[Federal Register Volume 59, Number 57 (Thursday, March 24, 1994)]
[Unknown Section]
[Page 0]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 94-7114]
[[Page Unknown]]
[Federal Register: March 24, 1994]
-----------------------------------------------------------------------
INTERSTATE COMMERCE COMMISSION
[Finance Docket No. 30186 (Sub No. 2)]
Tongue River Railroad Co.; Construction and Operation of
Additional Rail Line in Rosebud and Big Horn Counties, MT
In the Draft Environmental Impact Statement (DEIS) served July 17,
1992, the Commission's Section of Environmental Analysis (SEA)
addressed the Tongue River Railroad Company's (TRRC's) proposal to
construct and operate a 41-mile rail line from Ashland to Decker,
Montana (the Extension). The proposed rail line would serve as an
extension to TRRC's already-approved but not yet built 89-mile rail
line from Miles City to Ashland, Montana.
In the DEIS, SEA preliminarily concluded that because of the
environmental impacts associated with TRRC's proposed route, the Four
Mile Creek Alternative would be environmentally preferable should the
Commission decide to grant TRRC's construction application. However,
based on comments to the DEIS, SEA's further investigation, TRRC's
alignment changes to the proposed route, and a more comprehensive
Mitigation Plan, SEA now believes that the Four Mile Creek Alternative
would have more adverse consequences on the environment than TRRC's
current proposed route. Generally, when a substantial change is made to
the approach a Federal agency has taken in a DEIS, the rules of the
Council on Environmental Quality implementing the National
Environmental Policy Act require the preparation of a Supplement to the
DEIS [40 CFR 1502.9(c)]. Because SEA no longer believes that the Four
Mile Creek Alternative would be the environmentally preferable route if
the Commission grants TRRC's application, SEA has prepared this
Supplement to the DEIS (Supplement).
The ``no build'' alternative has been carefully considered by SEA.
This alternative would be environmentally neutral since construction
and operation of the proposed Extension and the related environmental
impacts would not occur. Because TRRC already has obtained Commission
authority to construct and operate a rail line between Miles City and
Ashland, TRRC would be able to serve new mines in the project area even
if the Commission denied the proposed Extension. Moreover, with the
``no build'' alternative, the present movement of coal from the Decker
mines would be unaffected because the Burlington Northern Railroad is
already providing service to these mines via an alternate route. In
sum, the ``no build'' alternative would preserve the environmental
status quo.
SEA invites comments on the Supplement. SEA specifically requests
comments on (1) the environmental preferability of TRRC's current
proposed route versus the Four Mile Creek Alternative; (2) the ``no
build'' alternative; and (3) any other feasible alternatives. These
comments should provide as much substantive information and supporting
evidence as possible.
SEA will consider all comments to this Supplement and the prior
comments to the DEIS before issuing a Final Environmental Impact
Statement (FEIS). The FEIS will take into account all the comments
received during the entire environmental review process and include
SEA's final environmental recommendations to the Commission. The
Commission will then consider the FEIS and the entire environmental
record in making its decision in this proceeding.
Send an original and 10 copies of comments referring to Finance
Docket No. 30186 (Sub No. 2) to: Dana White, Section of Environmental
Analysis, room 3214, Interstate Commerce Commission, Washington, DC
20423. Questions regarding this Supplement or requests for copies of
the Supplement should be directed to Ms. White or Elaine K. Kaiser,
Chief, Section of Environmental Analysis at (202) 927-6214. TDD for
hearing impaired: (202) 927-5721.
Also, a copy of the comments should be sent to TRRC's
representative: Mr. Thomas Ebzery, Village Center I, suite 165, 1500
Poly Drive, Billings, MT 59102.
Date made available to the public: March 17, 1994.
Comment due date: May 9, 1994.
By the Commission, Elaine K. Kaiser, Chief, Section of
Environmental Analysis.
Sidney L. Strickland,
Secretary.
[FR Doc. 94-7114 Filed 3-23-94; 8:45 am]
BILLING CODE 7035-01-P