    the original channel. These structures effectively blocked upper Icicle 
    Creek to fish passage and reduced the effective stream channel by 1.5 
    miles. Since these structures are no longer necessary for hatchery 
    operation, a fish passage and stream restoration project has been 
    proposed. The environmental analysis will examine different ways to 
    restore this portion of Icicle Creek as well as re-establish fish 
    passage.
        A range of alternatives for stream restoration will be considered, 
    including: a no action alternative (maintaining the current situation), 
    an alternative that would remove all unnecessary in-stream structures, 
    an alternative that would remove silt which has been deposited in the 
    historic stream channel and an alternative where diversion of the main 
    flow of Icicle Creek would be returned to the historic channel. Other 
    alternatives may be developed in response the comments received during 
    public scoping.
        To date the following issues have been identified: hydrologic and 
    sedimentation concerns, potential water quality changes, tribal 
    fishing, recreational fishing, irrigation or water rights, hatchery 
    operations, economic concerns, heritage values, and sensitive plants, 
    animals and fish.
        The decision to be made through this analysis is where, how, and to 
    what extent should stream restoration and fish passage projects be 
    implemented at the Leavenworth National Fish Hatchery.
        The U.S. Forest Service, Department of Agriculture, has agreed to 
    participate as a cooperating agency to evaluate potential effects to 
    sensitive plants and animals and to recreation in upper Icicle Creek, 
    and to provide hydrologic and planning skills. Public participation 
    will be especially important at several points during the analysis. The 
    U.S. Fish and Wildlife Service is seeking information, comments and 
    assistance from federal, state, tribal, and local agencies, as well as 
    individuals and organizations who may be interested or be affected by 
    the proposed actions. This information will be used in preparation of 
    the draft EIS. The scoping process includes: (1) Identifying potential 
    issues; (2) identifying additional alternatives; and (3) identifying 
    potential environmental effects of the proposed alternatives. The 
    Service invites written comments on the scope of this project. In 
    addition, the Service gives notice of this analysis so the interested 
    and affected people are aware of how they may participate and 
    contribute to the final decision.
    
        Dated: March 3, 1999.
    Don Weathers,
    Regional Director, Region 1, Fish and Wildlife Service.
    [FR Doc. 99-5935 Filed 3-9-99; 8:45 am]
    BILLING CODE 4310-55-P
    
    
    

Document Information

Published:
03/10/1999
Department:
Fish and Wildlife Service
Entry Type:
Notice
Action:
Notice of intent to prepare an Environmental Impact Statement.
Document Number:
99-5935
Dates:
Comments concerning the scope and analysis of this proposal should be received by June 1, 1999.
Pages:
11945-11945 (1 pages)
PDF File:
99-5935.pdf