97-5936. K N Wattenberg Transmission Limited Liability Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 62, Number 47 (Tuesday, March 11, 1997)]
    [Notices]
    [Pages 11166-11167]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-5936]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP97-256-000]
    
    
    K N Wattenberg Transmission Limited Liability Company; Notice of 
    Request Under Blanket Authorization
    
    March 5, 1997.
        Take notice that on February 20, 1997, K N Wattenberg Transmission 
    Limited Liability Company (K N Wattenberg), P.O. Box 281304, Lakewood, 
    CO 80228, filed in Docket No. CP97-256-000, a request pursuant to 
    Sections 157.205, 157.208 and 157.211 of the Commission's Regulations 
    under the Natural Gas Act (18 CFR 157.205, 157.208 and 157.211). K N 
    Wattenberg requests authorization to install a new delivery lateral 
    along with receipt point facilities and two delivery points in Morgan 
    County, CO to provide transportation service for two end user shippers, 
    under K N Wattenberg's blanket certificate issued in Docket No. CP92-
    203-000, pursuant to 18 CFR Part 157, Subpart F of the Natural Gas Act, 
    all as more fully set forth in the request which is on file with the 
    Commission and open to public inspection.
        Specifically, K N Wattenberg proposes to install approximately 4 
    miles of 6-inch pipe, 1 mile of 4-inch pipe, interconnect facilities at 
    the upstream end of the proposed lateral with the existing pipeline 
    facilities of Colorado Interstate Gas Company in Morgan County, CO, and 
    measurement and control facilities at two delivery points. K N 
    Wattenberg states that these proposed facilities would provide
    
    [[Page 11167]]
    
    transportation service to Leprino Foods Company and Excel Corporation 
    for use in their facilities at Fort Morgan, CO.
        K N Wattenberg also states that the estimated cost of the proposed 
    facilities is approximately $725,000. K N Wattenberg further states 
    that K N Energy, Inc., K N Wattenberg's parent company, would finance 
    the project out of funds on hand or by a loan or an equity investment, 
    or a combination of the two.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedureal Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective on the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 97-5936 Filed 3-10-97; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
03/11/1997
Department:
Energy Department
Entry Type:
Notice
Document Number:
97-5936
Pages:
11166-11167 (2 pages)
Docket Numbers:
Docket No. CP97-256-000
PDF File:
97-5936.pdf