95-6913. Parker-Davis ProjectProposed Firm Power Rate and Firm and Nonfirm Transmission Service Rates  

  • [Federal Register Volume 60, Number 54 (Tuesday, March 21, 1995)]
    [Notices]
    [Pages 14935-14936]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-6913]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    Western Area Power Administration
    
    
    Parker-Davis Project--Proposed Firm Power Rate and Firm and 
    Nonfirm Transmission Service Rates
    
    AGENCY: Western Area Power Administration, DOE.
    
    ACTION: Notice of proposed Parker-Davis Project power rate and firm and 
    nonfirm transmission rate adjustments.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Western Area Power Administration (Western) is initiating 
    rate adjustments for firm power and firm and nonfirm transmission 
    service for the Parker-Davis Project (P-DP). The power repayment study 
    and other analyses indicate that the revenues required to pay all 
    annual costs (including interest expense), plus repayment of required 
    investment within the allowable time period has decreased by 
    approximately $4.7 million since the last rate adjustment. The proposed 
    P-DP rates for firm power and firm and nonfirm transmission service are 
    expected to become effective October 1, 1995, and will supersede the 
    existing step two rates.
        On January 6, 1994, the Deputy Secretary of the Department of 
    Energy (DOE) approved the existing rates for firm power and firm and 
    nonfirm transmission service on an interim basis. The existing rates 
    for firm power and firm and nonfirm transmission service were placed in 
    effect on February 1, 1994, and consisted of a two-step rate 
    adjustment. Step one of the existing rates was effective February 1, 
    1994, through September 30, 1995, and step two of the existing rates 
    was to be effective on October 1, 1995, through January 31, 1999. The 
    Federal Energy Regulatory Commission (FERC) confirmed and approved the 
    rates on October 14, 1994.
        During this last P-DP rate adjustment process (WAPA-55), the 
    Arizona Power Pooling Association, Inc.; Arizona Power Authority; and 
    the Arizona Customer Group filed Motions To Intervene and Protest 
    FERC's confirmation and approval of the P-DP rates described in Rate 
    Order No. WAPA-55. On August 19, 1994, Western filed a Stipulation 
    Agreement signed by Western and these customers in which the 
    intervenors withdrew any protest and Western agreed to re-examine the 
    issues raised as well as commence a new rate adjustment proceeding 
    during fiscal year 1995.
        Western has re-examined the issues raised during the last rate 
    adjustment process and has developed proposed P-DP rates to supersede 
    step two of the existing rates which were to become effective October 
    1, 1995, for firm power and firm and nonfirm transmission service. The 
    major differences between step two of the existing rates and the 
    proposed P-DP rates resulted from several activities which involved 
    Western working in partnership with the P-DP customers. First, future 
    revenue requirements were reduced by controlling Western's operation 
    and maintenance costs, and by decreasing the construction and 
    replacement program through the Engineering Ten Year Planning Process. 
    The Engineering Ten Year Planning Process includes a decision making 
    partnership among P-DP customers and Western.
        Second, Western revised the allocation of costs between the power 
    and transmission customers which is described in a Costs Apportionment 
    Study. A working group including customer representatives, Western, and 
    the Bureau of Reclamation was formed to analyze the issues and concerns 
    expressed by the customers during the last rate adjustment process on 
    how costs were allocated between power and transmission. The working 
    group derived a new methodology for allocating these costs in a manner 
    deemed equitable. The new methodology also meets the concerns of both 
    P-DP customers and Western.
        Third, the working group developed a revised rate design 
    methodology using the results from the Costs Apportionment Study. The 
    results from the Costs Apportionment Study were applied to total 
    revenue requirements instead of incremental revenue requirements as was 
    done to derive step two of the existing rates.
        When compared to step two of the existing rates, the activities 
    stated resulted in a rate decrease for firm power customers and a rate 
    increase for firm and nonfirm transmission customers.
        The proposed P-DP rates provide for an energy rate of 1.91 mills 
    per kilowatthour (mills/kWh) and a capacity rate of $2.06 per kilowatt/
    month (kW/month) for a composite rate of 6.62 mills/kWh. The proposed 
    P-DP rates for transmission service provide for a firm transmission 
    service rate of $13.28 per kilowatt/year (kW/year) and a nonfirm 
    transmission service rate of 2.53 mills/kWh for P-DP and a firm 
    transmission service rate for the Salt Lake City Area/Integrated 
    Projects (SLCA/IP) of $6.64/kW/season. The SLCA/IP transmission service 
    is for the SLCA/IP customers' seasonal use of the P-DP transmission 
    system.
        Table One compares step two of the existing rates with the proposed 
    P-DP rates.
    
                                                                            
    [[Page 14936]]                                                          
                                                        Table One                                                   
    ----------------------------------------------------------------------------------------------------------------
                                                 Step two of the existing      Proposed rates October 1,    Percent 
                 Type of service                  rates October 1, 1995,      1995, through September 30,    change 
                                                 through January 31, 1999                2000                 (%)   
    ----------------------------------------------------------------------------------------------------------------
    Composite Rate...........................  12.01 mills/kWh.............  6.62 mills/kWh..............        -45
    Energy Rate..............................  6.01 mills/kWh..............  1.91 mills/kWh..............        -68
    Capacity Rate............................  $2.63 per kW/month..........  $2.06 per kW/month..........        -22
    Firm Transmission Service................  $12.55 per kW/year..........  $13.28 per kW/year..........          6
    Nonfirm Transmission Service.............  2.39 mills/kWh..............  2.53 mills/kWh..............          6
    Transmission Service for SLCA/IP.........  $6.27 per kW/season.........  $6.64 per kW/season.........          6
    ----------------------------------------------------------------------------------------------------------------
    
        Overall, annual revenue requirements for the proposed rates has 
    slightly increased as compared to step one of the existing rates and 
    has decreased as compared to step two of the existing rates. Table Two 
    shows a comparison of the annual revenue requirements for step one of 
    the existing rates, step two of the existing rates, and the proposed 
    rates.
    
                                    Table Two                               
    ------------------------------------------------------------------------
        Step one of the                                                     
         existing rates          Step two of the          Proposed rates    
       (February 1, 1994,    existing rates (October     (October 1, 1995,  
     through September 30,       1, 1995, through      through September 30,
             1995)              January 31, 1999)              2000)        
    ------------------------------------------------------------------------
    $37,209,290............          $42,099,987              $37,385,908   
    ------------------------------------------------------------------------
    
        Since the proposed P-DP rates constitute a major rate adjustment as 
    defined by the procedures for public participation in general rate 
    adjustments, as cited below, both a public information forum and a 
    public comment forum will be held. After review of public comments, 
    Western will recommend proposed P-DP rates for approval on an interim 
    basis by the Deputy Secretary of DOE (Deputy Secretary).
    
    DATES: The consultation and comment period will begin with publication 
    of this notice in the Federal Register and will end not less than 90 
    days later, or June 21, 1995, whichever occurs last. A public 
    information forum will be held at 9:30 a.m. on April 5, 1995, at 
    Western's Phoenix Area Office, 615 South 43rd Avenue, Phoenix, Arizona. 
    A public comment forum at which Western will receive oral and written 
    comments will be held at 9:30 a.m. on May 15, 1995, also at Western's 
    Phoenix Area Office.
        Written comments should be received by Western by the end of the 
    consultation and comment period to be assured consideration and should 
    be sent to the address below.
    
    FOR FURTHER INFORMATION CONTACT: Mr. J. Tyler Carlson, Area Manager, 
    Western Area Power Administration, Phoenix Area Office, P.O. Box 6457, 
    Phoenix, AZ 85005, (602) 352-2453.
    
    SUPPLEMENTARY INFORMATION: Power and transmission rates for the P-DP 
    are established pursuant to the Department of Energy Organization Act 
    (42 U.S.C. 7101 et seq.), the Reclamation Act of 1902 (43 U.S.C. 392 et 
    seq.), as amended and supplemented by subsequent enactments, 
    particularly section 9(c) of the Reclamation Project Act of 1939 (43 
    U.S.C. 485h(c)), and the Act of May 28, 1954 (ch. 241, 68 Stat. 143).
        By Amendment No. 3 to Delegation Order No. 0204-108, published 
    November 10, 1993 (58 FR 59716), the Secretary of Energy (Secretary) 
    delegated (1) the authority to develop long-term power and transmission 
    rates on a nonexclusive basis to the Administrator of Western; (2) the 
    authority to confirm, approve, and place such rates in effect on an 
    interim basis to the Deputy Secretary; and (3) the authority to 
    confirm, approve, and place into effect on a final basis, to remand, or 
    to disapprove such rates to the FERC. Existing DOE procedures for 
    public participation in rate adjustments (10 CFR Part 903) became 
    effective on September 18, 1985 (50 FR 37837).
    
    Availability of Information
    
        All brochures, studies, comments, letters, memorandums, and other 
    documents made or kept by Western for the purpose of developing the 
    proposed P-DP rates for firm power and firm and nonfirm transmission 
    service are and will be made available for inspection and copying at 
    the Phoenix Area Office, 615 South 43rd Avenue, Phoenix, Arizona 85005.
    
    Determination Under Executive Order 12866
    
        DOE has determined that this is not a significant regulatory action 
    because it does not meet the criteria of Executive Order 12866, 58 FR 
    51735. Western has an exemption from centralized regulatory review 
    under Executive Order 12866; accordingly, no clearance of this notice 
    by the Office of Management and Budget is required.
    
    Environmental Evaluation
    
        In compliance with the National Environmental Policy Act of 1969 
    (NEPA), 42 U.S.C. 4321 et seq.; Council on Environmental Quality 
    Regulations (40 CFR Parts 1500-1508); and DOE NEPA Regulations (10 CFR 
    Part 1021), Western has determined that this action is categorically 
    excluded from the preparation of an environmental assessment or an 
    environmental impact statement.
    
        Issued in Golden, Colorado, March 10, 1995.
    J. M. Shafer,
    Administrator.
    [FR Doc. 95-6913 Filed 3-20-95; 8:45 am]
    BILLING CODE 6450-01-P
    
    

Document Information

Published:
03/21/1995
Department:
Western Area Power Administration
Entry Type:
Notice
Action:
Notice of proposed Parker-Davis Project power rate and firm and nonfirm transmission rate adjustments.
Document Number:
95-6913
Dates:
The consultation and comment period will begin with publication of this notice in the Federal Register and will end not less than 90 days later, or June 21, 1995, whichever occurs last. A public information forum will be held at 9:30 a.m. on April 5, 1995, at Western's Phoenix Area Office, 615 South 43rd Avenue, Phoenix, Arizona. A public comment forum at which Western will receive oral and written comments will be held at 9:30 a.m. on May 15, 1995, also at Western's Phoenix Area Office.
Pages:
14935-14936 (2 pages)
PDF File:
95-6913.pdf