98-8375. Bonneville Power Administration South Oregon Coast Reinforcement Project  

  • [Federal Register Volume 63, Number 61 (Tuesday, March 31, 1998)]
    [Notices]
    [Pages 15391-15392]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-8375]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Bonneville Power Administration
    
    
    Bonneville Power Administration South Oregon Coast Reinforcement 
    Project
    
    AGENCY: Bonneville Power Administration (BPA), Department of Energy 
    (DOE).
    
    ACTION: Notice of intent to prepare an environmental impact statement 
    (EIS).
    
    -----------------------------------------------------------------------
    
    SUMMARY: Bonneville Power Administration proposes to build a 500-
    kilovolt (kV) transmission line and new substation to reinforce 
    electrical service to the southern coast of the state of Oregon. Nucor 
    Steel, a division of Nucor Corporation, may build a new steel mill in 
    the Coos Bay/North Bend, Oregon, area. This plant would require a peak 
    load of 150 megawatts (MW) and an instantaneous peak of 225 MW. The 
    existing transmission system to the area does not have the capacity to 
    serve this potential load and other anticipated load growth on the 
    south coast of Oregon. This project will look at providing a 
    transmission path to serve this load. The power supplier for this load 
    is subject to state utility regulations.
        The State of Oregon has agreed to provide BPA funding to 
    investigate solutions to reinforce the transmission system to the South 
    Oregon Coast area and to support industrial development. If Nucor Steel 
    decides not to build the steel mill, BPA will stop pre-proposal 
    activities and inform the public and agencies that the environmental 
    process has been suspended.
        Potential Federal cooperating agencies include the U.S. Department 
    of Interior, U.S. Bureau of Land Management; the U.S. Department of 
    Agriculture, U.S. Forest Service; and the U.S. Army Corps of Engineers. 
    In accordance with National Environmental Policy Act requirements, BPA 
    and the cooperating agencies will prepare an EIS to inform 
    decisionmakers about potential environmental effects of the proposal. 
    The environmental analysis will cover the proposed transmission line, a 
    new BPA substation, and related actions including: construction of the 
    Nucor Steel plant; a 230-kV transmission line that would connect the 
    new BPA substation to PacifiCorp's Isthmus Substation south of Coos 
    Bay; and two new 230-kV transmission lines connecting the new BPA 
    substation to a new substation at the plant site.
    
    DATES: Interested and affected members of the public such as 
    landowners, special interest groups, tribes, state and local 
    governments, utilities, and community groups are invited to help BPA 
    and the cooperating agencies identify alternatives, environmental 
    resources, and issues to be addressed in the draft EIS. Information to 
    explain the proposal, the environmental process, and how to participate 
    will be sent to interested or potentially affected members of the 
    public at the beginning of the scoping period. Three BPA-sponsored 
    scoping meetings will be held: Tuesday, April 14, at the Creswell 
    Community Center, 99 South First, Creswell, Oregon; Wednesday, April 
    15, at the Masonic Lodge Hall, 247 First Street, in Elkton, Oregon; and 
    Thursday, April 16, at the North Bend Community Center, 2222 Broadway, 
    North Bend, Oregon. Meetings will be held from 4-8 p.m. Meetings will 
    have an open-house format, with project material available for public 
    review. BPA, the cooperating agencies, the State of Oregon, Nucor 
    Steel, and PacifiCorp staff will answer questions. BPA will accept 
    verbal and written comments. The time and place of scoping meetings 
    will be announced in information being sent to interested members of 
    the public and local newspapers. Written comments before, during, or 
    after scoping meetings should be sent to the Communications Office at 
    the address below. The close of the comment period will be announced in 
    the pre-meeting information and at the public meetings.
        BPA, in conjunction with the cooperating agencies, plans to file 
    and distribute a draft EIS for public review in August 1998. BPA, the 
    cooperating agencies, and the State of Oregon will hold public meetings 
    in local communities to give the public an opportunity to review and 
    comment on the draft EIS.
    
    ADDRESSES: BPA invites participation, comments, and suggestions on the 
    proposed scope of the draft EIS. Send comment letters, requests to be 
    placed on the project mail list, and requests for more information to 
    the Communications Office, Bonneville Power Administration--ACS, P.O. 
    Box 12999, Portland, Oregon, 97212, or call 503-230-3478, toll-free 1-
    800-622-4519, or fax 503-230-3984. Comments may also be sent to the BPA 
    Internet address: comment@bpa.gov. Documents can be requested by 
    calling toll-free 1-800-622-4520.
    
    FOR FURTHER INFORMATION CONTACT: Laurens Driessen, Project Manager, 
    Bonneville Power Administration--TNF-3, P.O. Box 3621, Portland, 
    Oregon, 97208-3621. E-mail requests or questions should be sent to 
    lcdriessen@bpa.gov, or call toll-free 1-800-662-6963. You may also 
    contact Ken Barnhart, Environmental Project Manager, Bonneville Power 
    Administration--EC, P.O. Box 3621, Portland, Oregon, 97208-3621. E-mail 
    requests or questions should be sent to kabarnhart@bpa.gov, or call 
    toll-free 1-800-662-6963.
    
    SUPPLEMENTARY INFORMATION: The southern Oregon coast (from south of 
    Newport, Oregon, to the California-Oregon border and west of Eugene and 
    Roseburg, Oregon) is served from a 115-kV and a 230-kV transmission 
    line out of Lane Substation (near Eugene, Oregon), a 230-kV 
    transmission line from Santiam Substation (south of Salem, Oregon), and 
    a 230-kV transmission line from Dixonville (near Roseburg, Oregon). The 
    critical operating period for the Oregon coast is winter. Normal winter 
    load forecasts for the southern Oregon coast in the year 2000 show 
    about 720 MW of flow to the coast on these transmission lines to 
    support the area's winter load. With all lines in service, the existing 
    transmission system can support about 835 MW of flow on these lines. If 
    the Dixonville 230-kV transmission line is lost for any reason, the 
    system capacity is about 765 MW. Assuming 1.5 percent annual load 
    growth for this area (without the added load of the steel mill), a 
    transmission project may be required in the year 2004 to support the 
    southern Oregon coast for the loss of the Dixonville-Reston 230-kV 
    transmission line. According to existing BPA planning criteria, all 
    load must be served for the loss of a single
    
    [[Page 15392]]
    
    transmission line or transformer for all load conditions to maintain 
    reliable service.
        The proposed Nucor Steel mill would require an instantaneous peak 
    load of 225 MW for its arc furnace. The expected annual load growth 
    with the new mill is about 3 percent. The existing transmission system 
    cannot serve the new plant and the expected load growth. Furthermore, 
    the existing system is not capable of suppressing voltage changes 
    induced by the arc furnace.
    
    Alternatives Proposed for Consideration
    
        BPA has been studying ways to reinforce the transmission system. 
    Several options for adding new 230-kV transmission lines and series 
    compensation were studied. These options cannot provide the system 
    reliability requirements needed, and the costs for adding three 230-kV 
    transmission lines and series compensation are comparable to a new 500-
    kV transmission line. A new 500-kV line is needed to eliminate flickers 
    induced by the arc furnace.
        Potential routes for a 500-kV transmission line have been developed 
    in cooperation with PacifiCorp and Federal, state and local agencies. 
    Three routes that parallel existing transmission lines are being 
    studied. The first route would follow an existing BPA transmission line 
    that begins at BPA's Alvey Substation near Goshen, Oregon, west to near 
    Florence, Oregon, then would follow an existing BPA transmission line 
    south through Reedsport to a proposed new substation site in the hills 
    above Glasgow, Oregon. The second route would follow an existing BPA 
    transmission line from BPA's Alvey Substation south to near Roseburg, 
    Oregon, then west next to an existing BPA transmission line through 
    Fairview, and then north to the proposed substation site. A third route 
    would begin at PacifiCorp's Dixonville Substation and follow 
    PacifiCorp's transmission line west to BPA's Reston Substation, then 
    west following BPA's transmission line through Fairview, then north to 
    the proposed substation site.
        Two additional routes would parallel existing lines for part of the 
    route, but would then require new right-of-way. The first route would 
    follow an existing BPA transmission line from BPA's Alvey Substation 
    southwest to near Drain, Oregon. From near Drain, new right-of-way 
    would head southwest, cross the Umpqua River, then turn west and travel 
    to the proposed substation site above Glasgow, Oregon. The second route 
    also starts at BPA's Alvey Substation and again follows the existing 
    BPA transmission line to just south of Creswell, Oregon, then turns 
    southwest on new right-of-way. This corridor heads west to near Elkton, 
    crosses the Umpqua River, and ends at the same substation site.
        The routes cross land in Lane, Douglas, and Coos counties, Oregon. 
    A new 500-kV transmission line would be about 120 kilometers (75 miles) 
    long and would require approximately 46 meters (150 feet) of new right-
    of-way width. A new substation would need to be constructed and would 
    require about 2 hectares (5 acres). At this time, BPA believes the 
    routes using some new right-of-way may be the preferred routes to 
    study. BPA is also considering taking no action.
        BPA is mandated by the Northwest Power Act to recover its costs. 
    Each alternative will be evaluated to determine if the revenues 
    generated cover the costs of the alternative, and if the alternative is 
    consistent with sound business principles.
    
    Identification of Environmental Issues
    
        Potential issues presently identified for this proposal include: 
    (1) Effects on fish, wildlife, and vegetation, including threatened and 
    endangered species; (2) effects of economic development and 
    socioeconomic effects of building a line and substation; (3) effects of 
    construction and placement of electrical facilities in floodplains and 
    wetlands; (4) concern over visual effects, noise, and other 
    interference produced by electrical facilities in rural and populated 
    areas; (5) impacts on range, forest, and agricultural resources due to 
    construction and placement of electrical facilities; (6) concern over 
    human exposure to electric and magnetic fields created by electrical 
    facilities; (7) impacts to cultural resources; (8) impacts to 
    recreational resources; (9) conflicting land use; (10) impact to 
    property values; and (11) potential impacts to soils (erosion) and 
    water quality. Additional issues identified through the scoping process 
    may also be examined in the draft EIS.
    
        Issued in Portland, Oregon, on March 23, 1998.
    Steven G. Hickok,
    Acting Administrator and Chief Executive Officer.
    [FR Doc. 98-8375 Filed 3-30-98; 8:45 am]
    BILLING CODE 6450-01-P
    
    
    

Document Information

Published:
03/31/1998
Department:
Bonneville Power Administration
Entry Type:
Notice
Action:
Notice of intent to prepare an environmental impact statement (EIS).
Document Number:
98-8375
Dates:
Interested and affected members of the public such as landowners, special interest groups, tribes, state and local governments, utilities, and community groups are invited to help BPA and the cooperating agencies identify alternatives, environmental
Pages:
15391-15392 (2 pages)
PDF File:
98-8375.pdf