E6-4547. Gold Camp Road Final Plan/Environmental Impact Statement, Supplemental Information Report and Record of Decision #2
-
Start Preamble
AGENCY:
Forest Service, USDA.
ACTION:
Notice of availability and decision.
SUMMARY:
In accordance with the National Environmental Policy Act, the Pike National Forest of the Rocky Mountain Region of the Forest Service announces availability of the Final Plan and Final Environmental Impact Statement (Final Plan/EIS), Supplemental Information Report (SIR) and Record of Decision #2 (ROD #2) for the Gold Camp Road. The Forest Service is also announcing the agency's decision to restore and open a collapsed railroad tunnel and reopen a closed section of Gold Camp Road to one-way traffic, with a third party partner to operate the 8.5-mile segment of road (Modified Alternative E). The objective of the management plan for the road is to best accommodate public use and access to National Forest System lands and nearby private in-holdings while maintaining public safety and the historic character of the road. The affected road segment has been closed since 1988 for safety reasons.
On December 6, 2005, the Forest Service withdrew the original ROD. During this initial appeal process, five appeals were received. The Forest Service contacted each appellant and notified them that a ROD #2 would be issued and a new appeal process will be started.
No changes were made to the Final Plan/EIS, however, a Supplemental Information Report (SIR) is incorporated into the Final Plan/EIS. The SIR does not introduce new information, rather provides a greater detailed understanding of contents within the Final Plan/EIS and the intended effects they have on the Modified Alternative E.
DATES:
The appeal period for the decision will be 45 days from the date of publication in the Pueblo Chieftain Newspaper on April 2, 2006. The appeal period will be 45 consecutive calendar days and closing at midnight on May 17, 2006.
Document Availability: The Final Plan/EIS, SIR and ROD #2 are available on the Internet at http://www.fs.fed.us/r2/psicc/projects/gold_camp/. Copies of the Final Plan/EIS, SIR and ROD #2 may be obtained by contacting the Pikes Peak Ranger District, 601 S. Weber St., Colorado Springs, CO 80903. Phone number is 719-636-1602.
Appeal Process: Must be postmarked, delivered or electronic mail received before midnight on May 17, 2006. Notice of Appeal may be sent by U.S Mail to: USDA-Forest Service, Rocky Mountain Region, Attn: Appeals Deciding Officer, P.O. Box 25127, Lakewood, Colorado 80225. Notice of Appeal sent by other than U.S. Mail or dropped off in person to: Attn: Appeals Deciding Officer, U.S.D.A. Forest Service—Rocky Mountain Region, 740 Simms Street, Lakewood CO. 80401. Electronic Appeals may be sent to: appeals-rocky-mountain-regional-office@fs.fed.us.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Frank Landis, Supervisory Outdoor Recreation Planner, Pikes Peak Ranger District, at the address listed above or by telephone at 719-477-4203.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
The Final Plan/EIS, SIR and ROD #2 are also available for inspection at the following public libraries in Colorado:
Penrose Public Library—20 N. Cascade Ave., Colorado Springs, CO 80903 East Library—5550 N. Union Blvd., Colorado Springs, CO 80918
The Forest Service announced in the Federal Register (69 FR 39401, June 30, 2004) that the agency intended to prepare an EIS addressing the possible Federal action of preparing a plan for the Gold Camp Road and inviting comments on the scope of the EIS. Comments were received from April 12 through August 17, 2004 and were considered in the Draft Plan/EIS.
Notices of availability were published in the Federal Register for the Gold Camp Road Draft Plan/EIS by the Forest Service (70 FR 2605, January 14, 2005) and the EPA (70 FR 4119, January 28, 2005). Comments were accepted on the Draft Plan/EIS through March 29, 2005. Comments were considered and the Final Plan/EIS was prepared based on agency and public input. The Final Plan/EIS contains a new preferred alternative that incorporates elements of three of the other action alternatives.
A ROD #2 accompanies the Final Plan/EIS and SIR. The ROD #2 accompanying the Final Plan/EIS and SIR are subject to appeal pursuant to 36 CFR part 215.
Reviewers are obligated to structure their participation in the National Environmental Policy Act process so that it is meaningful and alerts the agency to the reviewer's position and contentions, [Vermont Yankee Nuclear Power Corp. v. NRDS. 435 U.S. 519, 553, (1978)]. Environmental objections that could have been raised at the draft stage may be waived if not raised until after completing the Final EIS [City of Angoon v. Hodel (9th Circuit 1986) and Wisconsin Heritages Inc. v. Harris 490 F. Suppl. 1334, 1338 (E.D. Wis. 1980)].
This notice is provided pursuant to federal regulations implementing the National Environmental Policy Act (40 CFR 1506.6).
Start SignatureDated: March 17, 2006.
Robert J. Leaverton,
Forest Supervisor.
[FR Doc. E6-4547 Filed 3-28-06; 8:45 am]
BILLING CODE 3410-ES-P
Document Information
- Published:
- 03/29/2006
- Department:
- Forest Service
- Entry Type:
- Notice
- Action:
- Notice of availability and decision.
- Document Number:
- E6-4547
- Dates:
- The appeal period for the decision will be 45 days from the date of publication in the Pueblo Chieftain Newspaper on April 2, 2006. The appeal period will be 45 consecutive calendar days and closing at midnight on May 17, 2006.
- Pages:
- 15693-15693 (1 pages)
- PDF File:
- e6-4547.pdf