95-6280. Notice of Intent To Prepare an Environmental Assessment (EA) and Notice To Scoping Meetings, and, if Determined To Be Necessary, Prepare an Environmental Impact Statement (EIS) on a Proposed Replacement Raw Water Pipeline in Mesa County, CO  

  • [Federal Register Volume 60, Number 49 (Tuesday, March 14, 1995)]
    [Notices]
    [Page 13730]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-6280]
    
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    DEPARTMENT OF THE INTERIOR
    
    Bureau of Land Management
    [CO-070-5101-CO12]
    
    
    Notice of Intent To Prepare an Environmental Assessment (EA) and 
    Notice To Scoping Meetings, and, if Determined To Be Necessary, Prepare 
    an Environmental Impact Statement (EIS) on a Proposed Replacement Raw 
    Water Pipeline in Mesa County, CO
    
    AGENCY: Bureau of Land Management, Interior.
    
    ACTION: Notice of Intent to Prepare an Environmental Assessment (EA), 
    and Notice to Scoping Meetings, and, if determined to be necessary, 
    prepare an Environmental Impact Statement (EIS) on a Proposed 
    Replacement Raw Water Pipeline in Western Colorado.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Pursuant to section 102(2)(C) of the National Environmental 
    Policy Act of 1969 (NEPA), the Grand Junction Resource Area Office, 
    Grand Junction District, will be directing the preparation of a NEPA 
    document. The NEPA document will be initiated as an EA, with the 
    understanding that it may be upgraded to an EIS. The document will be 
    prepared by a third party contractor, and will address impacts of the 
    Plateau Creek Pipeline Replacement project proposed by the Ute Water 
    Conservancy District (Ute Water). The project is a raw water conveyance 
    system proposed on private and public lands in Mesa County, Colorado to 
    replace a deteriorated and under sized pipeline currently approved 
    under BLM ROW grant C 081282.
    
    DATES: Written comments will be accepted until 4:00 p.m., MST, on April 
    13, 1995. A public scoping meeting will be held at 7:00 p.m. on March 
    29, 1995, at the Two Rivers Convention Center, 159 Main Street, Grand 
    Junction, Colorado.
    
    ADDRESSES: Comments should be sent to the Grand Junction Area Manager, 
    Bureau of Land Management, 2815 H Road, Grand Junction, CO 81506, ATTN: 
    Plateau Creek Pipeline Replacement Project.
    
    FOR FURTHER INFORMATION CONTACT:
    Dave Stevens, (303) 244-3009.
    
    SUPPLEMENTARY INFORMATION: The existing Plateau Creek Pipeline is an 
    essential part of the Ute Water system which provides water to more 
    than 55,000 Grand Valley residents. The Ute Water service area includes 
    most of the Grand Valley area surrounding the City of Grand Junction, 
    Colorado, and extends from east of the Town of Palisade to within 5 
    miles of the Colorado-Utah stateline. Ute Water is a political 
    subdivision of the State of Colorado formed under the Water Conservancy 
    Act of 1937, and is considered to be a quasi-municipal entity.
        The existing prestressed concrete pipe was installed in the early 
    1960s. A pipeline consisting of 42-inch and 36-inch diameter pipe 
    carries raw water for approximately 4.5 miles from the Lower Molina 
    Power Plant tail race to two storage reservoirs. From the reservoirs, 
    water is conveyed via a 24-inch-diameter pipeline approximately 14 
    miles along Plateau Creek Canyon and adjacent to Interstate Highway 70 
    to Ute Water's treatment plant located on Rapid Creek, near the Town of 
    Palisade. As of 1994, the pipeline was no longer able to provide an 
    adequate flow rate to meet the peak day customer demands. The pipeline 
    is presently subject to frequent breaks due to deteriorated pipe 
    condition, and is unreliable due to its location within geologic 
    hazards and stream erosion areas. In order for Ute Water to meet its 
    commitment of providing a reliable, cost effective, high quality water 
    source, replacement of the pipeline is necessary. The pipeline size and 
    capacity will be determined from independent water demand projections 
    based on population estimates to be generated and documented as part of 
    this effort.
        Ute Water has preliminary scoping to: (1) identify interested 
    stakeholders and agencies, (2) define key issues, and (3) identify 
    initial alternatives. On the basis of the preliminary scoping, 16 
    alternatives were developed. These include seven alternatives along the 
    Plateau Creek corridor, three different alternatives involving use of 
    water from nearby utilities, a Colorado River pump station alternative, 
    two alternatives for supplying water from the Kannah Creek watershed, 
    two alternatives for supplying water from the Whitewater Creek 
    watershed, and a No Action alternative. Groundwater alternatives and 
    conservation actions will be addressed in the EA. Four of the initially 
    considered alternatives, selected on the basis of screening criteria 
    described in Section 404(b) of the Clean Water Act, are proposed for 
    evaluation in the EA. These are:
        Alternative A--Replacement of the pipeline on an alignment parallel 
    to Plateau Creek such that impacts to all resources are minimized.
        Alternative B--Replacement of the pipeline parallel to Plateau 
    Creek entirely within the existing state highway 65 and 330 rights-of-
    way.
        Alternative C--Replacement of the pipeline in either alignment A or 
    B with a smaller pipeline. This alternative includes provisions for 
    construction of a booster station at the mouth of Plateau Canyon to be 
    built at a future date to meet long-term demands.
        Alternative D--A ``no federal action'' alternative.
        Major issues identified during the preliminary scoping include: (1) 
    wetlands and riparian areas, (2) threatened and endangered species, (3) 
    wildlife habitat, (4) need for demand projections, and (5) water 
    depletion issues. Preliminary review by the Bureau of Land Management 
    (BLM), Fish and Wildlife Service (FWS), and Army Corps of Engineers 
    (ACOE) indicates that the anticipated impacts may be entirely 
    mitigable, and may be limited to temporary disturbance. However, there 
    is a potential that significant impacts may be identified during the EA 
    process and it may be necessary to convert this documentation effort 
    into an EIS. Therefore, it is also the intent of this NOI to provide 
    for public notice and review necessary for an EIS pursuant to NEPA.
        The tentative project schedule is:
    
    Begin Public Comment Period--March 1995
    Complete Final EA--January 1996
    EA Finding--March 1996
    Complete Final Design--January 1997
    Begin Construction--March 1997
    
        The BLM's scoping process will include: (1) Identification of 
    additional issues to be addressed; (2) Identification of additional 
    viable alternatives, and (3) Notification of interested groups, 
    individuals and agencies so that additional information concerning 
    these issues can be obtained.
        The scoping process will be initiated by publication of this NOI in 
    the Federal Register and issuance of a news release announcing the 
    start of the process; letters of invitation to participate in the 
    scoping process, and distribution of a scoping document describing the 
    proposed action, alternatives and significant issues being considered 
    is available upon request.
    Mark T. Morse,
    District Manager.
    [FR Doc. 95-6280 Filed 3-13-95; 8:45 am]
    BILLING CODE 4310-JB-M
    
    

Document Information

Published:
03/14/1995
Department:
Land Management Bureau
Entry Type:
Notice
Action:
Notice of Intent to Prepare an Environmental Assessment (EA), and Notice to Scoping Meetings, and, if determined to be necessary, prepare an Environmental Impact Statement (EIS) on a Proposed Replacement Raw Water Pipeline in Western Colorado.
Document Number:
95-6280
Dates:
Written comments will be accepted until 4:00 p.m., MST, on April 13, 1995. A public scoping meeting will be held at 7:00 p.m. on March 29, 1995, at the Two Rivers Convention Center, 159 Main Street, Grand Junction, Colorado.
Pages:
13730-13730 (1 pages)
Docket Numbers:
CO-070-5101-CO12
PDF File:
95-6280.pdf