99-6986. Williams Gas Pipelines Central, Inc.; Notice of Request Under Blanket Authorization
[Federal Register Volume 64, Number 55 (Tuesday, March 23, 1999)]
[Notices]
[Page 13983]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 99-6986]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP99-247-000]
Williams Gas Pipelines Central, Inc.; Notice of Request Under
Blanket Authorization
March 17, 1999.
Take notice that on March 10, 1999, Williams Gas Pipelines Central,
Inc. (Williams), P.O. Box 3288, Tulsa, Oklahoma 74101, filed in Docket
No. CP99-247-000, a request pursuant to Sections 157.205 and 157.212 of
the Commission's Regulations under the Natural Gas Act (18 CFR 157.205
and 157.212) for authorization to use measuring, regulating and
appurtenant facilities constructed for the delivery of Natural Gas
Policy Act Section 311 transportation gas to MAPCO Natural Gas Liquid,
Inc., a Williams affiliate, in McPherson County, Kansas, for purposes
other than Section 311 transportation, under authorization issued in
Docket No. CP82-479-000 pursuant to Section 7 of the Natural Gas Act,
all as more fully set forth in the request on file with the Commission
and open to public inspection. This filing may be viewed on the web at:
http://www.ferc.fed.us/online/rims.htm (call 202-208-2222 for
assistance).
Williams states that the cost of the facilities was approximately
$156,880 and would be reimbursed by MAPCO through the subscription of
firm transportation service.
Williams further states that this change is not prohibited by an
existing tariff and that it has sufficient capacity to accomplish the
deliveries specified without detriment or disadvantage to its other
customers.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A. Watson, Jr.
Acting Secretary.
[FR Doc. 99-6986 Filed 3-22-99; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 03/23/1999
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 99-6986
- Pages:
- 13983-13983 (1 pages)
- Docket Numbers:
- Docket No. CP99-247-000
- PDF File:
-
99-6986.pdf