99-7249. Reliant Energy Gas Transmission Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 64, Number 57 (Thursday, March 25, 1999)]
    [Notices]
    [Page 14440]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-7249]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP99-249-000]
    
    
    Reliant Energy Gas Transmission Company; Notice of Request Under 
    Blanket Authorization
    
    March 19, 1999.
        Take notice that on March 11, 1999, Reliant Energy Gas Transmission 
    (REGT) formerly NorAm Gas Transmission Company (NGT), 1100 Louisiana 
    Street, Houston, Texas 77002, filed in Docket No. CP99-249-000 a 
    request pursuant to Sections 157.216 and 157.212 of the Commission's 
    Regulations (18 CFR 157.216, 157.212) under its blanket certificate 
    issued in Docket Nos. CP82-384-000 and CP82-384-001 to abandon and 
    operate certain facilities in Louisiana, all as more fully set forth in 
    the request which is on file with the Commission and open to public 
    inspection. This filing may be viewed on the web at http://
    www.ferc.fed.us/online/rims.htm (call 202-208-2222 for assistance).
        REGT specifically proposes to abandon a 1-inch meter station on 
    Line F-east in Lincoln Parish, Louisiana and to operate a 2-inch meter 
    station under Subpart G of the Regulations. It is stated that these 
    facilities were constructed on Line F-east to upgrade the 1-inch meter 
    station, solely to provide service under section 311 of the NGPA and 
    Subpart B of the Regulations on behalf of Reliant Energy Arkla, a 
    division of Reliant Energy, Inc. (Arkla). The volumes to be delivered 
    to this meter are about 56,000 Dth annually and 240 Dth on a peak day. 
    It is also stated that the meter station was upgraded on March 4, 1999, 
    at a cost of $17,870 and Arkla will reimburse REGT. The cost to abandon 
    the 1-inch station is $7,969, it is asserted.
        Any person or the Commission's Staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rule (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    date after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 99-7249 Filed 3-24-99; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
03/25/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-7249
Pages:
14440-14440 (1 pages)
Docket Numbers:
Docket No. CP99-249-000
PDF File:
99-7249.pdf