2021-05708. Florida Gas Transmission Company, LLC; Notice of Scoping Period Requesting Comments On Environmental Issues for The Proposed Big Bend Project  

  • Start Preamble Start Printed Page 14902

    The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental document that will discuss the environmental impacts of the Big Bend Project involving construction and operation of facilities by Florida Gas Transmission Company, LLC (FGT) in Calhoun, Jefferson, Gadsden, Gilchrist, Santa Rosa, and Taylor Counties, Florida. The Commission will use this environmental document in its decision-making process to determine whether the project is in the public convenience and necessity.

    This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies regarding the project. As part of the National Environmental Policy Act (NEPA) review process, the Commission takes into account concerns the public may have about proposals and the environmental impacts that could result from its action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. This gathering of public input is referred to as “scoping.” The main goal of the scoping process is to focus the analysis in the environmental document on the important environmental issues. Additional information about the Commission's NEPA process is described below in the NEPA Process and Environmental Document section of this notice.

    By this notice, the Commission requests public comments on the scope of issues to address in the environmental document. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC on or before 5:00 p.m. Eastern Time on April 14, 2021. Comments may be submitted in written form. Further details on how to submit comments are provided in the Public Participation section of this notice.

    Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the environmental document. Commission staff will consider all written comments during the preparation of the environmental document.

    If you submitted comments on this project to the Commission before the opening of this docket on January 29, 2021, you will need to file those comments in Docket No. CP21-45-000 to ensure they are considered as part of this proceeding.

    This notice is being sent to the Commission's current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern.

    If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable easement agreement. You are not required to enter into an agreement. However, if the Commission approves the project, the Natural Gas Act conveys the right of eminent domain to the company. Therefore, if you and the company do not reach an easement agreement, the pipeline company could initiate condemnation proceedings in court. In such instances, compensation would be determined by a judge in accordance with state law. The Commission does not subsequently grant, exercise, or oversee the exercise of that eminent domain authority. The courts have exclusive authority to handle eminent domain cases; the Commission has no jurisdiction over these matters.

    FGT provided landowners with a fact sheet prepared by the FERC entitled “An Interstate Natural Gas Facility On My Land? What Do I Need To Know?” which addresses typically asked questions, including the use of eminent domain and how to participate in the Commission's proceedings. This fact sheet along with other landowner topics of interest are available for viewing on the FERC website (www.ferc.gov) under the Natural Gas Questions or Landowner Topics link.

    Public Participation

    There are three methods you can use to submit your comments to the Commission. Please carefully follow these instructions so that your comments are properly recorded. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208-3676 or FercOnlineSupport@ferc.gov.

    (1) You can file your comments electronically using the eComment feature, which is located on the Commission's website (www.ferc.gov) under the link to FERC Online. Using eComment is an easy method for submitting brief, text-only comments on a project;

    (2) You can file your comments electronically by using the eFiling feature, which is located on the Commission's website (www.ferc.gov) under the link to FERC Online. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; a comment on a particular project is considered a “Comment on a Filing”; or

    (3) You can file a paper copy of your comments by mailing them to the Commission. Be sure to reference the project docket number (CP21-45-000) on your letter. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.

    Additionally, the Commission offers a free service called eSubscription which makes it easy to stay informed of all issuances and submittals regarding the dockets/projects to which you subscribe. These instant email notifications are the fastest way to receive notification and provide a link to the document files which can reduce the amount of time you spend researching proceedings. Go to https://www.ferc.gov/​ferc-online/​overview to register for eSubscription.

    Summary of the Proposed Project

    FGT proposes to construct and operate the Big Bend Project to provide about 29 million standard cubic feet of natural gas per day to serve the need for additional firm transportation service in Hillsborough and Pinellas Counties, Florida for current and future electricity generation. The project facilities would consist of:

    • West Loop: Approximately 1.7 miles of 36-inch-diameter pipeline Start Printed Page 14903loop [1] extension in Calhoun County, Florida;
    • East Loop: Approximately 1.5 miles of 36-inch-diameter pipeline loop extension in Jefferson County, Florida;
    • relocation of associated pig receiver stations in Calhoun and Jefferson Counties, Florida; and
    • upgrade existing natural gas-fired compressor turbines at four existing compressor stations:
    • Compressor Station 12—upgrade Unit 1207 from 15,000 horsepower (HP) to 16,000 HP in Santa Rosa County, Florida;
    • Compressor Station 14—upgrade Unit 1409 from 20,500 HP to 23,500 HP in Gadsden County, Florida;
    • Compressor Station 15—upgrade Unit 1507 from 15,000 HP to 16,000 HP in Taylor County, Florida; and
    • Compressor Station 24—upgrade Unit 2403 from 20,500 HP to 23,500 HP in Gilchrist County, Florida.

    The general location of the project facilities is shown in appendix 1.[2]

    Land Requirements for Construction

    Construction of the proposed facilities would disturb about 269.3 acres of land for the aboveground facilities and the pipeline. Following construction, FGT would maintain about 210.4 acres for permanent operation of the project's facilities; the remaining acreage would be restored and revert to former uses. All of the proposed pipeline route parallels existing pipeline, utility, or road rights-of-way. The modifications at Compressor Stations 12, 14, 15 and 24 would occur within the existing station boundaries without the need for ground disturbance.

    NEPA Process and the Environmental Document

    Any environmental document issued by the Commission will discuss impacts that could occur as a result of the construction and operation of the proposed project under the relevant general resource areas:

    • Geology and soils;
    • water resources and wetlands;
    • vegetation and wildlife;
    • threatened and endangered species;
    • cultural resources;
    • land use;
    • air quality and noise; and
    • reliability and safety.

    Commission staff will also evaluate reasonable alternatives to the proposed project or portions of the project and make recommendations on how to lessen or avoid impacts on the various resource areas. Your comments will help Commission staff identify and focus on the issues that might have an effect on the human environment and potentially eliminate others from further study and discussion in the environmental document.

    Following this scoping period, Commission staff will determine whether to prepare an Environmental Assessment (EA) or an Environmental Impact Statement (EIS). The EA or the EIS will present Commission staff's independent analysis of the issues. If Commission staff prepares an EA, a Notice of Schedule for the Preparation of an Environmental Assessment will be issued. The EA may be issued for an allotted public comment period. The Commission would consider timely comments on the EA before making its decision regarding the proposed project. If Commission staff prepares an EIS, a Notice of Intent to Prepare an EIS/Notice of Schedule will be issued, which will open up an additional comment period. Staff will then prepare a draft EIS which will be issued for public comment. Commission staff will consider all timely comments received during the comment period on the draft EIS and revise the document, as necessary, before issuing a final EIS. Any EA or draft and final EIS will be available in electronic format in the public record through eLibrary [3] and the Commission's natural gas environmental documents web page (https://www.ferc.gov/​industries-data/​natural-gas/​environment/​environmental-documents). If eSubscribed, you will receive instant email notification when the environmental document is issued.

    With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the environmental document.[4] Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice.

    Consultation Under Section 106 of the National Historic Preservation Act

    In accordance with the Advisory Council on Historic Preservation's implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic Preservation Office(s), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project's potential effects on historic properties.[5] The environmental document for this project will document findings on the impacts on historic properties and summarize the status of consultations under section 106.

    Environmental Mailing List

    The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission's regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project and includes a mailing address with their comments. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project.

    If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please complete one of the following steps:

    (1) Send an email to GasProjectAddressChange@ferc.gov stating your request. You must include the docket number CP21-45-000 in your request. If you are requesting a change to your address, please be sure to include your name and the correct Start Printed Page 14904address. If you are requesting to delete your address from the mailing list, please include your name and address as it appeared on this notice. This email address is unable to accept comments.

    OR

    (2) Return the attached “Mailing List Update Form” (appendix 2).

    Additional Information

    Additional information about the project is available from the Commission's Office of External Affairs, at (866) 208-FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on “General Search” and enter the docket number in the “Docket Number” field. Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings.

    Public sessions or site visits will be posted on the Commission's calendar located at https://www.ferc.gov/​news-events/​events along with other related information.

    Start Signature

    Dated: March 15, 2021.

    Nathaniel J. Davis, Sr.,

    Deputy Secretary.

    End Signature End Preamble

    Footnotes

    1.  A pipeline loop is a segment of pipe constructed parallel to an existing pipeline to increase capacity. A “pig” is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting internal inspections, or other purposes.

    Back to Citation

    2.  The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called “eLibrary” or from the Commission's Public Reference Room, 888 First Street NE, Washington, DC 20426, or call (202) 502-8371. For instructions on connecting to eLibrary, refer to the last page of this notice.

    Back to Citation

    3.  For instructions on connecting to eLibrary, refer to the last page of this notice.

    Back to Citation

    4.  The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Section 1501.8.

    Back to Citation

    5.  The Advisory Council on Historic Preservation's regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places.

    Back to Citation

    [FR Doc. 2021-05708 Filed 3-18-21; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
03/19/2021
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2021-05708
Pages:
14902-14904 (3 pages)
Docket Numbers:
Docket No. CP21-45-000
PDF File:
2021-05708.pdf