98-6524. Independence Pipeline Company, ANR Pipeline Company, National Fuel Gas Supply Corporation; Notice of Intent To Prepare an Environmental Impact Statement for the Proposed Independence Pipeline Project, Request for Comments on Environmental ...  

  • [Federal Register Volume 63, Number 49 (Friday, March 13, 1998)]
    [Notices]
    [Pages 12459-12463]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-6524]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP97-315-001, CP97-319-000, CP98-200-000]
    
    
    Independence Pipeline Company, ANR Pipeline Company, National 
    Fuel Gas Supply Corporation; Notice of Intent To Prepare an 
    Environmental Impact Statement for the Proposed Independence Pipeline 
    Project, Request for Comments on Environmental Issues, and Notice of 
    Public Scoping Meetings and Site Visit
    
    March 9, 1998.
        The staff of the Federal Energy Regulatory Commission (FERC or 
    Commission) will prepare an
    
    [[Page 12460]]
    
    Environmental Impact Statement (EIS) that will discuss the 
    environmental impacts of the construction and operation of 
    approximately 473 miles of natural gas transmission pipeline, three new 
    and three modified compressor stations, metering and delivering 
    facilities, other appurtenant facilities, and abandonment of 
    approximately 39 miles of pipeline proposed in the Independence 
    Pipeline Project.\1\ This EIS will be used by the Commission in its 
    decision-making process to determine whether the project is in the 
    public convenience and necessity.
    ---------------------------------------------------------------------------
    
        \1\ Independence Pipeline Company, ANR Pipeline Company, and 
    National Fuel Gas Supply Corporation's applications were filed with 
    the Commission under Section 7 of the Natural Gas Act and Part 157 
    of the Commission's regulations.
    ---------------------------------------------------------------------------
    
        If you are a landowner whose property will be crossed by the 
    proposed project, you may be contacted by a pipeline company 
    representative about the acquisition of an easement to construct, 
    operate, and maintain the proposed facilities. The pipeline company may 
    seek to negotiate a mutually acceptable agreement relative to land use 
    and access. However, if the project is approved by the Commission, the 
    pipeline has the right to us eminent domain. Therefore, if negotiations 
    fail to produce an agreement between the pipeline company and 
    landowner, the pipeline company could initiate condemnation proceedings 
    in accordance with state law. A fact sheet addressing a number of 
    typically asked questions, including the use of eminent domain, is 
    attached to this notice as appendix 1.
    
    Summary of the Proposed Project
    
        Independence Pipeline Company (Independence) wants to build new 
    natural gas pipeline transmission facilities in Ohio and Pennsylvania. 
    The facilities would provide transportation services to shippers 
    seeking to transport natural gas principally from expansion projects 
    destined for the Chicago, Illinois area to the Leidy, Pennsylvania Hub, 
    thereby facilitating access to gas markets in Ohio, Pennsylvania, and 
    throughout the Eastern United States. The proposed facilities would 
    have a summer design delivery capacity of 916.3 thousand cubic feet per 
    day (Mcf/d) and a winter design delivery capacity of 1.0 million cubic 
    feet per day (MMcf/d). Independence requests Commission authorization, 
    in Docket Nos. CP97-315-000, CP97-315-001, CP97-320-000, and CP97-321-
    000 to construct and operate the following facilities:
         400.4 miles of 36-inch-diameter pipeline in Defiance, 
    Henry, Wood, Seneca, Huron, Ashland, Wayne, Stark, Summit, and 
    Columbian Counties, Ohio, and Lawrence, Butler, Armstrong, Clarion, 
    Jefferson, Elk, Forest, McLean, Cameron, Potter, and Clinton Counties, 
    Pennsylvania. Of the 400.4 miles of pipeline, about 220.9 miles would 
    be in Ohio and 179.5 miles would be in Pennsylvania.
         Three new compressor stations with a total of 60,000 
    horsepower (hp) of compression:
    
    --East Defiance Compression Station (30,000 hp) in Defiance County, 
    Ohio.
    --Cannan Compression Station (15,000 hp) in Wayne County, Ohio.
    --Porter Compression Station (15,000 hp) in Clarion County, 
    Pennsylvania.
    
         One pig launcher and receiver located at the proposed 
    Canaan and Porter Compressor Stations.
         Three new meter stations located in Defiance County, Ohio, 
    and Elk and Clinton Counties, Pennsylvania.
         Other associated aboveground facilities, including six 
    taps in Wood (1), Ashland (1), Wayne (2), and Columbiana (1) Counties, 
    Ohio and Lawrence County, Pennsylvania (1).
         A total of 28 mainline block valves, 16 located in the 
    following counties in Ohio: Defiance (1), Henry (1), Wood (2), Seneca 
    (2), Huron (2), Ashland (1), Wayne (2), Summit (1), Stark (2), and 
    Columbiana (2); and 12 located in the following counties in 
    Pennsylvania: Lawrence (2), Butler (1), Armstrong (1), Clarion (1), 
    Jefferson (2), Elk (1), McKean (1), Cameron (1), Potter (1) and Clinton 
    (1).
        ANR Pipeline Company (ANR) wants to expand its existing Michigan 
    Leg South and Tieline facilities to provide incremental transportation 
    between Joliet, Illinois and Defiance, Ohio. This would allow ANR's 
    existing Northern Zone to become an economical link between the Chicago 
    Hub and Independence's proposed pipeline facilities. ANR's proposed 
    facilities would have a design delivery capacity of 750 MMcf/d. ANR 
    requests Commission authorization, in Docket No. CP97-319-000, to 
    construct and operate the following facilities:
         72.4 miles of 42- and 30-inch-diameter pipeline loop 
    extending from Joliet, Illinois to Defiance, Ohio:
    
    --Joliet Loop--15.9 miles of 42-inch-diameter pipeline in Kendall and 
    Will Counties, Illinois.
    --St. John West Loop--5.5 miles of 42-inch-diameter pipeline in Will 
    County Illinois and Lake County, Indiana.
    --St. John East Loop--20.9 miles of 42-inch-diameter pipeline in Lake 
    and Porter Counties, Indiana.
    --Bridgman Loop--16.0 miles of 30-inch-diameter pipeline in Berrien 
    County, Michigan.
    --Defiance Loop--14.1 miles of 30-inch-diameter pipeline in Defiance 
    County, Ohio.
    
         15,000 hp additional compression at the existing Bridgman 
    Compressor Station in Berrien County, Michigan, and Modifications not 
    involving compression change at the existing Lagrange Compressor 
    Station in Lagrange County, Indiana and Defiance Compressor Station in 
    Defiance County, Ohio.
         Associated aboveground facilities, including the 
    installation of pig receivers at the St. John and Defiance Compressor 
    Stations, and at the end of the Bridgman Loop facilities in Berrien 
    County, Michigan. Also, new pig launchers would be installed at the St. 
    John and Bridgman Compressor Stations, at the beginning of the Joliet 
    Loop in Kendall County, Illinois, and on the Defiance Loop in Defiance 
    County, Ohio.
        National Fuel Gas Supply Corporation (National Fuel) wants to 
    abandon, primarily by removal, three contiguous sections of its 
    existing natural gas pipeline facilities in Pennsylvania to facilitate 
    construction of Independence's proposed pipeline in that area. National 
    Fuel would also make minor changes to its remaining facilities in that 
    area to maintain service to existing customers. National Fuel requests 
    Commission authorization, in Docket No. CP98-200-000, to:
         Abandon by removal 13.3 miles of its 12-inch-diameter Line 
    K, from Eshbaugh to Eldred in Clarion and Jefferson Counties, 
    Pennsylvania.
         Abandon by removal 8.6 miles of its 12-inch-diameter Line 
    C and 22-inch-diameter Line K-197, from Eldred to Overbeck in Jefferson 
    County, Pennsylvania.
         Abandon by removal 17.4 miles of its 12-inch-diameter Line 
    C and 22-inch-diameter Line K-197, from Overbeck to Lamont in 
    Jefferson, Elk and Forest, Counties, Pennsylvania.
         Relocate taps, regulator stations, and inlet piping from 
    Line C to Line K, and install gas heaters and pipeline jumpers, in 
    Jefferson and Elk Counties, Pennsylvania.
         Perform an automation upgrade at its existing Knox 
    Compressor Station in Jefferson County, Pennsylvania.
        A general location map of the project facilities is shown in 
    appendix 2.
    
    Land Requirements for Construction
    
        Construction of Independence's proposed facilities would affect a 
    total of about 3,702 acres. Of this total, about
    
    [[Page 12461]]
    
    3,640 acres would be disturbed by construction of the pipeline. The 
    remaining 62 acres would be disturbed by construction and operation of 
    the three compressor stations and two meter stations. Mainline valves 
    would be built within or adjacent to Independence's permanent right-of-
    way. Extra work areas would be needed for pipe installation at roads, 
    railroads, waterbody and wetland crossings, additional topsoil storage, 
    pipe and equipment yards, and access roads. Approximately 209.7 miles 
    (52 percent) of the new pipeline would be installed adjacent to or 
    within existing rights-of-way. Independence would generally use a 75- 
    to 100-foot-wide construction right-of-way. Following construction and 
    restoration of the right-of-way and temporary work spaces, Independence 
    would retain a 50-foot-wide permanent pipeline right-of-way. Existing 
    land uses on the remainder of the disturbed areas, as well as most land 
    uses on the permanent right-of-way, would be allowed to continue 
    following construction. Total land requirements for the permanent 
    right-of-way would be about 2,426 acres.
        Construciton of ANR's proposed facilities would affect a total of 
    about 1,222 acres. Of this total, about 1,124 acres would be disturbed 
    by construction of the pipeline loops. The remaining 98 acres would be 
    disturbed by extra work areas, contractor yards, and access roads. 
    Approximately 63.7 miles (88 percent) of the new pipelines loops would 
    be installed adjacent and parallel to the existing mainline. ANR would 
    deviate from existing mainline in several locations to avoid 
    environmental or engineering constraints. Construction of the pipeline 
    loops would require a 75- to 145-foot-wide construction right-of-way. 
    ANR would retain a 35- to 50-foot-wide permanent pipeline right-of-way. 
    Existing land uses on the remainder of the disturbed areas, as well as 
    most land uses on the permanent right-of-way, would be allowed to 
    continue following construction. Total land requirements for the 
    permanent right-of-way would be about 291 acres.
        Removal of National Fuel's Lines K, C, and K-197, and modifications 
    to its existing taps and regulator stations would be entirely within 
    National Fuel's existing rights-of-way, and entirely within the 
    construction work areas that would be affected by construction of the 
    Independence Pipeline. National Fuel's proposed facilities would affect 
    a total of about 319 acres.
    
    The EIS Process
    
        The National Environmental Policy Act (NEPA) requires the 
    Commission to take into account the environmental impacts that could 
    result from an action whenever it considers the issuance of a 
    Certificate of Public Convenience and Necessity. The EIS we are 
    preparing will give the Commission the information to do that. NEPA 
    also requires us to discover and address concerns the public may have 
    about the proposals. We call this ``scoping''. The main goal of the 
    scoping process is to focus the analysis in the EIS on the important 
    environmental issues. By this Notice of Intent, the Commission requests 
    public comments on the scope of the issues it will address in the EIS. 
    All comments received are considered during the preparation of the EIS. 
    We encourage state and local government representatives to notify their 
    constituents of this proposed action and encourage them to comment on 
    their areas of concern. Local agencies are requested to provide 
    information on other projects, either ongoing or planned, which might 
    conflict with, or have cumulative effects when considered in 
    combination with, the Independence Pipeline Project.
        To ensure your comments are considered, please carefully follow the 
    instructions in the public participation section on pages 8 and 9 of 
    this Notice.
    
    Currently Identified Environmental Issues
    
        We have identified a number of issues based upon our preliminary 
    review of the proposed facilities, the environmental information 
    provided by Independence, ANR, National Fuel, and interested parties. 
    Some of these issues are listed below. Keep in mind that this is a 
    preliminary list, and is not a complete list of site-specific issues. 
    We may add to, subtract from, or change the list of issues based on 
    your comments and our analysis.
         Geology and Soils:
    
    --Temporary and permanent impact on prime farmland soils.
    --Mixing of topsoil and subsoil during construction.
    --Crossing of agricultural drainage systems.
    --Compaction of soil by heavy equipment.
    --Crossing of reclaimed and operating strip mines and abandoned deep 
    coal mines.
    --Crossing of East Ohio Gas Company Storage Fields.
    --Effect of blasting during trench excavation.
    --Erosion control and restoration of the right-of-way.
    
         Water Resources:
    
    --Crossing of 786 perennial and intermittent waterbodies.
    --Crossing of 7 perennial waterbodies over 100 feet wide, including Des 
    Plain, St. Joseph, Dowagiac, Allegheny, and Clarion Rivers, and 
    Slippery Rock and Kettle Creeks.
    --Effect on water supplies, including 57 private wells within 150 feet 
    of the construction work area.
    --Potentially contaminated sediments at waterbody crossings, including 
    Middle Fork of Little Beaver Creek in Columbiana County, Ohio.
    
         Vegetation and Wildlife:
    
    --Crossing of 135 acres of wetlands (totaling 13.7 miles).
    --Clearing of about 1,290 acres of forest (totaling 169.6 miles) and 
    removal of stumps, timber, and slash.
    --Effect of construction on wildlife and fisheries habitat.
    --Effect on federally listed endangered and threatened species, 
    including bald eagle, Indiana bat, copper-belly watersnake, clubshell 
    mussel, northern riffleshell mussel, northern monkshood, purple cats 
    paw, and eastern prairie fringed orchid.
    
         Cultural Resources:
    
    --Impact on historic and prehistoric sites.
    --Native American and tribal concerns.
    
         Land Use:
    
    --Use of eminent domain to acquire rights-of-way.
    --Impact on crop production.
    --Proximity to schools and residential developments.
    --Effect on 45 residences within 50 feet of the construction work area.
    --Crossings of septic fields and drains.
    --Effect on local roads.
    --Crossing of scenic highways, including State Routes 424 and 65 in 
    Ohio.
    --Effect on Canton-Akron regional airport, Summit County, Ohio, and 
    Willard Airport, Huron County, Ohio.
    --Control of unauthorized access to rights-of-way.
    
         Recreation and Public Interest Areas:
    
    --Crossing of hiking trails, including the North Country National Trail 
    System in Ohio and Pennsylvania, and the Buckeye Trail in Ohio.
    --Crossing of the Allegheny National Forest in Pennsylvania.
    --Crossing of the Allegheny National Forest in Pennsylvania.
    --Crossing of Illinois and Michigan Canal in Illinois; Independence Dam 
    State Park in Ohio; Clear Creek, McConnell' Mill, and Elk State Parks 
    in Pennsylvania; and Elk, Sproul, and
    
    [[Page 12462]]
    
    Susquehannock State Forests in Pennsylvania.
    --Crossing of Channahon Community Park in Illinois, Plum Grove Reserve 
    in Illinois/Indiana, Deep River County Park in Indiana, and F.H. 
    Dutlinger Preserve in Pennsylvania.
    --Crossing of one river included on the National Wild and Scenic River 
    System (Little Beaver Creek, in Columbiana County, Ohio).
    --Crossing of state designated or proposed wild, scenic, and 
    recreational rivers, including Maumee and Sandusky Rivers in Ohio, and 
    Allegheny and Clarion Rivers and Slippery Rock and Kettle Creeks in 
    Pennsylvania.
    
         Socioeconomics:
    
    --Impact on property values.
    --Effect of construction workforce on demands for services in 
    surrounding areas.
    
         Air Quality and Noise:
    
    --Impact on local air quality during construction, and regional air 
    quality during operation, of pipelines and compressor stations.
    --Noise impact on nearby areas from construction and operation of 
    pipelines and compressor stations.
    
         Reliability and Safety:
    
    --Assessment of hazards associated with national gas pipelines, 
    including placement in vicinity of schools and residential 
    developments.
    
         Cumulative Impact:
    
    --Assessment of the combined effect of the proposed project with other 
    projects which have been or may be proposed in the same region and 
    similar time frame.
    
        We will also evaluate possible alternatives to the proposed project 
    or portions of the project, and make recommendations on how to lessen 
    or avoid impacts on the various resource areas. A number of 
    alternatives have been identified to date, both in filings made by the 
    applicants and in comments received. We will evaluate all feasible 
    alternatives identified.
        Our independent analysis of the issues will be in a Draft EIS which 
    will be mailed to Federal, state, and local agencies, public interest 
    groups, interested individuals, affected landowners, newspapers, 
    libraries, and the Commission's official service list for these 
    proceedings. A 45-day comment period will be allotted for review of the 
    Draft EIS. We will consider all comments on the Draft EIS and revise 
    the document, as necessary, before issuing a Final EIS. The Final EIS 
    will treat all comments received on the Draft EIS.
    
    Public Participation and Scoping Meetings
    
        You can make a difference by your specific comments or concerns 
    about the project. By becoming a commentor, your concerns will be 
    addressed in the EIS and considered by the Commission. You should focus 
    on the potential environmental effects of the proposal, alternatives to 
    the proposal (including alternative routes or compressor station 
    sties), and measures to avoid or lessen environmental impact. The more 
    specific your comments, the more useful they will be. Please follow the 
    instructions below to ensure that your comments are received and 
    properly recorded:
         Reference Docket Nos. CP97-315-001, CP97-319-000. and 
    CP98-200-000.
         Send two copies of your comments to: David P. Boergers, 
    Acting Secretary, Federal Energy Regulatory Commission, 888 First St., 
    NE., Washington, DC 20426;
         Label one copy for the attention of the Environmental 
    Review and Compliance Branch, PR-11.1.
         Please mail your comments so that they will be received in 
    Washington, DC on or before April 29, 1998.
        In addition to or in lieu of sending written comments, you are 
    invited to attend one or more of the six public scoping meetings being 
    held in the project area. An additional meeting(s) may be held in July 
    or August. Meetings will be held at the following times and locations:
    
    ----------------------------------------------------------------------------------------------------------------
                 Date                          Time                                   Location                      
    ----------------------------------------------------------------------------------------------------------------
    Tuesday, April 7, 1998........  7:00 p.m..................  Joliet Central High School, Little Theatre, Corner  
                                                                 of Van Buren and Herkimer, (815) 727-6743, Joliet, 
                                                                 Illinois 60432.                                    
    Wednesday, April 8, 1998......  7:00 p.m..................  Buchanan High School Auditorium, 401 W. Chicago,    
                                                                 (616) 695-8403, Buchanan, Michigan 49107.          
    Monday, April 20, 1998........  7:00 p.m..................  Tiffin Columbian High School Auditorium, 300 South  
                                                                 Monroe Street, (419) 447-6331, Tiffin, Ohio 44883. 
    Tuesday, April 21, 1998.......  7:00 p.m..................  Hoover High School, Hoover Hall, 525 Seventh Street,
                                                                 NE, (330) 497-5600, North Canton, Ohio 44720.      
    Wednesday, April 22, 1998.....  7:00 p.m..................  Butler Intermediate High School Auditorium, 551     
                                                                 Fairground Hill Road, (724) 287-8721, Butler,      
                                                                 Pennsylvania 16001.                                
    Thursday, April 23, 1998......  7:00 p.m..................  Royal Inn, US Route 219 Boot Jack Road, (814) 773-  
                                                                 3153, Ridgeway, Pennsylvania 15853.                
    ----------------------------------------------------------------------------------------------------------------
    
        The purpose of the scoping meetings is to obtain input from state 
    and local governments and from the public. Federal agencies have formal 
    channels for input into the Federal process (including separate meeting 
    where appropriate). Federal agencies are expected to file their written 
    comments directly with the FERC and not use the scoping meetings for 
    this purpose.
        Independence, ANR, and National Fuel will be invited to present a 
    description of their proposals. Interested groups and individuals are 
    encouraged to attend the meetings and present oral comments on the 
    environmental issues which they believe should be addressed in the 
    Draft EIS. A transcript will be made of the meetings and will be made 
    part of the Commission's record in this proceeding. Written comments 
    and oral comments will be treated equally in our review.
        We are asking a number of Federal agencies to indicate whether they 
    wish to cooperate with us in the preparation of the EIS. These agencies 
    may choose to participate once they have evaluated each proposal 
    relative to their agencies' responsibilities. The list of agencies is 
    provided in appendix 3.\2\
    ---------------------------------------------------------------------------
    
        \2\ The appendices referenced in this notice are not being 
    printed in the Federal Register. Copies are available from the 
    Commission's Public Reference and Files Maintenance Branch, 888 
    First Street, NE., Washington, DC 20426, Room 2A or call (202) 208-
    1371. Copies of the appendices were sent to all those receiving this 
    notice in the mail.
    ---------------------------------------------------------------------------
    
        On the above dates we will also be conducting limited site visits 
    to the project area in the vicinity of each scoping meeting location. 
    Anyone interested in participating in the site visit may contact the 
    Commission's Office of External Affairs, identified at
    
    [[Page 12463]]
    
    the end of this notice, for more details and must provide their own 
    transportation.
    
    Becoming an Intervenor
    
        In addition to involvement in the EIS scoping process, you may want 
    to become an official party to the proceeding, known as an 
    ``intervenor''. Intervenors play a more formal role in the process. 
    Among other things, intervenors have the right to receive copies of 
    case-related Commission documents and filings by other intervenors. 
    Likewise, each intervenor must provide 14 copies of its filings to the 
    Secretary of the Commission and must send a copy to all other parties 
    on the Commission's service lists for these proceedings. If you want to 
    become an intervenor you must file a Motion to Intervene according to 
    Rule 214 of the Commission's Rules of Practice and Procedure (18 CFR 
    385.214) (see appendix 4). Only intervenors have the right to seek 
    rehearing of the Commission's decision.
        The date for filing timely motions to intervene in this proceeding 
    has passed, having ended February 23, 1998. Therefore, parties now 
    seeking to file late interventions must show good cause, as required by 
    section 385.214(b)(3), why this time limitation should be waived. 
    Environmental issues have been viewed as good cause for late 
    intervention. However, you do not need intervenor status to have your 
    comments considered.
    
    Environmental Mailing List
    
        Anyone offering scoping comments will be automatically kept on our 
    environmental mailing list for the project. If you do not want to offer 
    comments at this time but still want to keep informed and receive 
    copies of the Draft and Final EISs, please return the Environmental 
    Mailing List Information (appendix 5). If you do not return the card 
    you will be taken off the mailing list.
        Additional information about the proposed project is available from 
    Paul McKee in the Commission's Office of External Affairs at (202) 208-
    1088.
    David P. Boergers,
    Acting Secretary.
    [FR Doc. 98-6524 Filed 3-12-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
03/13/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-6524
Pages:
12459-12463 (5 pages)
Docket Numbers:
Docket No. CP97-315-001, CP97-319-000, CP98-200-000
PDF File:
98-6524.pdf