95-5111. Columbia Gas Transmission Corp.; Notice of Intent To Prepare an Environmental Assessment for the Proposed Majorsville/Crawford Storage Project and Request for Comments on Environmental Issues  

  • [Federal Register Volume 60, Number 41 (Thursday, March 2, 1995)]
    [Notices]
    [Pages 11662-11664]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-5111]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket Nos. CP95-61-000 and CP95-62-000]
    
    
    Columbia Gas Transmission Corp.; Notice of Intent To Prepare an 
    Environmental Assessment for the Proposed Majorsville/Crawford Storage 
    Project and Request for Comments on Environmental Issues
    
    February 24, 1995.
        The staff of the Federal Energy Regulatory Commission (FERC or the 
    Commission) will prepare an environmental assessment (EA) that will 
    discuss the environmental impacts of the construction and operation of 
    facilities proposed in the Majorsville/Crawford Storage Project.\1\ 
    This EA will be used by the Commission in its decision-making process 
    to determine if an environmental impact statement is necessary and 
    whether to approve the project.
    
        \1\Columbia Gas Transmission Corporation's applications in 
    Docket Nos. CP95-61-000 and CP95-62-000 were filed with the 
    Commission under Section 7 of the Natural Gas Act and Part 157 of 
    the Commission's regulations.
    ---------------------------------------------------------------------------
    
    Summary of the Proposed Project
    
        In Docket No. CP95-61-000, Columbia Gas Transmission Corporation 
    (Columbia) requests Commission authorization to temporarily deactivate 
    the storage operations at its Majorsville-Heard Storage Complex to 
    allow coal mining operations by the Consol Pennsylvania Coal Company 
    and/or its affiliates. Columbia needs to deactivate its storage 
    facilities when the coal mining operation is nearby since ``long wall 
    mining'' typically causes surface subsidence which could result in 
    adverse impact on the wells and pipelines. Once mining has ended, 
    Columbia would determine if the facility can be reactivated or should 
    be permanently abandoned.
        At the Majorsville/Heard Storage Complex in Greene and Washington 
    Counties, Pennsylvania and Marshall County, West Virginia, Columbia 
    proposes to temporarily deactivate portions of the storage field for at 
    least the next 13 years. This would include:
         Abandoning up to 238 wells; and
         Abandoning up to 60 miles of existing pipeline.
        In Docket No. CP95-62-000, Columbia requests Commission 
    authorization to increase its natural gas storage capability and to 
    construct and operate additional facilities at its Crawford Storage 
    Field and Crawford Compressor Station to offset the temporary 
    deactivation of the Majorsville-Heard Storage Complex. Columbia 
    proposes to increase:
         The storage capability of the Crawford Storage Field by 5 
    billion cubic feet (Bcf) to 52 Bcf;
         The annual withdrawals by 8.15 Bcf to 17.65 Bcf; and
         The design day deliverability by 67.2 million cubic feet 
    per day (MMcfd) to 232.2 MMcfd.
        At the Crawford Storage Field in Hocking County, Ohio, Columbia 
    proposes to:
         Drill four new wells;
         Construct about 5.01 miles of pipeline, including:
    
    --2.30 miles of 20-inch-diameter pipeline replacing 1.40 mile of 16-
    inch-diameter pipeline and 0.90 mile of 10- and 8-inch-diameter 
    pipeline;
    --0.80 mile of 10-inch-diameter pipeline replacing 0.80 mile of 4-inch-
    diameter pipeline;
    --0.76 mile of 10-inch-diameter new pipeline;
    --0.36 mile of 8-inch-diameter pipeline replacing 0.40 mile of 4-inch-
    diameter pipeline;
    --0.45 mile of 8-inch-diameter new pipeline;
    --0.32 mile of 6-inch-diameter pipeline replacing 0.30 mile of 4-inch-
    diameter pipeline; and
    --0.02 mile of 6-inch-diameter new pipeline.
    
         Install other appurtenant facilities, including:
    
    --Wellhead measurement stations at four new and two existing wells;
    --Electric measurement cables within the right-of-way to the four new 
    wells;
    --Up to 10 pig launching/receiving facilities; and
    --Valve replacement sets at six existing and one new well.
    
        [[Page 11663]] At the Crawford Compressor Station in Fairfield 
    County, Ohio, Columbia proposes to:
         Add a third dehydration contactor and related reboiler and 
    piping;
         Add a gas cooler to each of the three existing compressor 
    units;
         Replace a compressor cylinder on one of the existing 
    compressor units; and
         Add a gas cleaner and make other changes.
        The general location of the project facilities is shown in appendix 
    1. Specific locations of the proposed Crawford Storage Field facilities 
    are shown in appendix 2.\2\
    
        \2\The appendices referenced in this notice are not being 
    printed in the Federal Register. Copies are available from the 
    Commission's Public Reference and Files Maintenance Branch, Room 
    3104, 941 North Capitol Street, NE., Washington, DC 20426, or call 
    (202) 208-1371. Copies of the appendices were sent to all those 
    receiving this notice in the mail.
    ---------------------------------------------------------------------------
    
    Land Requirements for Construction
    
    Majorsville/Heard Storage Complex
    
        The temporary deactivation of the Majorsville/Heard Storage Complex 
    facilities would require some construction activity. Abandonment of the 
    pipelines (either in place or by removal) would occur within the 
    existing right-of-way. Abandonment and plugging of the wells would 
    require some disturbance in the immediate area of the well.
    
    Crawford Storage Field
    
        Construction and operation of the four proposed new well sites 
    would disturb a total of about 2.8 acres of land.
        columbia intends to use its existing 50-foot-wide right-of-way for 
    removal of the existing pipelines and construction of the small 
    diameter (less than 18-inch-diameter) replacement pipelines. All new 
    pipelines would be constructed within a 50-foot-wide right-of-way. For 
    the 20-inch-diameter replacement pipeline, Columbia proposes to use a 
    75-foot-wide construction right-of-way, of which 50 feet would be 
    existing right-of-way and 25 feet would be new temporary right-of-way. 
    All of the replacement pipelines would be built in about the same 
    location as the existing pipelines. All other appurtenant facilities 
    would be constructed within the right-of-way for the new and 
    replacement pipelines. Construction of the pipelines would affect about 
    43.1 acres of land.
        Extra temporary work space would be also required for staging areas 
    for topsoil segregation; for road, wetland and stream crossings; 
    equipment mobilization; and contractor and pipe storage yards. Columbia 
    estimates that these extra work spaces would temporarily disturb about 
    7.1 acres of land.
        Following construction, the new and replacement pipelines would be 
    within a 50-foot-wide permanent right-of-way centered on the pipeline. 
    All temporary construction right-of-way and extra workspaces would be 
    restored and allowed to revert to their former use. About 7.5 acres of 
    land would be required for the new permanent right-of-way.
    
    Crawford Compressor Station
    
        Construction of the additional facilities at the Crawford 
    Compressor Station would take place entirely within the existing 
    station fenceline.
    
    The EA Process
    
        The National Environmental Policy Act (NEPA) requires the 
    Commission to take into account the environmental impacts that could 
    result from an action whenever it considers the issuance of a 
    Certificate of Public Convenience and Necessity. NEPA also requires us 
    to discover and address concerns the public may have about proposals. 
    We call this ``scoping''. The main goal of the scoping process is to 
    focus the analysis in the EA on the important environmental issues. By 
    this Notice of Intent, the Commission requests public comments on the 
    scope of the issues it will address in the EA. All comments received 
    are considered during the preparation of the EA. State and local 
    government representatives are encouraged to notify their constituents 
    of this proposed action and encourage them to comment on their areas of 
    concern.
        The EA will discuss impacts that could occur as a result of the 
    construction and operation of the proposed project under these general 
    headings:
         Geology and soils.
         Water resources, fisheries, and wetlands.
         Vegetation and wildlife.
         Endangered and threatened species.
         Land use.
         Cultural resources.
         Air quality.
         Public safety.
        We will also evaluate possible alternatives to the proposed project 
    or portions of the project, and make recommendations on how to lessen 
    or avoid impacts on the various resource areas.
        Our independent analysis of the issues will be in the EA. Depending 
    on the comments received during the scoping process, the EA may be 
    published and mailed to Federal, state, and local agencies, public 
    interest groups, interested individuals, affected landowners, 
    newspapers, libraries, and the Commission's official service list for 
    this proceeding. A comment period will be allotted for review if the EA 
    is published. We will consider all comments on the EA before we 
    recommend that the Commission approve or not approve the project.
    
    Currently Identified Environmental Issues
    
        We have already identified several issues that we think deserve 
    attention based on a preliminary review of the proposed facilities and 
    the environmental information provided by Columbia. Keep in mind that 
    this is a preliminary list. The list of issues may be added to, 
    subtracted from, or changed based on your comments and our analysis. 
    Issues are:
    
    Crawford Storage Field
    
         The pipelines would cross three perennial waterbodies and 
    eight non-forested wetlands.
         The pipelines may cross or be near historic structures and 
    archeological sites.
         Two pipeline segments would cross a state scenic highway 
    (State Route 374).
         Construction of one pipeline segment would take place 
    within 50 feet of three residences.
         Some of the pipeline segments would possibly cross 
    potential habitat for the Indiana bat, a federally listed endangered 
    species.
         Increasing the capacity of the storage field may increase 
    the potential for leakage.
    
    Crawford Compressor Station
    
         Some of the additional facilities would be within a 100-
    year floodplain.
         The reboiler for the dehydration contactor would slightly 
    increase the NOX emission levels of the station.
    
    Public Participation
    
        You can make a difference by sending a letter addressing your 
    specific comments or concerns about the project. You should focus on 
    the potential environmental effects of the proposal, alternatives to 
    the proposal (including alternative routes), and measures to avoid or 
    lessen environmental impact. The more specific your comments, the more 
    useful they will be. Please follow the instructions below to ensure 
    that your comments are received and properly recorded:
         Address your letter to: Lois Cashell, Secretary, Federal 
    Energy Regulatory Commission, 825 North Capitol St., N.E., Washington, 
    D.C. 20426. [[Page 11664]] 
         Reference Docket Nos. CP95-61-000 and CP95-62-000.
         Send a copy of your letter to: Ms. Laura Turner, EA 
    Project Manager, Federal Energy Regulatory Commission, 825 North 
    Capitol Street., N.E., Room 7312, Washington, D.C. 20426.
         Mail your comments so that they will be received in 
    Washington, D.C. on or before April 3, 1995.
    If you wish to receive a copy of the EA, you should request one from 
    Ms. Turner at the above address.
    
    Becoming and Intervenor
    
        In addition to involvement in the EA scoping process, you may want 
    to become an official party to the proceeding or become an 
    ``intervenor''. Among other things, intervenors have the right to 
    receive copies of case-related Commission documents and filings by 
    other intervenors. Likewise, each intervenor must provide copies of its 
    filings to all other parties. If you want to become an intervenor you 
    must file a motion to intervene according to Rule 214 of the 
    Commission's Rules of Practice and Procedure (18 CFR 385.214) (see 
    appendix 3).
        The date for filing timely motions to intervene in this proceeding 
    has passed. Therefore, parties now seeking to file late interventions 
    must show good cause, as required by Sec. 385.214(b)(3), why this time 
    limitation should be waived. Environmental issues have been viewed as 
    good cause for late intervention. You do not need intervenor status to 
    have your scoping comments considered.
        Additional information about the proposed project is available from 
    Ms. Laura Turner, EA Project Manager, at (202) 208-0916.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 95-5111 Filed 3-1-95; 8:45 am]
    BILLING CODE 6717-01-M
    
    

Document Information

Published:
03/02/1995
Department:
Energy Department
Entry Type:
Notice
Document Number:
95-5111
Pages:
11662-11664 (3 pages)
Docket Numbers:
Docket Nos. CP95-61-000 and CP95-62-000
PDF File:
95-5111.pdf