2020-06675. Double E Pipeline, LLC; Notice of Availability of the Environmental Assessment for the Proposed Double E Pipeline Project  

  • Start Preamble

    The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the Double E Pipeline Project (Project), proposed by Double E Pipeline, LLC (Double E) in the above-referenced docket. Double E filed an application in Docket No. CP19-495-000 requesting a Certificate of Public Convenience and Necessity pursuant to Section 7(c) of the Natural Gas Act to construct and operate certain natural gas pipeline facilities. Double E requests authorization to construct and operate approximately 135 combined miles of varying diameter trunk-lines and lateral pipeline connecting the Delaware Basin production areas in New Mexico and Texas to the Waha Hub. The proposed trunkline and lateral pipelines run through Eddy County, New Mexico and Loving, Ward, Reeves, and Pecos Counties, Texas.

    The EA assesses the potential environmental effects of the construction and operation of the Double E Pipeline Project in accordance with the requirements of the National Environmental Policy Act (NEPA). The FERC staff concludes that approval of the proposed Project, with appropriate mitigating measures, would not constitute a major federal action significantly affecting the quality of the human environment.

    The U.S. Department of Interior Bureau of Land Management (BLM) participated as a cooperating agency in the preparation of the EA. Cooperating agencies have jurisdiction by law or special expertise with respect to resources potentially affected by the proposal and participate in the NEPA analysis. The BLM will adopt and use the EA to issue a Right-of-Way Grant and Temporary Use Permits for the portion of the Project on federal lands.

    The proposed Double E Pipeline Project includes the following facilities:

    • Approximately 33.3 miles of new 30-inch-diameter T100 pipeline from Summit Midstream Partners, LP's existing Lane Processing Plant located in Eddy County, New Mexico, to the proposed Poker Lake Meter Station site, also in Eddy County;
    • 84.2 miles of new 42-inch-diameter T200 pipeline from the proposed Poker Lake Meter Station in Eddy County, New Mexico through Loving, Ward, and Reeves Counties, Texas and terminating at the proposed Waha Receiver and Separation site in Reeves County, Texas;
    • 1.4 miles of new 42-inch-diameter T300 pipeline from the proposed Double E Waha Receiver and Separation site in Reeves County, Texas to the final delivery locations in Pecos County, Texas; and
    • 16.4 miles of new 30-inch-diameter L100 pipeline from the existing Loving Processing Plants to the proposed T100 pipeline in Eddy County, New Mexico.

    The Commission mailed a copy of the Notice of Availability to federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American tribes; potentially affected landowners and other interested individuals and groups; and newspapers and libraries in the project area. The EA is only available in electronic format. It may be viewed and downloaded from the FERC's website (www.ferc.gov), on the Environmental Documents page (https://www.ferc.gov/​industries/​gas/​enviro/​eis.asp). In addition, the EA may be accessed by using the eLibrary link on the FERC's website. Click on the eLibrary link (https://www.ferc.gov/​docs-filing/​elibrary.asp), click on General Search, and enter the docket number in the Docket Number field, excluding the last three digits (i.e. CP19-495). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, contact (202) 502-8659.

    Any person wishing to comment on the EA may do so. Your comments should focus on the EA's disclosure and discussion of potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that the Commission has the opportunity to consider your comments prior to making its decision on this project, it is important that we receive your comments in Washington, DC on or before 5:00 p.m. Eastern Time on April 23, 2020.Start Printed Page 17870

    For your convenience, there are three methods you can use to file your comments to the Commission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208-3676 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded.

    (1) You can file your comments electronically using the eComment feature on the Commission's website (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project;

    (2) You can also file your comments electronically using the eFiling feature on the Commission's website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on eRegister. You must select the type of filing you are making. If you are filing a comment on a particular project, please select “Comment on a Filing”; or

    (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (CP19-495-000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426.

    Any person seeking to become a party to the proceeding must file a motion to intervene pursuant to Rule 214 of the Commission's Rules of Practice and Procedures (18 CFR 385.214). Motions to intervene are more fully described at http://www.ferc.gov/​resources/​guides/​how-to/​intervene.asp. Only intervenors have the right to seek rehearing or judicial review of the Commission's decision. The Commission may grant affected landowners and others with environmental concerns intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which no other party can adequately represent. Simply filing environmental comments will not give you intervenor status, but you do not need intervenor status to have your comments considered.

    Additional information about the project is available from the Commission's Office of External Affairs, at (866) 208-FERC, or on the FERC website (www.ferc.gov) using the eLibrary link. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings.

    In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/​docs-filing/​esubscription.asp.

    Start Signature

    Dated: March 24, 2020.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. 2020-06675 Filed 3-30-20; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
03/31/2020
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2020-06675
Pages:
17869-17870 (2 pages)
Docket Numbers:
Docket No. CP19-495-000
PDF File:
2020-06675.pdf