96-6936. Yankee Atomic Electric Company; Issuance of Supplemental Director's Decision Under 10 CFR 2.206  

  • [Federal Register Volume 61, Number 57 (Friday, March 22, 1996)]
    [Notices]
    [Pages 11898-11903]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-6936]
    
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-029; License No. DPR-3]
    
    
    Yankee Atomic Electric Company; Issuance of Supplemental 
    Director's Decision Under 10 CFR 2.206
    
        Notice is hereby given that by a Director's Decision (DD 96-02), 
    dated March 18, 1996, the Director, Office of Nuclear Reactor 
    Regulation, denied a supplemental Petition submitted by Citizens 
    Awareness Network and New England Coalition on Nuclear Pollution 
    (Petitioners) and dated February 9, 1996. Petitioners requested that 
    the Nuclear Regulatory Commission (NRC) take action with regard to 
    operation by Yankee Atomic Energy Company (YAEC or Licensee) of its 
    Nuclear Power Station at Rowe, Massachusetts (Yankee Rowe).
        Petitioners request that the NRC comply with Citizens Awareness 
    Network Inc. v. United States Nuclear Regulatory Commission and Yankee 
    Atomic Electric Company, 59 F.3d 284 (1st Cir. 1995) (CAN v. NRC). 
    Specifically, Petitioners request that the Commission prohibit the 
    licensee from conducting six activities prior to approval of a 
    decommissioning plan. These activities are: (1) Consolidation of 
    sediment in the reactor vessel; (2) removal of miscellaneous Safety 
    Injection Building equipment; (3) installation of a temporary 
    electrical system; (4) removal of pipe on the exterior of the Vapor 
    Container; (5) removal of Main Coolant System insulation; and (6) 
    installation of a temporary waste processing system. Petitioners state 
    that none of these activities constitute minor alterations to the 
    facility, and thus are not permitted.
        The NRC staff also evaluated five other ongoing or planned 
    activities at Yankee Rowe that were identified in the licensee's 
    letters of January 29, 1996, February 16, 1996, and February 28, 1996. 
    These activities are: (1) Preparation for decontamination of the Main 
    Coolant System--removal of spool pieces; (2) removal of miscellaneous 
    equipment outside the Vapor Container bioshield wall; (3) removal of 
    Primary Auxiliary Building tanks; (4) removal of Turbine Building 
    insulation; and (5) removal of spent fuel pool upender.
    
    [[Page 11899]]
    
        The staff concluded that the eleven activities are permissible, 
    prior to approval of a decommissioning plan, under the pre-1993 
    interpretation of the Commission's decommissioning regulation, as 
    explained in the ``Director's Decision Pursuant to 10 CFR 2.206'' (DD 
    96-02), the complete text of which follows this notice and is available 
    for public inspection at the Commission's Public Document Room, the 
    Gelman Building, 2120 L Street, NW, Washington, DC and at the local 
    public document room located at the Greenfield Community College 
    Library, 1 College Drive, Greenfield, Massachusetts, 01301.
        A copy of the decision will be filed with the Secretary of the 
    Commission for the Commission's review in accordance with 10 CFR 
    2.206(c) of the Commission's regulations. As provided by this 
    regulation, the Decision will constitute the final action of the 
    Commission 25 days after the date of issuance unless the Commission, on 
    its own motion, institutes a review of the Decision in that time.
    
        Dated at Rockville, Maryland, this 18th day of March 1996.
    
        For the Nuclear Regulatory Commission.
    William T. Russell, Director, Office of Nuclear Reactor Regulation.
    
    Attachment to Issuance of Supplemental Director's Decision Under 10 
    C.F.R. Sec. 2.206
    
    I. Introduction
    
        On January 17, 1996, Citizens Awareness Network and New England 
    Coalition on Nuclear Pollution (Petitioners) submitted an ``EMERGENCY 
    MOTION FOR COMPLIANCE WITH CIRCUIT COURT OPINION'' (Petition). 
    Petitioners requested that the United States Nuclear Regulatory 
    Commission (NRC or Commission) take action with respect to activities 
    conducted by Yankee Atomic Electric Company (YAEC or Licensee) at the 
    Yankee Nuclear Power Station in Rowe, Massachusetts (Yankee Rowe or the 
    facility). In particular, Petitioners requested that the NRC comply 
    with Citizens Awareness Network Inc. v. United States Nuclear 
    Regulatory Commission and Yankee Atomic Electric Company, 59 F. 3d 284 
    (1st Cir. 1995) (CAN v. NRC), and that the Commission immediately order 
    YAEC not to undertake and the staff not to approve, and YAEC to cease, 
    further major dismantling activities or other decommissioning 
    activities, unless such activities are necessary to assure the 
    protection of occupational and public health and safety. Petitioners 
    requested that the Commission prohibit five of nine activities which 
    the Licensee proposed to conduct prior to approval of a decommissioning 
    plan, which activities were evaluated by the staff in a letter dated 
    November 2, 1995.
        By letter dated February 2, 1996, the NRC staff declined to take 
    emergency action to prohibit the Licensee's shipment of low-level 
    radioactive waste, and found that Petitioners' request to prohibit four 
    other activities was moot.
        By a Supplemental Petition, Petitioners requested the Commission to 
    reverse the NRC staff's February 2, 1996 decision on the emergency 
    aspects of the Petition, and contended that the staff had implicitly 
    approved six additional activities, which the Licensee identified for 
    the first time as under consideration in its January 29, 1996 response 
    to the Petition, although the activities are not minor alterations to 
    the facility. (A seventh activity was mentioned, but not contested). 
    See Citizens Awareness Network's and New England Coalition on Nuclear 
    Pollution's Motion for Exercise of Plenary Commission Authority to 
    Reverse NRC Staff 2.206 Opinion (February 9, 1996).
        By Order dated February 15, 1996, the Commission directed the 
    Licensee to provide the NRC with at least two weeks advance notice 
    before engaging in any of the seven new activities identified at page 
    13 of the Supplemental Petition, and directed the staff to address the 
    arguments advanced by Petitioners at page 13 of the Supplemental 
    Petition in a supplementary 10 CFR 2.206 decision.
        By letter dated February 16, 1996, the Licensee notified the NRC 
    staff and Petitioners that YAEC intended to commence five activities 
    between March 1, 1996 and March 25, 1996.
        On February 22, 1996, the staff issued a Director's Decision (DD 
    96-01) on the Petition as a whole. The staff denied Petitioners' 
    request to prohibit the Licensee's shipments of low-level radioactive 
    waste, and found four other activities contested by Petitioners to be 
    moot.
        By letter dated February 27, 1996, the NRC staff requested the 
    Licensee to supply information regarding the seven activities 
    identified by the Supplemental Petition, plus information regarding 
    four other activities identified as ongoing in the Licensee's January 
    29, 1996 response to the Petition. The Licensee responded by letter 
    dated February 28, 1996, providing information regarding the eleven 
    activities plus an additional activity, removal of the Spent Fuel Pool 
    Upender. Three activities were ongoing, and the remaining nine were 
    scheduled to commence between March 1, 1996 and April 22, 1996.
        By letter dated March 1, 1996, the staff notified the Licensee that 
    three activities scheduled to commence March 1, 1996, are permissible, 
    before approval of a decommissioning plan, under the pre-1993 
    interpretation of the Commission's decommissioning regulations, and 
    thus, that there was no reason to take emergency action to prevent YAEC 
    from starting or to order discontinuance of the ongoing activities. 
    Additionally, the staff found no health or safety reason for immediate 
    NRC action.
        The staff has evaluated the six ongoing and planned activities 
    contested by the Supplemental Petition and the five additional 
    activities identified in the Licensee's letters of January 29, 1996, 
    February 16, 1996, and February 28, 1996. Two activities, removal of 
    miscellaneous equipment outside the Vapor Container bioshield wall and 
    preparation for decontamination 1 of the Main Coolant System 
    (removal of spool pieces) were completed in February 1996. For the 
    reasons discussed below, the staff has concluded that the activities 
    are permissible, prior to approval of a decommissioning plan, under the 
    pre-1993 interpretation of the Commission's decommissioning 
    regulations. Accordingly, Petitioners' request that the NRC prohibit 
    YAEC from undertaking or continuing the six contested activities 
    identified at page 13 of the Supplemental Motion is denied.
    
        \1\  Decontamination at a nuclear plant is the flushing of 
    pipes, pumps, pressure vessels etc., with fluids to remove materials 
    that are contaminated with radiation from the inner surfaces of 
    these components.
    ---------------------------------------------------------------------------
    
    II. Background
    
        As explained in detail in DD 96-01, Petitioners sought judicial 
    review of certain NRC actions, related to the Licensee's Component 
    Removal Project (CRP). Petitioners challenged the CRP as an 
    impermissible activity, before the approval of a decommissioning plan, 
    under the pre-1993 interpretation of the Commission's decommissioning 
    regulations.
        On July 20, 1995, the United States Court of Appeals held, in part, 
    that the Commission had: (1) Failed to provide an opportunity for 
    hearing to CAN, as required by Section 189 of the Atomic Energy Act, in 
    connection with the Commission's decision to permit the CRP 
    decommissioning activities; and (2) changed its pre-1993 interpretation 
    of its decommissioning regulations without notice to the public and in 
    violation of the Administrative
    
    [[Page 11900]]
    Procedure Act. Citizens Awareness Network versus NRC and Yankee Atomic 
    Electric Company, 59 F. 3d 284, 291-2, and 292-3 (lst Cir. 1995). The 
    court remanded the matter to the Commission for proceedings consistent 
    with the court's opinion.
        The Commission implemented CAN versus NRC, in part, by issuing 
    Yankee Atomic Electric Company (Yankee Nuclear Power Station), CLI-95-
    14, 42 NRC 130 (1995). In CLI-95-14, the Commission reinstated its pre-
    1993 interpretation of its decommissioning policy, required the 
    issuance of a notice of opportunity for an adjudicatory hearing on the 
    Yankee Rowe decommissioning plan,2 held that YAEC may not conduct 
    further ``major'' decommissioning activities at Yankee Rowe until 
    approval of a decommissioning plan after completion of any required 
    hearing, and directed YAEC to inform the Commission within 14 days of 
    the steps it is taking to come into compliance with the reinstated 
    interpretation of the Commission's decommissioning regulations. Yankee 
    Atomic Electric Company, CLI-95-14, 42 NRC 130 (1995).
    
        \2\ Pursuant to CLI-95-14, a proceeding was commenced to offer 
    an opportunity for hearing on the Licensee's decommissioning plan 
    for Yankee Rowe. Petitioners sought intervention and a hearing. By 
    an Order dated March 1, 1996, the Atomic Safety and Licensing Board 
    denied the request for intervention and dismissed the proceeding. 
    Yankee Atomic Electric Company, LBP-96-2. By Order dated February 
    27, 1996, the Commission stayed any order of the Board insofar as it 
    may have the affect of authorizing decommissioning activities which 
    were prohibited prior to approval of a decommissioning plan.
    ---------------------------------------------------------------------------
    
    III. Discussion
    
        A. The licensee's planned and ongoing activities are permissible, 
    prior to approval of a decommissioning plan, under the Commission's 
    pre-1993 interpretation of its decommissioning regulations, and thus 
    are permissible under CAN v. NRC and CLI 95-14.
        Petitioners contest six of the seven activities they mention in the 
    Supplemental Petition on the ground that they do not constitute minor 
    alterations to the facility, and thus are not permissible before 
    approval of a decommissioning plan under the pre-1993 interpretation of 
    the Commission's decommissioning regulations. Specifically, Petitioners 
    object to: (1) Consolidation of sediment in the reactor vessel; (2) 
    removal of miscellaneous Safety Injection Building equipment; (3) 
    installation of a temporary electrical system; (4) removal of pipe on 
    the exterior of the Vapor Container; (5) removal of Main Coolant System 
    insulation; and (6) installation of a temporary waste processing 
    system. Petitioners do not object to decontamination of the Main 
    Coolant System. The staff has also evaluated the following five 
    activities identified by the Licensee in its letters of January 29, 
    1996, February 16, 1996, and February 28, 1996: (1) Preparation for 
    decontamination of the Main Coolant System--removal of spool pieces; 
    (2) removal of miscellaneous equipment outside the Vapor Container 
    bioshield wall; (3) removal of Primary Auxiliary Building tanks; (4) 
    removal of Turbine Building insulation; and (5) removal of spent fuel 
    pool upender.
        Under the Commission's pre-1993 interpretation of its 
    decommissioning regulations, a licensee ``may proceed with some 
    activities such as decontamination, minor component disassembly, and 
    shipment and storage of spent fuel if the activities are permitted by 
    the operating license and/or Sec. 50.59'' prior to final approval of a 
    licensee's decommissioning plan,3 as long as the activity does not 
    involve major structural or other changes and does not materially and 
    demonstrably affect the methods or options available for 
    decommissioning or substantially increase the costs of decommissioning. 
    Long Island Lighting Company (Shoreham Nuclear Power Station, Unit 1), 
    CLI-90-8, 32 NRC 201, 207 n.3 (1990); Long Island Lighting Company 
    (Shoreham Nuclear Power Station, Unit 1), CLI-91-2, 33 NRC 61, 73 n.5 
    (1991); and Sacramento Municipal Utility District (Rancho Seco Nuclear 
    Generating Station), CLI-92-2, 35 NRC 47, 61 n. 7 (1992).
    
        \3\ Statement of Consideration, ``General Requirements for 
    Decommissioning Nuclear Facilities'', 53 FR 24018, 24025-26 (June 
    27, 1988).
    ---------------------------------------------------------------------------
    
        Activities such as normal maintenance and repairs, removal of small 
    radioactive components for storage or shipment, and removal of 
    components similar to that for maintenance and repair also were 
    permitted prior to approval of a decommissioning plan under the 
    Commission's pre-1993 interpretation of the Commission's 
    decommissioning regulations. See NRC Inspection Manual, Chapter 2561, 
    Section 06.06. (Issue Date: 03/20/92).4
    
        \4\ ``Examples of modifications and activities, that are allowed 
    during the post-operational phase [the interval between permanent 
    shutdown and the NRC's approval of the licensee's decommissioning 
    plan] are (1) those that could be performed under normal maintenance 
    and repair activities, (2) removal of certain, relatively small 
    radioactive components, such as control rod drive mechanism, control 
    rods, and core internals for disassembly, and storage or shipment, 
    (3) removal of non-radioactive components and structures not 
    required for safety in the post-operational phase, (5) shipment of 
    reactor fuel offsite, and (6) activities related to site and 
    equipment radiation and contamination characterization.'' Id.
    ---------------------------------------------------------------------------
    
        Under the pre-1993 interpretation of the Commission's 
    decommissioning regulations, examples of activities which were 
    conducted at various facilities under a possession-only license, and 
    which the staff considered permissible before approval of a 
    decommissioning plan included:
    
    Shoreham 5
    
        a. Core borings in biological shield wall.
    
        \5\ See letter dated December 11, 1991, from John D. Leonard, 
    Jr., Long Island Lighting Company, to U.S. Nuclear Regulatory 
    Commission, Docket No. 50-322.
    ---------------------------------------------------------------------------
    
        b. Core borings of the reactor pressure vessel.
        c. Regenerative heat exchanger removal and disassembly.
        d. Various sections of reactor water clean-up system piping cut out 
    and removed to determine effectiveness of chemical decontamination 
    processes being used.
        e. Removal of approximately half of reactor pressure vessel 
    insulation and preparation for disposal.
        f. Removal of fuel support castings and peripheral pieces removed 
    and shipment offsite for disposal at Barnwell, South Carolina.
        g. Reactor water clean-up system recirculation holding pump removed 
    and shipped to James A. FitzPatrick Nuclear Power Plant.
        h. Control rod drive pump shipped to Brunswick Nuclear Station.
        i. One full set of control rod blade guides sold to Carolina Power 
    and Light Company.
        j. Control rod drives removed, cleaned, and stored in boxes for 
    salvage.
        k. Process initiated for segmenting and removing reactor pressure 
    vessel cavity shield blocks.
        l. Process initiated for removal of instrument racks, tubing, 
    conduits, walkways, and pipe insulation presenting interferences for 
    decommissioning activities and/or removal of salvageable equipment.
    
    Fort St. Vrain 6
    
        a. Control rod drive and orifice assemblies and control rods 
    removed from core during defueling and shipped offsite for processing 
    or disposal as low-level waste.
    
        \6\ See letter dated September 4, 1992, from Donald M. 
    Warembourg, Public Service Company of Colorado, to the U.S. Nuclear 
    Regulatory Commission, Docket No. 50-267.
    ---------------------------------------------------------------------------
    
        b. All helium circulators removed and shipped offsite for disposal.
        c. Core region constraint devices (internals) removed and 
    approximately one-half shipped offsite for disposal.
    
    [[Page 11901]]
    
        d. About 50 core metal-clad reflector blocks (top layer of core) 
    removed and stored in fuel storage wells.
        e. Removal of remaining hexagonal graphite reflector elements, 
    defueling elements, and metal-clad reflector blocks begun.
        f. Pre-stressed concrete reactor vessel (PCRV) top cross-head 
    tendons and some circumferential tendons detensioned.
        g. Some detensioned tendons removed from PCRV.
        h. Work initiated to cut and remove PCRV liner cooling system 
    piping presenting interferences to detensioning of PCRV tendons, and
        i. Asbestos insulation completely removed from piping under PCRV.
        In its letter of November 2, 1995, the NRC staff identified certain 
    activities, although not proposed by the Licensee, which may not be 
    conducted before reapproval of a decommissioning plan. Those activities 
    include dismantlement of systems such as the main reactor coolant 
    system, the lower neutron shield tank, vessels that have significant 
    radiological contamination, pipes, pumps and other such components and 
    the vapor container (containment). The staff also identified 
    segmentation or removal of the reactor vessel from its support 
    structure as a major dismantlement not to be conducted until after the 
    decommissioning plan is reapproved.
        Upon review of the Supplemental Petition and the Licensee's letters 
    of January 29, 1996, February 16, 1996, and February 28, 1996, the 
    staff concludes that the eleven planned and ongoing activities are 
    permissible, prior to approval of a decommissioning plan, under the 
    pre-1993 interpretation of the Commission's decommissioning 
    regulations.
        (1) Consolidation of sediment in the reactor vessel.
        This item is a decontamination activity. It involves flushing loose 
    radioactive material from the bottom of the reactor vessel (RV) and 
    binding it in a solid mass inside the RV, in a centralized volume and, 
    thus, displacing the contamination from the lower head of the vessel. 
    This activity results in a large reduction of external dose during 
    later removal and shipping of the vessel, and in a reduction of 
    external dose to personnel who must perform day-to-day maintenance and 
    monitoring activities.
        In view of the above, this activity is permissible, before approval 
    of a decommissioning plan, under the pre-1993 interpretation of the 
    Commission's decommissioning regulations.
        (2) Removal of miscellaneous Safety Injection Building equipment.
        This activity entails the removal of mechanical and electrical 
    equipment and some seismic reinforcement that is no longer required in 
    the Safety Injection Building. The components involved in this activity 
    are small, and constitute a minor decommissioning activity. Similar 
    activities were conducted at the Shoreham plant prior to 
    decommissioning plan approval. See items c, d, and g, above. 
    Accordingly, this activity is permissible prior to approval of a 
    decommissioning plan under the pre-1993 interpretation of the 
    Commission's decommissioning regulations.
        (3) Installation of a new electrical system.
        This activity is not decommissioning. This activity is part of the 
    Licensee's overall project to enhance the safety of the Spent Fuel Pool 
    by establishing independent systems dedicated to Spent Fuel Pool 
    reliability, and is consistent with NRC Bulletin 94-01, ``Potential 
    Fuel Pool Draindown Caused by Inadequate Maintenance Practice at 
    Dresden Unit 1'' (April 14, 1994). Installation of the new electrical 
    system involves installation of power supply and switching capability 
    to the previously installed electrical conduit, which conduit 
    installation the staff found to be permissible prior to approval of a 
    decommissioning plan. See DD 96-01, Section III. A(7).
        Accordingly, this activity is permissible before approval of a 
    decommissioning plan under the pre-1993 interpretation of the 
    Commission's decommissioning regulations.
        (4) Removal of pipe on the exterior of the Vapor Container.
        These pipe lines are located outdoors beneath the Vapor Container 
    and are in secondary-side systems, such as piping carrying steam from 
    the secondary side of the steam generator to the turbine. Because this 
    involves the removal of piping from the secondary side, it is not a 
    major decommissioning activity. Similar activities were conducted at 
    the Shoreham plant, see items d and g, above, and at the Fort St. Vrain 
    plant, see item b, above, prior to approval of the decommissioning 
    plans.
        In view of the above, this activity is permissible, before approval 
    of a decommissioning plan, under the pre-1993 interpretation of the 
    Commission's decommissioning regulations.
        (5) Removal of Main Coolant System insulation.
        This insulation will not be removed until after the decontamination 
    of the Main Coolant System. This insulation is not a major component 
    and its removal is, therefore, not a major decommissioning activity. 
    Similar activities were conducted at the Shoreham plant, see item e, 
    above, and at the Fort St. Vrain plant, see item i, above, prior to 
    approval of the decommissioning plans.
        In view of the above, this activity is permissible, before approval 
    of a decommissioning plan, under the pre-1993 interpretation of the 
    Commission's decommissioning regulations.
        (6) Installation of a temporary waste processing system.
        This activity is not decommissioning. It is permitted by the 
    Defueled Technical Specifications, an appendix to the POL. The activity 
    involves installation of a liquid waste processing system designed to 
    process spent fuel pool water by removing contaminants. The activity 
    will increase assurance of satisfactory long-term operation of the 
    spent fuel pool and is, therefore, a safety enhancement.
        In view of the above, this activity is permissible, before approval 
    of a decommissioning plan, under the pre-1993 interpretation of the 
    Commission's decommissioning regulations.
        (7) Preparation for decontamination of the Main Coolant System-
    removal of spool pieces.
        This is a decontamination activity which involved the removal of 
    eight spool pieces, and was completed in February 1996. It was part of 
    an ongoing project, preparation of pipe flanges for the chemical 
    decontamination of the Main Coolant System.
        Because this action is in preparation for decontamination and 
    without which decontamination could not proceed, this activity is 
    permissible. Decontamination is permissible, before approval of a 
    decommissioning plan, under the pre-1993 interpretation of the 
    Commission's decommissioning regulations. In any event, the Petition, 
    insofar as it can be inferred to request action in this matter, is 
    moot.
        (8) Removal of miscellaneous equipment outside the Vapor Container 
    bioshield wall.
        This activity involved the removal of heating and ventilating 
    equipment from the Vapor Container, and was completed in mid-February 
    1996. The components removed are minor and do not constitute a major 
    decommissioning activity. Similar activities were conducted at the 
    Shoreham plant prior to approval of the decommissioning plan. See items 
    c and d, above.
        Accordingly, this activity is permissible, before approval of a 
    decommissioning plan, under the pre-1993 interpretation of the 
    Commission's decommissioning regulations. In any
    
    [[Page 11902]]
    event, the Petition, insofar as it can be inferred to request action in 
    this matter, is moot.
        (9) Removal of Primary Auxiliary Building tanks.
        This activity involves the removal of four low pressure or drain 
    tanks from the Primary Auxiliary Building, because they are not needed 
    to support operation of the spent fuel pool. Two of the tanks were 
    removed during February 1996. Similar activities were conducted at the 
    Shoreham plant prior to approval of the decommissioning plan. See items 
    c, d, and g, above. This is not a major decommissioning activity 
    because the removed equipment involves minor components.
        In view of the above, this activity is permissible, before approval 
    of a decommissioning plan, under the pre-1993 interpretation of the 
    Commission's decommissioning regulations.
        (10) Removal of Turbine Building insulation.
        This is an ongoing activity involving the removal of non-
    radioactive material from a non-contaminated area of the plant. This is 
    not a decommissioning activity.
        Accordingly, this activity is permissible, before approval of a 
    decommissioning plan, under the pre-1993 interpretation of the 
    Commission's decommissioning regulations.
        (11) Removal of spent fuel pool upender.
        This device was used during reactor operations to transfer fuel, 
    during reload outages, into the Vapor Container. The upender is not 
    needed to support storage of fuel in the spent fuel pool. The upender 
    is not a major component or structure and, therefore, this is not a 
    major decommissioning activity. Similar activities were conducted at 
    the Shoreham plant, see items d and f, above and at Fort St. Vrain, see 
    item a above, prior to approval of the decommissioning plan.
        In view of the above, this activity is permissible, before approval 
    of a decommissioning plan, under the pre-1993 interpretation of the 
    Commission's decommissioning regulations.
        B. The eleven ongoing and planned activities will neither 
    individually nor collectively substantially increase the costs of 
    decommissioning.
        YAEC estimates the cost of the six activities contested by 
    Petitioners and the five additional planned and ongoing activities to 
    be approximately $6.0 million.7 YAEC estimates the cost of the 
    previously contested five activities to be $6.5 million. See DD 96-01, 
    Section III.B. The total cost of all activities which have been 
    evaluated by the staff is approximately $12.5 million or 3.4% of the 
    estimated $368.8 million total decommissioning cost. It would be 
    speculative to conclude that the decommissioning method proposed by 
    Petitioners, SAFSTOR, would be less expensive. Moreover, there is no 
    evidence that the combined activities will give rise to consequences 
    that will increase the total cost of decommissioning. Thus, the staff 
    concludes that there is no evidence the combined activities will 
    substantially increase the costs of decommissioning.
    
        \7\ See NRC letter from Russell A. Mellor, YAEC, to Morton B. 
    Fairtile, NRC, dated February 28, 1996.
    ---------------------------------------------------------------------------
    
        C. The activities contested by Petitioners will neither 
    individually nor collectively demonstrably affect the methods or 
    options available for decommissioning.
        As the staff explained in Yankee Atomic Electric Company, DD 96-01 
    (1996), the criteria for determining whether the Licensee's planned and 
    ongoing activities will demonstrably affect the methods or options 
    available for decommissioning have not been well-defined. During review 
    of the Petition and the Supplemental Petition, the NRC staff has 
    continued to examine the question of whether the Licensee's activities 
    will demonstrably affect the methods or options available for 
    decommissioning. In this case, the staff has now also compared the 
    radiation dose involved in the contested activities with the radiation 
    doses estimated for decommissioning of the Licensee's facility. This is 
    because, under Petitioners' theory regarding the choice of the 
    decommissioning option, as we understand it, it seems that adoption of 
    a different decommissioning option would most likely be required to 
    reduce dose.
        The Licensee estimates that the radiation dose involved in the six 
    activities contested by the Supplemental Petition is 23.6 person-
    rem.8 The Licensee estimates that the radiation dose involved in 
    shipment of low-level radioactive waste, contested in the Petition, is 
    17 person-rem.9 The Licensee estimates that the radiation dose 
    involved in the other four activities contested by the Petition is 24.7 
    person-rem.10 Accordingly, the radiation dose involved in all 
    activities contested by Petitioners is approximately 65.3 person-rem. 
    Thus, the estimated dose from the contested activities is less than 10% 
    of the total 755 person-rem estimate for total radiation exposure from 
    decommissioning Yankee Rowe.11 The staff estimates that the 
    remaining estimated dose from decommissioning activities at Yankee Rowe 
    is, at the most, approximately 358 person-rem.12 Thus the 
    estimated dose from the activities contested by Petitioners is 
    approximately 18.3% of the remaining dose from decommissioning the 
    facility.13 Accordingly, the staff concludes that the contested 
    activities will not demonstrably affect the methods and options 
    available for decommissioning.
    
        \8\ The Licensee estimates the radiation dose to be 13.8 person-
    rem for consolidation of sediment in the Reactor Vessel; 0.4 person-
    rem for removal of miscellaneous Safety Injection Building 
    equipment; 0.5 person-rem for installation of a temporary electrical 
    system; 0.4 person-rem for removal of pipe on the exterior of the 
    Vapor Container; 7.7 person-rem for removal of Main Coolant system 
    insulation; and 0.8 person-rem for installation of a temporary waste 
    processing system. See letter dated February 28, 1996, from Russell 
    A. Mellor, YAEC, to Morton B. Fairtile, NRC.
        \9\ See letter dated February 21, 1996, from K. J. Heider, YAEC, 
    to Morton B. Fairtile, NRC.
        \10\ The Licensee estimates the radiation dose to be 4 person-
    rem for Fuel Chute Isolation and negligible for Spent Fuel Pool 
    Electrical Conduit Installation. See letter dated February 21, 1996, 
    from K. J. Heider, YAEC, to Morton B. Fairtile, NRC. The staff 
    estimates the radiation dose to be 19.7 person-rem from completion 
    of removal of the remaining portions of the Upper Neutron Shield 
    Tank, and 1.0 person-rem from removal of Component Cooling Water 
    System pipes and components and Spent Fuel Cooling System pipes and 
    components based on a telephone conversation with the licensee on 
    March 15, 1996.
        \11\ See Order Approving the Decommissioning Plan and 
    Authorizing Decommissioning of Facility (Yankee Nuclear Power 
    Station), ``Environmental Assessment by the U.S. Nuclear Regulatory 
    Commission Related to the Request to Authorize Facility 
    Decommissioning'', p. 22.
        \12\ To estimate the remaining dose from decommissioning, the 
    staff subtracted, from the 755 person-rem estimate for total 
    allotted dose, the personnel exposures reported for calendar years 
    1993, 1994 and 1995, or 163, 156 and 78 person-rem, respectively. 
    See ``Personnel Exposure Report by duty Function and 10 CFR 20.407 
    Personnel Monitoring Report'', dated December 31, 1993, December 31, 
    1994, and December 31, 1995. The resulting estimate of approximately 
    358 person-rem may be an underestimate of the remaining available 
    exposure. Some of the dose from 1993 includes non-decommissioning 
    activities and some of the dose from the contested activities was 
    incurred during calendar year 1995, but should not be counted as 
    expended for purposes of estimating remaining dose.
        \13\ DD-96-01 compared the dose from the contested shipping 
    activity to the total radiation exposure from decommissioning, see 
    Section III.B.(9). It is, however, preferable to use the more 
    sophisticated approach of comparing dose from contested activities 
    to the remaining radiation exposure from decommissioning. 
    Nonetheless, under both approaches the staff concludes that the 
    contested activities will not demonstrably affect the options and 
    methods available for decommissioning.
    ---------------------------------------------------------------------------
    
        It is not possible to determine with precision how much of the 65.3 
    person-rem involved in the contested activities might be avoidable by 
    using the SAFSTOR option, i.e., by delaying completion of those 
    activities for several decades to allow for radioactive decay. But even 
    if the entire 65.3 person-rem
    
    [[Page 11903]]
    could be counted as part of the potential SAFSTOR dose savings (an 
    unlikely situation), the SAFSTOR dose savings still available is 
    substantially more than the 65.3 person-rem ``lost'' by carrying out 
    the contested activities now. Thus, even in an unlikely worst case, the 
    SAFSTOR option would be substantially preserved. Accordingly, the staff 
    concludes that the contested activities will not demonstrably affect 
    the methods and options available for decommissioning.
        In sum, the NRC staff will not take action to halt relatively minor 
    YAEC activities, many of which are closely similar to ones allowed at 
    Shoreham and Ft. St. Vrain, where there is no evidence that these 
    activities are consuming a significant portion of the remaining 
    radioactive dose at Yankee Rowe. In the staff's judgment, the 
    prohibition against dismantling major systems, such as the reactor 
    vessel and other reactor components with substantial 
    contamination,14 sufficiently preserves the possibility of 
    ultimately moving to the SAFSTOR option, should that be the result of 
    the still-pending challenge to YAEC's decommissioning plan.
    
        \14\ See letter dated November 2, 1995, from Morton B. Fairtile, 
    NRC, to James A. Kay, YAEC.
    ---------------------------------------------------------------------------
    
    IV. Conclusion
    
        For the reasons given above, Petitioner's request to prohibit six 
    activities is denied. Those activities, plus an additional five 
    activities identified by the Licensee as planned or ongoing, are 
    permissible prior to approval of a decommissioning plan under the pre-
    1993 interpretation of the Commission's decommissioning regulations.
        As provided by 10 CFR 2.206(c), a copy of this Decision will be 
    filed with the Secretary of the Commission for the Commission's review. 
    The Decision will become the final action of the Commission 25 days 
    after issuance, unless the Commission on its own motion institutes 
    review of the Decision within that time.
    
        Dated at Rockville, Maryland, this 18th day of March 1996.
    
        For the Nuclear Regulatory Commission.
    William. T. Russell,
    Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 96-6936 Filed 3-21-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
03/22/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
96-6936
Dates:
03/20/92).4
Pages:
11898-11903 (6 pages)
Docket Numbers:
Docket No. 50-029, License No. DPR-3
PDF File:
96-6936.pdf