97-7074. Revision to the NASA FAR Supplement to Eliminate Non-Statutory Certification Requirements
[Federal Register Volume 62, Number 57 (Tuesday, March 25, 1997)]
[Rules and Regulations]
[Pages 14035-14036]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-7074]
-----------------------------------------------------------------------
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
48 CFR Parts 1819 and 1845
Revision to the NASA FAR Supplement to Eliminate Non-Statutory
Certification Requirements
agency: National Aeronautics and Space Administration (NASA).
action: Final rule.
-----------------------------------------------------------------------
summary: This is a final rule amending the NASA FAR Supplement to
eliminate offeror and contractor certification requirements not
mandated by statute.
effective date: March 25, 1997.
for further information contact: Tom O'Toole, (202) 358-0478.
SUPPLEMENTARY INFORMATION:
Background
NASA published a proposed rule in the December 18, 1996 Federal
Register (61 FR 66643-66646) of its intent to delete a number of
offeror and contractor certification requirements in the NASA FAR
Supplement (NFS). Only editorial comments were received, and these are
considered in the final rule. The proposed changes to sections
1819.7211 and 1845.302-73 are incorporated as a final rule without
revision.
The changes to the following NFS sections listed in the proposed
rule have already been accomplished via the ongoing NFS rewrite:
1. 1816.303 Cost Sharing Contracts. Certification requirement
deleted from renumbered section 1816.303-70 in the October 7, 1996
interim rule (61 FR 52325-52347) and subsequent January 23, 1997 final
rule (62 FR 3464-3487).
2. 1823.7002 Responsibility. Section deleted in the October 29,
1996 final rule (61 FR 55753-55764).
3. 1832.7004(b) Contractual Implementation (Milestone Billing).
Section deleted in the October 29, 1996 final rule (61 FR 55765-55774).
4. 1834.005-1 Competition. Certification requirement deleted from
renumbered Subpart 1834.70 in the January 30, 1997 final rule (62 FR
4466-4492).
5. 1870.102-703, VI, Proposed Submission Information (Investigation
Acquisition System). Certification requirement deleted in renumbered
Part 1872 in the January 30, 1997 final rule (62 FR 4466-4492).
The changes to the following sections listed in the proposed rule
will be accomplished as part of the NFS rewrite in a separate final
rule:
1. 1852.223-70, Safety and Health.
2. 1852.247-73, Shipment by Government Bills of Lading.
Impact
NASA certifies that this regulation will not have a significant
economic impact on a substantial number of small entities under the
Regulatory Flexibility Act (5 U.S.C. 601 et seq.). This final rule does
not impose any reporting or record keeping requirements subject to the
Paperwork Reduction Act.
List of Subjects in 48 CFR Parts 1819 and 1845
Government procurement.
Tom Luedtke,
Deputy Associate Administrator for Procurement.
Accordingly, 48 CFR Parts 1819 and 1845 are amended as follows:
1. The authority citation for 48 CFR Parts 1819 and 1845 continues
to read as follows:
Authority: 42 U.S.C. 2473(c)(1).
PART 1819--SMALL BUSINESS AND SMALL DISADVANTAGED BUSINESS CONCERNS
1819.7211 [Amended]
2. In section 1819.7211, paragraph (b)(1) is revised to read as
follows:
1819.7211 Application process for mentor firms to participate in the
program.
(a) * * *
(b) * * *
[[Page 14036]]
(1) A statement that the mentor firm is currently performing under
at least one active approved subcontracting plan (small business
exempted) and that they are eligible, as of the date of application,
for the award of Federal contracts.
* * * * *
PART 1845--GOVERNMENT PROPERTY
1845.302-73 [Amended]
3. In section 1845.302-73(b), the first two sentences of paragraph
3 under FINDINGS are revised to read as follows:
1845.302-73 Determination and findings.
(a) * * *
(b) * * *
Findings
* * * * *
3. (If the contract effort cannot be fulfilled by any other
means, indicate why the contractor cannot provide the facilities.
For example, due to financial constraints, the contractor has
demonstrated inability to acquire the facilities; or, even though
the contractor is willing and financially able to acquire these
facilities for its own account, the contractor has stated that time
will not permit making arrangements to obtain timely delivery to
meet NASA requirements. * * *
* * * * *
[FR Doc. 97-7074 Filed 3-24-97; 8:45 am]
BILLING CODE 7510-01-M
Document Information
- Effective Date:
- 3/25/1997
- Published:
- 03/25/1997
- Department:
- National Aeronautics and Space Administration
- Entry Type:
- Rule
- Action:
- Final rule.
- Document Number:
- 97-7074
- Dates:
- March 25, 1997.
- Pages:
- 14035-14036 (2 pages)
- PDF File:
-
97-7074.pdf
- CFR: (2)
- 48 CFR 1819
- 48 CFR 1845