96-5993. Diamond H Testing Company; Pocatello, Idaho; Order Imposing Civil Monetary Penalty  

  • [Federal Register Volume 61, Number 50 (Wednesday, March 13, 1996)]
    [Notices]
    [Pages 10387-10389]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-5993]
    
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 030-32202; License No. 11-27316-01; EA 95-148]
    
    
    Diamond H Testing Company; Pocatello, Idaho; Order Imposing Civil 
    Monetary Penalty
    
    I
    
        Diamond H Testing Company (DHT, Licensee) is the holder of NRC 
    Materials License No. 11-27316-01 issued by the Nuclear Regulatory 
    Commission (NRC or Commission). The license authorizes the Licensee to 
    possess sealed radioactive sources and to utilize those sources to 
    conduct industrial radiography in accordance with the conditions 
    specified therein.
    
    II
    
        An inspection of the Licensee's activities was conducted June 16 
    through July 12, 1995, following the Licensee's report of an incident 
    that occurred during radiography activities in Hawaii. The results of 
    this inspection, documented in a report issued on September 11, 1995, 
    indicated that the Licensee had not conducted its activities in full 
    compliance with NRC requirements. A predecisional enforcement 
    conference was conducted on September 26, 1995, in the NRC's Arlington, 
    Texas, office. A written Notice of Violation and Proposed Imposition of 
    Civil Penalty (Notice) in the amount of $8,000 was served upon the 
    Licensee by letter dated October 25, 1995. The Notice described the 
    nature of the violations, the provisions of the NRC's requirements that 
    the Licensee had violated, and the amount of the civil penalty proposed 
    for the violations.
        The Licensee responded to the Notice in two letters both dated 
    November 15, 1995 (Reply to a Notice of Violation and Answer to a 
    Notice of Violation). In its responses, the Licensee admitted that 
    portions of the regulations were violated, but denied that it should be 
    held responsible for the violations because they resulted from 
    independent decisions made by one of its radiographers, and stated that 
    certain factors warranted mitigation of the proposed civil penalty.
    
    III
    
        After consideration of the Licensee's response and the statements 
    of fact, explanation, and argument for mitigation contained therein, 
    the NRC staff has determined, as set forth in the Appendix to this 
    Order, that the violations occurred as described in the Notice, that 
    the Licensee is fully responsible for the violations committed by its 
    radiographer, and that the penalty proposed for the violations 
    designated in the Notice should be mitigated by $3,000. Thus, a civil 
    penalty in the amount of $5,000 should be imposed.
    
    IV
    
        In view of the foregoing and pursuant to Section 234 of the Atomic 
    Energy Act of 1954, as amended (Act), 42 U.S.C. 2282, and 10 CFR 2.205, 
    it is hereby ordered that:
        The Licensee pay a civil penalty in the amount of $5,000 within 30 
    days of the date of this Order, by check, draft, money order, or 
    electronic transfer, payable to the Treasurer of the United States and 
    mailed to James Lieberman, Director, Office of Enforcement, U.S. 
    Nuclear Regulatory Commission, One White Flint North, 11555 Rockville 
    Pike, Rockville, MD 20852-2738.
    
    V
    
        The Licensee may request a hearing within 30 days of the date of 
    this Order. Where good cause is shown, consideration will be given to 
    extending the time to request a hearing. A request for extension of 
    time must be made in writing to the Director, Office of Enforcement, 
    U.S. Nuclear Regulatory Commission Washington, D.C. 20555, and include 
    a statement of good cause for the extension. A request for a hearing 
    should be clearly marked as a ``Request for an Enforcement Hearing'' 
    and shall be addressed to the Director, Office of Enforcement, U.S. 
    Nuclear Regulatory Commission Washington, D.C. 20555, with a copy to 
    the Commission's Document Control Desk, Washington, D.C. 20555. Copies 
    also shall be sent to the Assistant General Counsel for Hearings and 
    Enforcement at the same address and to the Regional Administrator, NRC 
    Region IV, 611 Ryan Plaza Drive, Suite 400, Arlington, Texas 76011.
        If a hearing is requested, the Commission will issue an Order 
    designating the time and place of the hearing. If the Licensee fails to 
    request a hearing within 30 days of the date of this Order (or if 
    written approval of an extension of time in which to request a hearing 
    has not been granted), the provisions of this Order shall be effective 
    without further proceedings. If payment has not been made by that time, 
    the matter may be referred to the Attorney General for collection.
        In the event the Licensee requests a hearing as provided above, the 
    issues to be considered at such hearing shall be:
        (a) Whether the Licensee was in violation of the Commission's 
    requirements as set forth in Section I of the Notice referenced in 
    Section II above, and
    
    [[Page 10388]]
    
        (b) Whether, on the basis of such violations, this Order should be 
    sustained.
    
        For the Nuclear Regulatory Commission.
    
        Dated at Rockville, Maryland, this 5th day of March 1996.
    James Lieberman,
    Director, Office of Enforcement.
    
    Appendix--Evaluation and Conclusions
    
        On October 25, 1995, a Notice of Violation and Proposed 
    Imposition of Civil Penalty (Notice) in the amount of $8,000 was 
    issued to Diamond H Testing Company (DHT or Licensee) for violations 
    identified during an NRC inspection. The Licensee responded to the 
    Notice in two letters both dated November 15, 1995. The Licensee 
    admitted that portions of the regulations were violated, but denied 
    that it should be held responsible for the violations because they 
    resulted from independent decisions made by one of its 
    radiographers, and stated that certain factors warranted mitigation 
    of the proposed civil penalty.
    
    Restatement of Violations I.A, I.B, and I.C
    
        A. 10 CFR 34.22(a) requires, in part, that, during radiographic 
    operations, the sealed source assembly be secured in the shielded 
    position each time the source is returned to that position.
        Contrary to the above, on two occasions on June 14, 1995, during 
    radiographic operations at the Hawaiian Electric Company Kahe Unit 5 
    Power Plant, a licensee radiographer did not secure the sealed 
    source assembly in the shielded position after returning the source 
    to that position. (01012)
        B. 10 CFR 34.33(a) requires that the licensee not permit any 
    individual to act as a radiographer or a radiographer's assistant 
    unless, at all times during radiographic operations, the individual 
    wears a direct-reading pocket dosimeter, an alarm ratemeter, and 
    either a film badge or a thermoluminescent dosimeter.
        Contrary to the above, on June 14, 1995, during radiographic 
    operations at the Hawaiian Electric Company Kahe Unit 5 Power Plant, 
    a licensee radiographer did not wear an alarm ratemeter while 
    conducting radiographic operations. (01022)
        C. 10 CFR 34.43(b) requires, in part, the licensee to ensure 
    that a survey with a calibrated and operable radiation survey 
    instrument is made after each radiographic exposure to determine 
    that the sealed source has been returned to its shielded position. 
    The survey must include the entire circumference of the radiographic 
    exposure device and any source guide tube.
        Contrary to the above, on June 14, 1995, during radiographic 
    operations at the Hawaiian Electric Company Kahe Unit 5 Power Plant, 
    a licensee radiographer did not perform an adequate survey after a 
    radiographic exposure to determine that the sealed source had been 
    returned to its shielded position in that the survey only included a 
    portion of the source guide tube. (01032)
        These violations represent a Severity Level II problem 
    (Supplement VI). Civil Penalty--$8,000
    
    Summary of Licensee's Response to Violations I.A, I.B, and I.C
    
        The Licensee argued that there are several parts to each of the 
    cited requirements for the above violations and that only one part 
    of each requirement was violated. In addition, the Licensee denied 
    that it should be held responsible for the violations because they 
    resulted from independent decisions made by one of its 
    radiographers.
        DHT did not admit responsibility for the violations, all of 
    which DHT asserts resulted from the independent actions of the same 
    radiographer who, DHT states, was experienced and appropriately 
    trained. DHT also noted that the NRC found no negligence on DHT's 
    part with respect to its radiation safety program or training of 
    employees.
    
    NRC Evaluation of the Licensee's Response to Violations I.A, I.B, 
    and I.C
    
        The sections of 10 CFR Part 34 cited in the Notice set forth a 
    number of requirements, and, in some cases, more than one 
    requirement is contained in the same subsection or paragraph. As an 
    NRC licensee, DHT is required to comply with each and every 
    requirement in every instance in which a requirement applies. In 
    this case, DHT failed to ensure that: (1) The sealed source was 
    secured in the camera, (2) an adequate survey was performed, and (3) 
    an alarm ratemeter was worn during radiographic operations; and the 
    Licensee did not dispute the fact that these violations occurred. 
    Therefore, the NRC concludes that the violations occurred as stated.
        The NRC strongly disagrees with, and is concerned about, DHT's 
    failure to accept responsibility for the violations. The Commission 
    resolved the responsibility issue between a licensee and its 
    employees in its decision concerning the Atlantic Research 
    Corporation case, CLI-80-7, dated March 14, 1980, a copy of which is 
    enclosed. In that case, the Commission stated, in part, that ``a 
    division of responsibility between a licensee and its employees has 
    no place in the NRC regulatory regime which is designed to implement 
    our obligation to provide adequate protection to the health and 
    safety of the public in the commercial nuclear field.''
        The NRC does not specifically license the management or the 
    employees of a company; rather, the NRC licenses the entity. The 
    licensee uses, and is responsible for the possession of, licensed 
    material. The licensee is the entity that hires, trains, and 
    supervises the employees. All licensed activities are carried out by 
    employees of licensees and, therefore, all violations are committed 
    by employees of licensees. The licensee obtains the benefits of the 
    employees good performance and suffers the consequences of their 
    poor performance. Not holding the licensee responsible for the 
    action of its employees, whether negligent or willful, is tantamount 
    to saying that the licensee is not responsible for the use or 
    possession of licensed material. If the NRC accepted DHT's position: 
    (1) The NRC would have little ability to ensure its requirements on 
    licensees were met and the public health and safety were protected; 
    and (2) there would be little incentive for licensees to monitor 
    their activities to assure compliance. Therefore, the NRC holds 
    licensees responsible for the actions of their employees (``General 
    Statement of Policy and Procedure for NRC Enforcement Actions'' 
    (Enforcement Policy), NUREG-1600, Section VI.A). With regard to the 
    DHT's argument that the NRC found no negligence on DHT's part and 
    found its radiation safety and training programs adequate, the NRC 
    considers this irrelevant to whether a violation occurred. As to 
    civil penalties, Section VI.B of the Enforcement Policy provides 
    that ``the lack of management involvement may not be cause to 
    mitigate a civil penalty.''
    
    Summary of the Licensee's Request for Mitigation
    
        The Licensee offered numerous arguments for mitigation of the 
    proposed penalty. Below is a summary listing of the Licensee's 
    arguments that are related to its request for mitigation, some of 
    which have been consolidated. The NRC's evaluation follows each 
    argument.
        1. DHT argued that it should be given credit for identifying the 
    violations, in accordance with Section VI.B.2 of the NRC Enforcement 
    Policy (Policy).
    
    NRC Evaluation
    
        DHT correctly notes that credit may be given for identification 
    through an event. The NRC agrees that the licensee responded 
    promptly and thoroughly to the event, and that the licensee's 
    investigation was important in determining the actual circumstances 
    that resulted in the event. However, the intent of this provision is 
    to allow credit only in situations where a licensee's investigation 
    following an event uncovers violations and problems that were not 
    apparent (for example, where a licensee uncovers programmatic 
    weaknesses in procedures or training or design of equipment and 
    takes action to correct those in addition to taking action to 
    correct the direct causes of the event).
        The Policy notes that ``ease of discovery'' and ``licensee self-
    monitoring effort'' are two of the factors that will be considered. 
    In the case at hand, the NRC believes that the violations that 
    resulted in the incident were easily discovered and were not 
    identified as a result from a DHT self-monitoring effort, such as an 
    audit or a program review. The overriding Policy principle in this 
    case is to emphasize the importance of preventing events that 
    threaten the safety of employees or members of the public. After 
    considering the guidance in Section VI.B.2.b and in particular sub 
    paragraph (iv) the NRC concludes that the Licensee did not provide 
    an adequate basis for mitigating the civil penalty based on DHT's 
    identification.
        2. DHT argued that the violations do not appear to fit any of 
    the examples of Severity Level II violations in Supplement VI, and 
    that they appear to fit Example C.7 in Supplement VI (``A breakdown 
    in the control of licensed activities involving a number of 
    violations . . .''). The Licensee argued therefore that the 
    violations should have been classified at Severity Level III.
    
    [[Page 10389]]
    
    
    NRC Evaluation
    
        As noted in Section IV of the Policy, the examples in the 
    supplements are neither exhaustive nor controlling. The NRC noted in 
    the letter proposing the civil penalty that each of the violations 
    that formed the basis for the civil penalty could have been 
    classified at Severity Level III (Supplement VI, C.8) and, 
    therefore, could have been assessed separate penalties. Factoring in 
    the significance of the violations, their relationship to a single 
    event, and the involved willfulness on the part of the radiographer 
    with respect to at least one of the violations, the NRC utilized its 
    discretion to consider the violations collectively and to treat them 
    at the next highest severity level, Severity Level II.
        3. DHT argued that compliance was achieved in a major portion of 
    all three of the regulations, substantiating that the radiographer 
    had knowledge of the requirements and was not operating under a 
    total disregard for the safety requirements, but rather under a 
    potentially significant lack of attention or carelessness toward 
    licensed activities. In addition, DHT contends that the violations 
    appear to fit the criteria in Section VII.B.1.(d)(iii) for 
    enforcement discretion because the violations appeared to be an 
    isolated act of an employee without management involvement.
    
    NRC Evaluation
    
        The NRC agrees with DHT's views concerning the radiographer's 
    conduct. However, the Licensee's argument is not applicable with 
    regard to mitigation of the civil penalty. As to DHT's contention 
    that the violations appear to fit the criteria in Section 
    VII.B.1.(d)(iii), the NRC disagrees with the Licensee because 
    Section VII.B.1.(d)(iii) concerns licensee-identified Severity Level 
    IV violations, not Severity Level II violations. Moreover, a 
    radiographer, for purpose of the Enforcement Policy, is not a ``low-
    level individual.'' Therefore, enforcement discretion based on 
    Section VII.B.1. does not apply to this case.
        4. DHT cited several corrective actions which went beyond those 
    described at the predecisional enforcement conference and therefore 
    were not considered in the decision to propose a civil penalty. The 
    additional corrective actions cited by DHT included 40-hour (versus 
    8-hour) refresher training for all radiography personnel who have 
    been with the company for more than 1 year and are due for annual 
    refresher training.
    
    NRC Evaluation
    
        These corrective actions were taken by the Licensee after the 
    conference and were not factored into the decision-making process. 
    Although the NRC gave the Licensee credit for its corrective actions 
    in determining the proposed civil penalty amount, the NRC considers 
    these additional corrective actions noteworthy because they go 
    beyond what most small radiography licensees commit to and are 
    somewhat beyond our expectations, given the circumstances of this 
    case. Therefore, the NRC believes that discretion should be utilized 
    to mitigate the proposed civil penalty by $3,000.
    
    NRC Conclusion
    
        The NRC has considered all of the arguments the Licensee made 
    and concluded that the violations occurred as stated in the original 
    Notice and that they were appropriately classified as a Severity 
    Level II problem. However, given the extensive corrective actions 
    committed to by this Licensee, particularly the additional training 
    of its radiography personnel, the NRC has determined that a basis 
    exists for exercising discretion to reduce the proposed penalty by 
    $3,000. Consequently, a civil penalty in the amount of $5,000 should 
    be imposed.
    
    EVALUATION OF VIOLATIONS NOT ASSESSED A CIVIL PENALTY
    
        Of the violations not assessed a civil penalty, Diamond H 
    Testing Company (DHT or Licensee) neither admitted nor denied 
    Violations II.A and Violation II.B. However, the Licensee again 
    argued that the violations were the result of independent actions by 
    its radiographer. In addition, the Licensee questioned the validity 
    of citing 10 CFR 20.1801 with regard to Violation II.B.
    
    Restatement of Violation II.B
    
        B. 10 CFR 20.1801 requires that the licensee secure from 
    unauthorized removal or access licensed materials that are stored in 
    unrestricted areas. 10 CFR 20.1802 requires that the licensee 
    control and maintain constant surveillance of licensed material that 
    is in an unrestricted area and that is not in storage. As defined in 
    10 CFR 20.1003, unrestricted area means an area, access to which is 
    neither limited nor controlled by the licensee.
        Contrary to the above, during an 8 to 10 minute period between 
    approximately 9:45 p.m. and 10:00 p.m. on June 14, 1995, the 
    licensee did not secure from unauthorized removal or limit access to 
    a 48.2 curie iridium-192 sealed source in a Gamma Century exposure 
    device located on the 9th floor of the Hawaiian Electric Company 
    Kahe Unit 5 Power Plant, an unrestricted area, nor did the licensee 
    control and maintain constant surveillance of this licensed 
    material. (03014)
        This is a Severity Level IV violation (Supplement IV).
    
    Summary of Licensee's Response to Violation II.B
    
        The Licensee questioned the validity of including 10 CFR 20.1801 
    as applying to the circumstances in question. The Licensee stated 
    that ``It [the exposure device] had been left for a period of 8 to 
    10 minutes when the radiographer went to notify the RSO [radiation 
    safety officer] of the situation.'' DHT's position is that 10 CFR 
    20.1801, which was cited in conjunction with 10 CFR 20.1802, should 
    not apply because the radiography camera was not ``stored'' at the 
    field site location.
    
    NRC Evaluation of Licensee's Response
    
        The Licensee admits that the camera was left in an unrestricted 
    area and neither secured the material from unauthorized removal nor 
    maintained constant surveillance of the licensed material. 
    Therefore, while the NRC agrees with DHT that 10 CFR 20.1801 may not 
    have applied, the NRC concludes that Licensee failed to comply with 
    these requirements.
    
    NRC Conclusion
    
        Based on the above, the NRC concludes that the licensee has not 
    provided an adequate basis for withdrawal of the Violation II.B. 
    Therefore, the Violation II.B occurred as stated in the Notice.
    
    [FR Doc. 96-5993 Filed 3-12-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
03/13/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
96-5993
Pages:
10387-10389 (3 pages)
Docket Numbers:
Docket No. 030-32202, License No. 11-27316-01, EA 95-148
PDF File:
96-5993.pdf