95-7542. Koch Gateway Pipeline Co.; Notice of Request Under Blanket Authorization
[Federal Register Volume 60, Number 59 (Tuesday, March 28, 1995)]
[Notices]
[Page 15911]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 95-7542]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP95-268-000]
Koch Gateway Pipeline Co.; Notice of Request Under Blanket
Authorization
March 21, 1995.
Take notice that on March 17, 1995, as supplemented on March 21,
1995, Koch Gateway Pipeline Company (Koch), P.O. Box 1478, Houston,
Texas 77251-1478, filed in Docket No. CP95-268-000 a request pursuant
to Secs. 157.205 and 157.211 of the Commission's Regulations under the
Natural Gas Act (18 CFR 157.205 and 157.211) for approval to construct
and operate approximately three miles of six-inch pipeline and a meter/
regulator station delivery tap located in DeSoto Parish, Louisiana for
delivery of natural gas to International Paper (IP), an end-user,
pursuant to Section 7(c) of the Natural Gas Act (NGA), all as more
fully set forth in the request which is on file with the Commission and
open to public inspection.
Koch requests authorization to construct and operate approximately
15,700 feet of six-inch pipeline and a six-inch meter/regulator station
which will connect with Koch's 24-inch Carthage-Sterlington line near
Mansfield, Louisiana. Koch states these facilities are required to
comply with the terms of a transportation agreement with IP to provide
it with 20,000 MMBtu of interruptible service on a peak day.
Koch indicates that it is authorized to provide interruptible
transportation to IP in Docket No. ST95-86-000. Koch states that it
provides such transportation to IP pursuant to Koch's blanket
certificate in Docket No. CP88-6-000. Koch also indicates that the
volumes delivered are within IP's certificated entitlement and that
Koch's tariff does not prohibit the construction or operation of the
proposed facilities. Koch further indicates that it has sufficient
capacity to accomplish the deliveries without detriment or disadvantage
to its other customers. It is indicated that the estimated cost of
construction is $640,000.
Any person or the Commission's Staff may, within 45 days of the
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Rules of Practice and Procedure (18 CFR
385.214), a motion to intervene and pursuant to Sec. 157.205 of the
regulations under the Natural Gas Act (18 CFR 157.205), a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activities shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn 30 days after the time allowed for filing a protest,
the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 95-7542 Filed 3-27-95; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 03/28/1995
- Department:
- Energy Department
- Entry Type:
- Notice
- Document Number:
- 95-7542
- Pages:
- 15911-15911 (1 pages)
- Docket Numbers:
- Docket No. CP95-268-000
- PDF File:
-
95-7542.pdf