96-7672. Distrigas of Massachusetts Corporation, et al.; Natural Gas Certificate Filings  

  • [Federal Register Volume 61, Number 62 (Friday, March 29, 1996)]
    [Notices]
    [Pages 14095-14097]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-7672]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP96-254-000, et al.]
    
    
    Distrigas of Massachusetts Corporation, et al.; Natural Gas 
    Certificate Filings
    
    March 22, 1996.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. Distrigas of Massachusetts Corporation
    
    [Docket No. CP96-254-000]
    
        Take notice that on March 15, 1996, Distrigas of Massachusetts 
    Corporation (DOMAC), 75 State Street, Boston, Massachusetts 02109, 
    filed in Docket No. CP96-254-000, an application pursuant to Section 
    7(c) of the Natural Gas Act and Section 157.7 and Part 157 of the 
    Commission's Regulations for a certificate of public convenience and 
    necessity to install additional vaporization capacity and to install 
    and construct additional facilities appurtenant thereto at DOMAC's 
    liquefied natural gas (LNG) terminal in Everett, Massachusetts, all as 
    more fully set forth in the application which is on file with the 
    Commission and open to public inspection.
        DOMAC seeks authorization to construct and install additional LNG 
    vaporization facilities wholly within the existing boundary of DOMAC's 
    Everett Marine Terminal. DOMAC states that the new LNG vaporization 
    system will be located in the same general area of the plant as the 
    existing vaporization facilities. There will be two vaporization 
    trains, each with a nominal capacity rating of 75,000 Mcf/d to be 
    delivered through a new 750 psig send-out system. In addition to 
    providing new vaporization capacity of 150,000 Mcf/d, the new system 
    can serve as a back-up to existing vaporizer facilities. DOMAC states 
    that it anticipates the project will have an approximate cost of $15.5 
    million and will be financed by DOMAC using cash on hand. DOMAC further 
    states that the proposed facilities will be installed to meet the 
    anticipated need for increased vaporization capacity in the fall of 
    1998. DOMAC states that it will assume 100 percent of the cost recovery 
    risk related to the project and that the project will have no impact on 
    the rates charged for DOMAC's sales services.
        DOMAC also states that it anticipates the construction of a 
    pipeline interconnection between its facilities and those of Tennessee 
    Gas Pipeline Company (Tennessee) which is the subject of a pending 
    certificate application, Docket No. CP96-164-000, that is before the 
    Commission. DOMAC states that Tennessee's proposed 7.5-mile, 20-inch 
    pipeline will directly connect Tennessee's existing Revere Lateral line 
    in Saugus, Massachusetts with DOMAC's facilities in Everett. DOMAC 
    further states that although DOMAC's proposed vaporization facilities 
    are necessary to deliver vaporized LNG into Tennessee's new pipeline at 
    750 psig, DOMAC's need for additional vaporization capacity is 
    independent of Tennessee's proposal to directly connect to the 
    facilities. DOMAC states that it intends to proceed with the expansion 
    of its vaporization capacity even in the absence of the Tennessee 
    interconnection.
        Comment date: April 12, 1996, in accordance with Standard Paragraph 
    F at the end of this notice.
    
    2. Northwest Pipeline Corporation
    
    [Docket No. CP96-258-000]
    
        Take notice that on March 18, 1996, Northwest Pipeline Corporation 
    (Northwest), 295 Chipeta Way, Salt Lake City, Utah 84108, filed in 
    Docket No. CP96-258-000 a request pursuant to Sections 157.205, 157.211 
    and 157.216 of the Commission's Regulations under the Natural Gas Act 
    (18 CFR 157.205, 157.211 and 157.216) for authorization to abandon 
    certain facilities and to construct and operate upgraded replacement 
    facilities at an existing delivery point in Benton County, Washington, 
    to accommodate deliveries of natural gas to Cascade Natural Gas Company 
    (Cascade), under Northwest's blanket certificate issued in Docket No. 
    CP82-433-000 pursuant to Section 7 of the Natural Gas Act, all as more 
    fully set forth in the request that is on file with the Commission and 
    open to public inspection.
        Northwest requests authorization to abandon facilities at the 
    Kennewick Meter Station consisting of 2 2-inch regulators, 2 4-inch 
    orifice meters and appurtenant piping and valves and a 2-inch tap. 
    Northwest proposes to abandon the regulators and meters by removal and 
    to abandon the tap in place. It is stated that Northwest proposes to 
    replace these facilities because they are undersized for the existing 
    maximum daily delivery obligation to Cascade of 12,092 dt equivalent of 
    natural gas per day.
        To replace the facilities proposed for abandonment, Northwest 
    proposes to install 2 3-inch regulators, 2 6-inch turbine meters and 
    appurtenant piping and valves and a 4-inch tap. These proposed 
    facilities would increase the maximum design capacity of the meter 
    station from 8,900 dt equivalent per day to approximately 21,830 dt 
    equivalent per day. It is estimated that the cost to remove the old 
    facilities would be $13,000, and the cost to install the replacement 
    facilities would be $371,800. It is asserted that Northwest makes 
    deliveries to Cascade under its Rate Schedules TF-1 and TF-2.
        It is stated that no customers would lose service as a result of 
    the proposed abandonment and replacement. It is further stated that 
    Northwest's tariff does not prohibit the upgrade of delivery point 
    facilities and that there would be no impact on Northwest's peak day 
    and annual deliveries. It is explained that deliveries at the Kennewick 
    delivery point would be within authorized entitlements of Cascade or 
    other shippers.
        Comment date: May 6, 1996, in accordance with Standard Paragraph G 
    at the end of this notice.
    
    3. Williams Natural Gas Company
    
    [Docket No. CP96-260-000]
    
        Take notice that on March 18, 1996, Williams Natural Gas Company 
    (Williams), P.O. Box 3288, Tulsa, Oklahoma 74101, filed in Docket No. 
    CP96-260-000 a request pursuant to Sections 157.205, 157.208 and 
    157.216 of the Commission's Regulations under the Natural Gas Act (18 
    CFR 157.205, 157.208 and 157.216) for authorization to abandon certain 
    pipeline facilities and to construct and operate replacement facilities 
    located in Cowley County, Kansas, under Williams' blanket certificate 
    issued in Docket No. CP82-479-000 pursuant to Section 7 of the Natural 
    Gas Act, all as more fully set forth in the request that is on file 
    with the Commission and open to public inspection.
        Williams requests authorization to abandon partly by reclaim and 
    partly in place approximately 7.5 miles of Williams' Dilworth-Cambridge 
    16-inch pipeline and to construct and operate
    
    [[Page 14096]]
    7.5 miles of replacement 6-inch pipeline. It is stated that this 
    proposal is a continuation of the replacement of the Dilworth-Cambridge 
    Line begun in Docket No. CP95-682-000. It is asserted that the 
    replacement of the line by 6-inch pipe will allow for more efficient 
    use of Williams' facilities. Williams proposes to uprate the line on 
    completion of its replacement from its present maximum allowable 
    operating pressure (MAOP) of 315 to 265 psig to a proposed MAOP of 720 
    psig. It is stated that the uprating of the line will eliminate the 
    need for pressure regulation and reduce related maintenance costs. It 
    is estimated that the cost to reclaim facilities would be $1,000, the 
    cost to construct the replacement facilities would be $1,644,000, and 
    the estimated salvage value would be $3,000. It is asserted that 
    Williams has sufficient capacity to make the changes without detriment 
    or disadvantage to its customers. It is stated that the present volume 
    of gas transported on the Dilworth-Cambridge pipeline is 13,400 Mcf of 
    gas per day.
        Comment date: May 6, 1996, in accordance with Standard Paragraph G 
    at the end of this notice.
    
    4. Texas Gas Transmission Corporation
    
    [Docket No. CP96-262-000]
    
        Take notice that on March 19, 1996, Texas Gas Transmission Company 
    (Texas Gas), P.O. Box 20008, Owensboro, Kentucky 42304, filed in Docket 
    No. CP96-262-000 a request pursuant Sections 157.205(b) and 157.212 of 
    the Commission's Regulations under the Natural Gas Act (18 CFR 
    157.205(b) and 157.212) for authorization to add a new delivery point 
    in Henderson County, Kentucky, to serve Western Kentucky Gas Company 
    (Western), a local distribution company, under Texas Gas' blanket 
    certificate issued in Docket No. CP82-407-000 pursuant to Section 7 of 
    the Natural Gas Act, all as more fully set forth in the request which 
    is on file with the Commission and open to public inspection.
        Texas Gas states that it has received a request from Western for a 
    new delivery point on Texas Gas' Slaughters-Evansville 10-inch Line in 
    Henderson County, Kentucky, to enable Western to render natural gas 
    service to a new customer, Hudson Foods, Inc. It is also stated that 
    the natural gas delivered to the proposed delivery point would be used 
    for service to Hudson's new chicken processing plant. Texas Gas states 
    that Western would reimburse Texas Gas for the cost of this delivery 
    point, which cost is estimated to be $81,100.
        Texas Gas further states that Western would not require any 
    increase in existing firm contract quantities to accommodate service to 
    the new delivery point. Since no increase in contract quantities has 
    been requested by Western, Texas Gas states that the service to the 
    proposed delivery point could be accomplished without detriment to 
    Texas Gas' other customers.
        It is further asserted that the natural gas volumes that would be 
    delivered at the proposed delivery point would be a maximum daily 
    quantity of 4,500 MMBtu, with a maximum annual quantity of 1,200,000 
    MMBtu.
        Comment date: May 6, 1996, in accordance with Standard Paragraph G 
    at the end of this notice.
    
    5. Michigan Gas Storage Company
    
    [Docket No. CP96-263-000]
    
        Take notice that on March 20, 1996, Michigan Gas Storage Company 
    (MGSCo), 212 West Michigan Avenue, Jackson, Michigan 49201, filed in 
    Docket No. CP96-263-000 an application pursuant to Section 7(c) of the 
    Natural Gas Act to construct and operate certain pipeline facilities in 
    the Cranberry Lake Storage Field in Clare County, Michigan and pursuant 
    to Section 7(b) of the Natural Gas Act for permission and approval to 
    abandon the pipeline facilities being replaced, all as more fully set 
    forth in the application on file with the Commission and open to public 
    inspection.
        MGSCo requests authorization to construct and operate 5.2 miles of 
    20-inch pipeline to replace 1.3 miles of 10-inch, 3.9 miles of 16-inch 
    and 5.2 miles of 8-inch pipeline in the Cranberry Lake Storage Field 
    from Station 60 to the Muskegon River Compressor Station, all located 
    in Clare County, Michigan. MGSCo states that the purpose of the 
    proposed project is to replace deteriorating pipeline and to allow for 
    efficient cleaning/inspection of the header pipeline for the storage 
    field.
        MGSCo estimates the cost of the proposed project to be $3,550,000. 
    MGSCo states that it proposes to recover the construction and operation 
    costs of the 20-inch piping replacement in a future Section 4 rate 
    filing with the Commission, on a rolled-in basis.
        Comment date: April 12, 1996, in accordance with Standard Paragraph 
    F at the end of this notice.
    
    6. Sea Robin Pipeline Company
    
    [Docket No. CP96-266-000]
    
        Take notice that on March 20, 1996, Sea Robin Pipeline Company (Sea 
    Robin), Post Office Box 2563, Birmingham, Alabama 35202-2563, filed a 
    request with the Commission in Docket No. CP96-266-000 pursuant to 
    Sections 157.205 and 157.212 of the Commission's Regulations under the 
    Natural Gas Act (NGA) for authorization to construct and operate a new 
    delivery point, to enable Sea Robin to deliver gas to Equitable Storage 
    Company (Equitable), authorized in blanket certificate issued in Docket 
    No. CP82-429-000, all as more fully set forth in the request on file 
    with the Commission and open to public inspection.
        Sea Robin proposes to construct, install and operate a new delivery 
    point at its existing Erath Compressor Station site. The delivery point 
    would be located in Sea Robin's Erath Compressor Station yard in 
    Section 41, Township 13 South, Range 4 East, in Vermillion Parish, 
    Louisiana. The delivery point would be used to deliver gas to 
    Equitable. Sea Robin states that the estimated cost of the construction 
    and installation of the delivery point facilities would be 
    approximately $434,148. Equitable has agreed to reimburse Sea Robin for 
    the total actual cost of the facilities.
        Comment date: May 6, 1996, in accordance with Standard Paragraph G 
    at the end of this notice.
    
    Standard Paragraphs
    
        F. Any person desiring to be heard or make any protest with 
    reference to said filing should on or before the comment date file with 
    the Federal Energy Regulatory Commission, 888 First Street NE., 
    Washington, D.C. 20426, a motion to intervene or a protest in 
    accordance with the requirements of the Commission's Rules of Practice 
    and Procedure (18 CFR 385.211 and 385.214) and the Regulations under 
    the Natural Gas Act (18 CFR 157.10). All protests filed with the 
    Commission will be considered by it in determining the appropriate 
    action to be taken but will not serve to make the protestants parties 
    to the proceeding. Any person wishing to become a party to a proceeding 
    or to participate as a party in any hearing therein must file a motion 
    to intervene in accordance with the Commission's Rules.
        Take further notice that, pursuant to the authority contained in 
    and subject to jurisdiction conferred upon the Federal Energy 
    Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and 
    the Commission's Rules of Practice and Procedure, a hearing will be 
    held without further notice before the Commission or its designee on 
    this filing if no motion to intervene is filed within the time required 
    herein, if the Commission on its own review of the
    
    [[Page 14097]]
    matter finds that a grant of the certificate is required by the public 
    convenience and necessity. If a motion for leave to intervene is timely 
    filed, or if the Commission on its own motion believes that a formal 
    hearing is required, further notice of such hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for the applicant to appear or be represented at 
    the hearing.
        G. Any person or the Commission's staff may, within 45 days after 
    the issuance of the instant notice by the Commission, file pursuant to 
    Rule 214 of the Commission's Procedural Rules (18 CFR 385.214) a motion 
    to intervene or notice of intervention and pursuant to Section 157.205 
    of the Regulations under the Natural Gas Act (18 CFR 157.205) a protest 
    to the request. If no protest is filed within the time allowed 
    therefore, the proposed activity shall be deemed to be authorized 
    effective the day after the time allowed for filing a protest. If a 
    protest is filed and not withdrawn within 30 days after the time 
    allowed for filing a protest, the instant request shall be treated as 
    an application for authorization pursuant to Section 7 of the Natural 
    Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-7672 Filed 3-28-96; 8:45 am]
    BILLING CODE 6717-01-P
    
    

Document Information

Published:
03/29/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-7672
Dates:
April 12, 1996, in accordance with Standard Paragraph F at the end of this notice.
Pages:
14095-14097 (3 pages)
Docket Numbers:
Docket No. CP96-254-000, et al.
PDF File:
96-7672.pdf