99-7595. Pacific Gas and Electric Company; Notice of Consideration of Issuance of Amendments to Facility Operating Licenses and Opportunity for a Hearing  

  • [Federal Register Volume 64, Number 59 (Monday, March 29, 1999)]
    [Notices]
    [Pages 14946-14950]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-7595]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket Nos. 50-275 and 50-323]
    
    
    Pacific Gas and Electric Company; Notice of Consideration of 
    Issuance of Amendments to Facility Operating Licenses and Opportunity 
    for a Hearing
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an amendment to Facility Operating License Nos. 
    NPF-80 and 82, issued to Pacific Gas and Electric Company (PG&E or the 
    licensee), for operation of the Diablo Canyon Power Plant, Units 1 and 
    2 (DCPP), located in San Luis Obispo County, California.
        The initial notice of consideration of issuance of amendment to 
    facility operating license and opportunity for hearing was originally 
    published in the Federal Register (63 FR 55152) on October 14, 1998. 
    The information included in the supplemental letters indicates that the 
    original notice, that included 13 proposed beyond-scope issues (BSIs) 
    to the Improved Technical Specifications (ITS) conversion, needs to be 
    expanded (to add 15 new BSIs) and revised (to delete 8 previous BSIs) 
    to include a total of 20 BSIs. This notice supercedes the previous 
    notice.
        The proposed amendment, requested by the licensee in a letter dated 
    June 2, 1997, as supplemented by letters dated January 9, June 25, 
    August 5, August 28, September 25, October 16, October 23, November 25, 
    December 4, December 17, and December 30, 1998, and February 24 and 
    March 10, 1999, would represent a full conversion from the current 
    Technical Specifications (CTS) to a set of ITS based on NUREG-1431, 
    ``Standard Technical Specifications, Westinghouse Plants,'' Revision 1, 
    dated April 1995. NUREG-1431 has been developed by the Commission's 
    staff through working groups composed of both NRC staff members and 
    industry representatives, and has been endorsed by the staff as part of 
    an industry-wide initiative to standardize and improve the Technical 
    Specifications (TSs) for nuclear power plants. As part of this 
    submittal, the licensee has applied the criteria contained in the 
    Commission's ``Final Policy Statement on Technical Specification 
    Improvements for Nuclear Power Reactors (Final Policy Statement),'' 
    published in the Federal Register on July 22, 1993 (58 FR 39132), to 
    the CTS, and, using NUREG-1431 as a basis, proposed an ITS for DCPP. 
    The criteria in the Final Policy Statement were subsequently added to 
    10 CFR 50.36, ``Technical Specifications,'' in a
    
    [[Page 14947]]
    
    rule change that was published in the Federal Register on July 19, 1995 
    (60 FR 36953) and became effective on August 18, 1995.
        This conversion is a joint effort in concert with three other 
    utilities: Texas Utilities Electric for Comanche Peak Steam Electric 
    Station, Units 1 and 2 (Docket Nos. 50-445 and 446); Union Electric 
    Company for Callaway Plant (Docket No. 50-483); and Wolf Creek Nuclear 
    Operating Corporation for Wolf Creek Generating Station (Docket No. 50-
    482). This joint effort includes a common methodology for the licensees 
    in marking-up the CTS and NUREG-1431 Specifications, and the NUREG-1431 
    Bases, that has been accepted by the staff. This includes the 
    convention that, if the words in a CTS specification are not the same 
    as the words in the ITS specification but they mean the same or have 
    the same requirements as the words in the ITS specification, the 
    licensees do not indicate or describe a change to the CTS.
        This common methodology is discussed at the end of Enclosure 2, 
    ``Mark-Up of Current TS''; Enclosure 5a, ``Mark-Up of NUREG-1431 
    Specifications''; and Enclosure 5b, ``Mark-Up of NUREG-1431 Bases'', 
    for each of the 14 separate ITS sections that were submitted with the 
    licensee's application. For each of the 14 ITS sections, there is also 
    the following: Enclosure 1, the cross reference table, sorted by CTS 
    and ITS Specifications; Enclosure 3, the description of the changes to 
    the CTS section and the comparison table showing which plants (of the 
    four licensees in the joint effort) that each change applies to; 
    Enclosure 4, the no significant hazards consideration (NSHC) of 10 CFR 
    50.91 for the changes to the CTS with generic NSHCs for administrative, 
    more restrictive, relocation, and moving-out-of-CTS changes, and 
    individual NSHCs for less restrictive changes and with the organization 
    of the NSHC evaluation discussed in the beginning of the enclosure; and 
    Enclosure 6, the descriptions of the differences from NUREG-1431 
    specifications and the comparison table showing which plants (of the 
    four licensees in the joint effort) that each difference applies to. 
    Another convention of the common methodology is that the technical 
    justifications for the less restrictive changes are included in the 
    NSHCs.
        The licensee has categorized the proposed changes to the CTS into 
    four general groupings. These groupings are characterized as 
    administrative changes, relocated changes, more restrictive changes and 
    less restrictive changes.
        Administrative changes are those that involve restructuring, 
    renumbering, rewording, interpretation and complex rearranging of 
    requirements and other changes not affecting technical content or 
    substantially revising an operating requirement. The reformatting, 
    renumbering and rewording process reflects the attributes of NUREG-1431 
    and does not involve technical changes to the existing TSs. The 
    proposed changes include: (a) Providing the appropriate numbers, etc., 
    for NUREG-1431 bracketed information (information that must be supplied 
    on a plant-specific basis, and which may change from plant to plant), 
    (b) identifying plant-specific wording for system names, etc., and (c) 
    changing NUREG-1431 section wording to conform to existing licensee 
    practices. Such changes are administrative in nature and do not impact 
    initiators of analyzed events or assumed mitigation of accident or 
    transient events.
        Relocated changes are those involving relocation of requirements 
    and surveillances for structures, systems, components, or variables 
    that do not meet the criteria for inclusion in the TSs. Relocated 
    changes are those current TSs requirements that do not satisfy or fall 
    within any of the four criteria specified in the Commission's policy 
    statement and may be relocated to appropriate licensee-controlled 
    documents.
        The licensee's application of the screening criteria is described 
    in Attachment 2 to its June 2, 1997, submittal, which is entitled, 
    ``General Description and Assessment.'' The affected structures, 
    systems, components or variables are not assumed to be initiators of 
    analyzed events and are not assumed to mitigate accident or transient 
    events. The requirements and surveillances for these affected 
    structures, systems, components, or variables will be relocated from 
    the TS to administratively controlled documents such as the quality 
    assurance program, the Final Safety Analysis Report (FSAR), the ITS 
    Bases, the Equipment Control Guidelines (EGC) that is incorporated by 
    reference in the FSAR, the Core Operating Limits Report (COLR), the 
    Offsite Dose Calculation Manual (ODCM), the Inservice Testing (IST) 
    Program, or other licensee-controlled documents. Changes made to these 
    documents will be made pursuant to 10 CFR 50.59 or other appropriate 
    control mechanisms, and may be made without prior NRC review and 
    approval. In addition, the affected structures, systems, components, or 
    variables are addressed in existing surveillance procedures that are 
    also subject to 10 CFR 50.59. These proposed changes will not impose or 
    eliminate any requirements.
        More restrictive changes are those involving more stringent 
    requirements compared to the CTS for operation of the facility. These 
    more stringent requirements do not result in operation that will alter 
    assumptions relative to the mitigation of an accident or transient 
    event. The more restrictive requirements will not alter the operation 
    of process variables, structures, systems, and components described in 
    the safety analyses. For each requirement in the CTS that is more 
    restrictive than the corresponding requirement in NUREG-1431 that the 
    licensee proposes to retain in the ITS, they have provided an 
    explanation of why they have concluded that retaining the more 
    restrictive requirement is desirable to ensure safe operation of the 
    facility because of specific design features of the plant.
        Less restrictive changes are those where CTS requirements are 
    relaxed or eliminated, or new plant operational flexibility is 
    provided. The more significant ``less restrictive'' requirements are 
    justified on a case-by-case basis. When requirements have been shown to 
    provide little or no safety benefit, their removal from the TSs may be 
    appropriate. In most cases, relaxations previously granted to 
    individual plants on a plant-specific basis were the result of (a) 
    generic NRC actions, (b) new NRC staff positions that have evolved from 
    technological advancements and operating experience, or (c) resolution 
    of the Owners Groups' comments on the Improved Standard Technical 
    Specifications. Generic relaxations contained in NUREG-1431 were 
    reviewed by the staff and found to be acceptable because they are 
    consistent with current licensing practices and NRC regulations. The 
    licensee's design will be reviewed to determine if the specific design 
    basis and licensing basis are consistent with the technical basis for 
    the model requirements in NUREG-1431, thus providing a basis for these 
    revised TS, or if relaxation of the requirements in the current TS is 
    warranted based on the justification provided by the licensee.
        These administrative, relocated, more restrictive, and less 
    restrictive changes to the requirements of the CTS do not result in 
    operations that will alter assumptions relative to mitigation of an 
    analyzed accident or transient event.
        In addition to the proposed changes solely involving the 
    conversion, there are also changes proposed that are
    
    [[Page 14948]]
    
    differences to the requirements in both the CTS and the Improved 
    Standard Technical Specifications (NUREG-1431). The first five BSIs 
    were included in the previous (superceded notice) and still apply to 
    the conversion, however there are fourteen additional BSIs. The 
    additional beyond-scope issues (BSIs) are discussed in the licensee's 
    response to requests for additional information (RAIs) from the NRC 
    staff. These proposed BSIs to the ITS conversion are as follows:
        1. ITS 3.1.7. Adds a new action for more than one digital rod 
    position indicator (DRPI) per group inoperable.
        2. ITS Surveillance Requirements (SR) 3.2.1.1 and 3.2.1.2. Changes 
    the frequency to allow 24 hours for verifying that the axial heat flux 
    hot channel factor is within limit after achieving equilibrium 
    conditions.
        3. ITS SR 3.6.3.7. A note is added to not require leak rate test of 
    containment purge valves with resilient seals when penetration flow 
    path is isolated by test-tested blank flange.
        4. ITS 3.1.3 and 5.6.5. Adds moderator temperature coefficient to 
    the core operating limits report.
        5. ITS 3.9.1 and 5.6.5. Adds refueling boron concentration to the 
    core operating limits report.
        The format for the fifteen BSIs listed below is the associated 
    change number, RAI number, RAI response submittal date, and description 
    of the change.
        6. Change 2-17-LS-1 (CTS 6.0) in the application and difference 
    5.5-14 to the Improved Standard Technical Specifications (ITS 5.0), 
    question Q5.5-2, response letter dated September 25, 1998. The proposed 
    change adds an allowance to CTS SR 6.8.4.i for the reactor coolant pump 
    flywheel inspection program (ITS 5.5.7) to permit an exception to the 
    examination requirements specified in the CTS SR (i.e., regulatory 
    position C.4.b of NRC Regulatory Guide (RG) 1.14, Revision 1) that is 
    consistent with WCAP-14535, ``Topical Report on Reactor Coolant Pump 
    Flywheel Inspection Elimination.''
        7. Change 1-22-M (CTS 3/4.3), question Q3.3-49, response letter 
    dated December 4, 1998. The proposed change is a revision to the 
    original application. Quarterly channel operational tests (COTs) would 
    be added to CTS Table 4.3-1 for the power range neutron flux-low and 
    intermediate range neutron flux. The CTS only require a COT prior to 
    startup for these functions. New Note 19 would be added to require that 
    the new quarterly COT be performed within 12 hours after reducing power 
    below P-10 for the power range and intermediate range instrumentation 
    (P-10 is the dividing point marking the applicability for these trip 
    functions), if not performed within the previous 92 days. New Note 20 
    would be added to state that the P-6 and P-10 interlocks are verified 
    to be in their required state during all COTs on the power range 
    neutron flux-low and intermediate range neutron flux trip functions.
        8. Change 1-9-A (CTS 6.0), question Q5.2-1, response letter dated 
    September 25, 1998. A new administrative change is added. The CTS 
    6.2.2.f requirements concerning overtime would be replaced by a 
    reference to administrative procedures for the control of working 
    hours.
        9. Change 1-15-A (CTS 6.0), question Q5.2-1, response letter dated 
    September 25, 1998. A new administrative change is added. The proposed 
    change would revise CTS 6.2.4 to eliminate the title of Shift Technical 
    Advisor. The engineering expertise is maintained on shift, but a 
    separate individual would not be required as allowed by a Commission 
    Policy Statement.
        10. Change 2-18-A (CTS 6.0), question Q5.2-1, response letter dated 
    September 25, 1998. A new administrative change is added. The dose rate 
    limits in CTS 6.8.4.g on the Radioactive Effluent Controls Program for 
    releases to areas beyond the site boundary would be revised to reflect 
    10 CFR Part 20 requirements.
        11. Change 2-22-A (CTS 6.0), question Q5.2-1, response letter dated 
    September 25, 1998. A new administrative change is added. The 
    requirements in CTS 6.8.4.g on the Radioactive Effluents Controls 
    Program would be revised to include clarification statements denoting 
    that the provisions of CTS 4.0.2 and 4.0.3, which allow extensions to 
    surveillance frequencies, are applicable to these activities.
        12. Change 3-11-A (CTS 6.0), question Q5.2-1, response letter dated 
    September 25, 1998. The proposed change is a revision to the original 
    application. CTS 6.12, which provides high radiation area access 
    control alternatives pursuant to 10 CFR 20.203(c)(2), would be revised 
    to meet the current requirements in 10 CFR Part 20 and the guidance in 
    NRC RG 8.38, ``Control of Access to High and Very High Radiation Areas 
    in Nuclear Power Plants,'' on such access controls.
        13. Change 3-18-LS-5 (CTS 6.0), question Q5.2-1, response letter 
    dated September 25, 1998. A new less restrictive change is added. The 
    CTS 6.9.1.7 requirement to provide documentation of all challenges to 
    the power operated relief valves (PORVs) and safety valves on the 
    reactor coolant system would be deleted. This is based on NRC Generic 
    Letter 97-02, ``Revised Contents of the Monthly Operating Report,'' 
    which reduced the requirements for submitting such information to the 
    NRC. The GL did not include these valves for information to be 
    submitted.
        14. Change 4-8-LS-34 (CTS 3/4.4), question Q3.4.11-2, response 
    letter dated September 25, 1998. The proposed change was requested in 
    the original application. The proposed change would limit the CTS SRs 
    4.4.4.1.a and 4.4.4.2 requirements to perform the 92-day surveillance 
    of the pressurizer PORV block valves and the 18-month surveillance of 
    the pressurizer PORVs (i.e., perform one complete cycle of each valve) 
    to only Modes 1 and 2.
        15. Change 4-9-LS-36 (CTS 3/4.4), question Q3.4.11-4, response 
    letter dated September 25, 1998. The proposed change is added. The 
    proposed change would limit the CTS 4.4.4.2 requirement to perform the 
    92-day surveillance of the pressurizer PORV block valves in that the SR 
    would not be performed if the PORV block valve is closed to meet Action 
    a of CTS LCO 3.4.4. Action a is for an PORV being inoperable, but 
    capable of being cycled.
        16. Change 1-60-A (CTS 3/4.3), question TR 3.3-007, followup items 
    letter dated December 30, 1998. A new administrative change (identified 
    as TR 3.3-007 on the marked up pages) is added to be identified as 
    Change 1-60-A to the CTS. The change would revise the frequency for 
    performing the trip actuating device operational test (TADOT) in CTS 
    Table 4.3-1 for the turbine trip (Functional units 17.a and 17.b) to be 
    consistent with the modes for which the surveillance is required. This 
    would add a footnote to the TADOT that states ``Prior to exceeding the 
    P-9 interlock whenever the unit has been in Mode 3.''
        17. Change 1-18-LS-11 (CTS 3/4.8). The proposed change was 
    requested in the original application and addressed in Q3.8.1-18 of the 
    March 10, 1999 letter. The change would revise the diesel generator 
    (DG) loading requirements for the load rejection test in CTS SR 
    4.8.1.1.2.b.4 to specify a range of acceptable loads in kW without 
    tripping instead of specifying only a single minimum acceptable kW 
    load. The CTS require that the minimum load for the load rejection test 
    in SR 4.8.1.1.2.b.4 is 2484 kW and the proposed range of loads is 
    2370 kW and  2610 kW.
        18. Change 1-27-LS-9 (CTS 3/4.8). The proposed change was requested 
    in the original application and addressed in Q3.8.1-18 of the March 10, 
    1999,
    
    [[Page 14949]]
    
    letter. The change would increase the maximum allowable DG voltage 
    following load rejection in CTS SR 4.8.1.1.2.b.4 from 4580 to 6200 
    volts.
        19. Change 1-76-LS-29 (CTS 3/4.8). The proposed change is added and 
    addressed in Q3.8.1-33 of the March 10, 1999, letter. The change would 
    remove the wording ``during shutdown'' from the frequency of CTS SR 
    4.8.1.1.1.b.1 for manual bus transfers, SR 4.8.1.1.2b.4 for emergency 
    diesel generator (EDG) full load testing, and SR 4.8.1.1.2.b.8 for the 
    EDG 24-hour load run testing. The change will facilitate post 
    maintenance testing of an EDG without requiring a plant shutdown.
        20. Change 1-3-LS1, (CTS 3/4.3), question Q 1-B GEN, response 
    letter dated December 4, 1998. The proposed change would incorporate 
    WCAP 13632-P-A, ``Eliminate Response Time Testing of Pressure 
    Sensors,'' into CTS SR 4.3.1.2 and SR 4.3.2.2, to state that the 
    function shall be ``verified'' rather than ``demonstrated.'' This 
    changes the Bases for ITS SR 3.3.1.16 and SR 3.3.2.10 to allow the 
    elimination of pressure sensor response time testing.
        Before issuance of the proposed license amendments, the Commission 
    will have made findings required by the Atomic Energy Act of 1954, as 
    amended (the Act) and the Commission's regulations.
        By April 28, 1999, the licensee may file a request for a hearing 
    with respect to issuance of the amendments to the subject facility 
    operating licenses and any person whose interest may be affected by 
    this proceeding and who wishes to participate as a party in the 
    proceeding must file a written request for a hearing and a petition for 
    leave to intervene. Requests for a hearing and a petition for leave to 
    intervene shall be filed in accordance with the Commission's ``Rules of 
    Practice for Domestic Licensing Proceedings'' in 10 CFR Part 2. 
    Interested persons should consult a current copy of 10 CFR 2.714 which 
    is available at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room located at the California Polytechnic State University, 
    Robert E. Kennedy Library, Government Documents and Maps Department, 
    San Luis Obispo, California 93407. If a request for a hearing or 
    petition for leave to intervene is filed by the above date, the 
    Commission or an Atomic Safety and Licensing Board, designated by the 
    Commission or by the Chairman of the Atomic Safety and Licensing Board 
    Panel, will rule on the request and/or petition; and the Secretary or 
    the designated Atomic Safety and Licensing Board will issue a notice of 
    hearing or an appropriate order.
        As required by 10 CFR 2.714, a petition for leave to intervene 
    shall set forth with particularity the interest of the petitioner in 
    the proceeding, and how that interest may be affected by the results of 
    the proceeding. The petition should specifically explain the reasons 
    why intervention should be permitted with particular reference to the 
    following factors: (1) the nature of the petitioner's right under the 
    Act to be made a party to the proceeding; (2) the nature and extent of 
    the petitioner's property, financial, or other interest in the 
    proceeding; and (3) the possible effect of any order which may be 
    entered in the proceeding on the petitioner's interest. The petition 
    should also identify the specific aspect(s) of the subject matter of 
    the proceeding as to which petitioner wishes to intervene. Any person 
    who has filed a petition for leave to intervene or who has been 
    admitted as a party may amend the petition without requesting leave of 
    the Board up to 15 days prior to the first prehearing conference 
    scheduled in the proceeding, but such an amended petition must satisfy 
    the specificity requirements described above.
        Not later than 15 days prior to the first prehearing conference 
    scheduled in the proceeding, a petitioner shall file a supplement to 
    the petition to intervene which must include a list of the contentions 
    which are sought to be litigated in the matter. Each contention must 
    consist of a specific statement of the issue of law or fact to be 
    raised or controverted. In addition, the petitioner shall provide a 
    brief explanation of the bases of the contention and a concise 
    statement of the alleged facts or expert opinion which support the 
    contention and on which the petitioner intends to rely in proving the 
    contention at the hearing. The petitioner must also provide references 
    to those specific sources and documents of which the petitioner is 
    aware and on which the petitioner intends to rely to establish those 
    facts or expert opinion. Petitioner must provide sufficient information 
    to show that a genuine dispute exists with the applicant on a material 
    issue of law or fact. Contentions shall be limited to matters within 
    the scope of the amendment under consideration. The contention must be 
    one which, if proven, would entitle the petitioner to relief. A 
    petitioner who fails to file such a supplement which satisfies these 
    requirements with respect to at least one contention will not be 
    permitted to participate as a party.
        Those permitted to intervene become parties to the proceeding, 
    subject to any limitations in the order granting leave to intervene, 
    and have the opportunity to participate fully in the conduct of the 
    hearing, including the opportunity to present evidence and cross-
    examine witnesses.
        A request for a hearing or a petition for leave to intervene must 
    be filed with the Secretary of the Commission, U.S. Nuclear Regulatory 
    Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
    Adjudications Staff, or may be delivered to the Commission's Public 
    Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, 
    by the above date. A copy of the petition should also be sent to the 
    Office of the General Counsel, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555-0001, and to Christopher J. Warner, Esq., Pacific 
    Gas & Electric Company, P.O. Box 7442, San Francisco, California 94120, 
    attorney for the licensee.
        Nontimely filings of petitions for leave to intervene, amended 
    petitions, supplemental petitions and/or requests for hearing will not 
    be entertained absent a determination by the Commission, the presiding 
    officer or the presiding Atomic Safety and Licensing Board that the 
    petition and/or request should be granted based upon a balancing of the 
    factors specified in 10 CFR 2.714(a)(1)(I)-(v) and 2.714(d).
        If a request for a hearing is received, the Commission's staff may 
    issue the amendment after it completes its technical review and prior 
    to the completion of any required hearing if it publishes a further 
    notice for public comment of its proposed finding of no significant 
    hazards consideration in accordance with 10 CFR 50.91 and 50.92.
        For further details with respect to this action, see the 
    application for amendment dated June 2, 1997, and supplemental letters 
    dated January 9, June 25, August 5, August 28, September 25, October 
    16, October 23, November 25, December 4, December 17, and December 30, 
    1998, and February 24 and March 10, 1999, which are available for 
    public inspection at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room located at the California Polytechnic State University, 
    Robert E. Kennedy Library, Government Documents and Maps Department, 
    San Luis Obispo, California 93407.
    
        Dated at Rockville, Maryland, this 23rd day of March 1999.
    
    
    [[Page 14950]]
    
    
        For the Nuclear Regulatory Commission.
    Steven D. Bloom,
    Project Manager, Project Directorate IV-2, Division of Licensing 
    Project Management, Office of Nuclear Reactor Regulation.
    [FR Doc. 99-7595 Filed 3-26-99; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
03/29/1999
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
99-7595
Pages:
14946-14950 (5 pages)
Docket Numbers:
Docket Nos. 50-275 and 50-323
PDF File:
99-7595.pdf