        Take notice that on March 9, 1998, Dale Schwarzhoff (First Seller) 
    filed a petition for adjustment under section 502(c) of the Natural Gas 
    Policy Act of 1978 (NGPA),\1\ requesting that the refund procedures in 
    the Commission's September 10, 1997 order in Docket Nos. RP97-369-000, 
    GP97-3-000, GP97-4-000, and GP97-5-000,\2\ be altered with respect to 
    Schwarzhoff's Kansas ad valorem tax refund liability.
    ---------------------------------------------------------------------------
    
        \1\ 15 U.S.C. 3142(c) (1982).
        \2\ See 80 FERC para. 61,264 (1997); order denying reh'g issued 
    January 28, 1998, 82 FERC para. 61,058 (1998).
    ---------------------------------------------------------------------------
    
        The Commission's September 10 order on remand from the D.C. Circuit 
    Court of Appeals \3\ directed first sellers under the NGPA to make 
    Kansas ad valorem tax refunds, with interest, for the period from 1983 
    to 1988. The Commission issued a January 28, 1998 order in Docket No. 
    RP98-39-001, et al. (January 28 Order),\4\ clarifying the refund 
    procedures, stating that producers could request additional time to 
    establish the uncollectability of royalty refunds, and that first 
    seller may file requests for NGPA section 502(c) adjustment relief from 
    the refund requirement and the timing and procedures for implementing 
    the refunds, based on the individual circumstances applicable to each 
    first seller.
    ---------------------------------------------------------------------------
    
        \3\ Public Service Company of Colorado v. FERC, 91 F.3d 1478 
    (D.C. 1996), cert. denied, Nos. 96-954 and 96-1230 (65 U.S.L.W. 3751 
    and 3754, May 12, 1997).
        \4\ 82 FERC para. 61,059 (1998).
    ---------------------------------------------------------------------------
    
        First Seller requests, pursuant to the Commission's January 28 
    Order, that the Commission grant First Seller and Northern Natural Gas 
    Pipeline Company (Pipeline), an extension of 90 days to allow First 
    Seller and Pipeline to resolve any dispute as to the proper amount of 
    the refund liability of First Seller for the Kansas ad valorem tax 
    reimbursements set forth in the Statement of Refunds Due (SRD) 
    addressed to Benson Mineral Group, Inc. (BMG), the Operator, or to 
    submit such dispute to FERC for resolution if the parties cannot 
    resolve the dispute within such time. In addition, First Seller also 
    request that in order to stop the accrual of interest pending 
    resolution of disputes and legal issues, that an adjustment be granted 
    to the FERC's procedures to allow First Seller to place into an escrow 
    account not only any disputed amount of the refund amount calculated by 
    Pipeline, but also principal and interest on amounts attributable to 
    production prior to October 4, 1983, and interest on all other amounts 
    claimed to be due under the SRD.
        First Seller argues that it seeks to establish these procedures to 
    ensure that it pays only that which is legitimately owed, and that it 
    will be able to recover the overpayment, if it is subsequently 
    determined that First Seller's refund liability was less than that 
    originally claimed by BMG.
        Any person desiring to be heard or to make any protest with 
    reference to said petition should on or before 15 days after the date 
    of publication in the
    
    [[Page 14457]]
    
    Federal Register of this notice, file with the Federal Energy 
    Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
    a motion to intervene or a protest in accordance with the requirements 
    of the Commission's Rules of Practice and Procedure (18 CFR 385.214, 
    385.211, 385.1105, and 385.1106). All protests filed with the 
    Commission will be considered by it in determining the appropriate 
    action to be taken but will not serve to make the protestants parties 
    to the proceeding. Any person wishing to become a party to a proceeding 
    or to participate as a party in any hearing therein must file a motion 
    to intervene in accordance with the Commission's Rule.
    David P. Boergers,
    Acting Secretary.
    [FR Doc. 98-7772 Filed 3-24-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
03/25/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-7772
Pages:
14456-14457 (2 pages)
Docket Numbers:
Docket No. SA98-20-000
PDF File:
98-7772.pdf