95-7542. Koch Gateway Pipeline Co.; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 60, Number 59 (Tuesday, March 28, 1995)]
    [Notices]
    [Page 15911]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-7542]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP95-268-000]
    
    
    Koch Gateway Pipeline Co.; Notice of Request Under Blanket 
    Authorization
    
    March 21, 1995.
        Take notice that on March 17, 1995, as supplemented on March 21, 
    1995, Koch Gateway Pipeline Company (Koch), P.O. Box 1478, Houston, 
    Texas 77251-1478, filed in Docket No. CP95-268-000 a request pursuant 
    to Secs. 157.205 and 157.211 of the Commission's Regulations under the 
    Natural Gas Act (18 CFR 157.205 and 157.211) for approval to construct 
    and operate approximately three miles of six-inch pipeline and a meter/
    regulator station delivery tap located in DeSoto Parish, Louisiana for 
    delivery of natural gas to International Paper (IP), an end-user, 
    pursuant to Section 7(c) of the Natural Gas Act (NGA), all as more 
    fully set forth in the request which is on file with the Commission and 
    open to public inspection.
        Koch requests authorization to construct and operate approximately 
    15,700 feet of six-inch pipeline and a six-inch meter/regulator station 
    which will connect with Koch's 24-inch Carthage-Sterlington line near 
    Mansfield, Louisiana. Koch states these facilities are required to 
    comply with the terms of a transportation agreement with IP to provide 
    it with 20,000 MMBtu of interruptible service on a peak day.
        Koch indicates that it is authorized to provide interruptible 
    transportation to IP in Docket No. ST95-86-000. Koch states that it 
    provides such transportation to IP pursuant to Koch's blanket 
    certificate in Docket No. CP88-6-000. Koch also indicates that the 
    volumes delivered are within IP's certificated entitlement and that 
    Koch's tariff does not prohibit the construction or operation of the 
    proposed facilities. Koch further indicates that it has sufficient 
    capacity to accomplish the deliveries without detriment or disadvantage 
    to its other customers. It is indicated that the estimated cost of 
    construction is $640,000.
        Any person or the Commission's Staff may, within 45 days of the 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Rules of Practice and Procedure (18 CFR 
    385.214), a motion to intervene and pursuant to Sec. 157.205 of the 
    regulations under the Natural Gas Act (18 CFR 157.205), a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activities shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn 30 days after the time allowed for filing a protest, 
    the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 95-7542 Filed 3-27-95; 8:45 am]
    BILLING CODE 6717-01-M
    
    

Document Information

Published:
03/28/1995
Department:
Energy Department
Entry Type:
Notice
Document Number:
95-7542
Pages:
15911-15911 (1 pages)
Docket Numbers:
Docket No. CP95-268-000
PDF File: